Examples of Project Construction Schedule in a sentence
Narrative report to define problem areas, anticipated delays, and impact on the Project Construction Schedule.
After Contractor and District Representative agree to a base line schedule, it will become the Project Construction Schedule.
Prepare and submit, in accordance with the approved Project Construction Schedule, a separate document listing dates by which shop drawings, product data and samples must be submitted for each material, product or equipment item requiring submittal.
Contractor shall revise the Project Construction Schedule to incorporate all activities involved in completing change orders or extra Work orders and submit it to District Representative for review.
Update Submittals: District Representative has the right to withhold progress payments if Contractor fails to update and submit the Project Construction Schedule and reports as required by District Representative.