Examples of New Services Queue in a sentence
All customers that submit an Interconnection Request, a Completed Application, or an Upgrade Request that is pending in the New Services Queue.
Each January 31, April 30, July 31, and October 31 shall be the Queue Closing Date for the New Services Queue comprised of Interconnection Requests, Completed Applications, and Upgrade Requests received during the three-month period ending on such date.
All Interconnection Requests, Completed Applications, and Upgrade Requests that are received within each three-month period ending on January 31, April 30, July 31, and October 31 of each year shall collectively comprise a New Services Queue.
An Interconnection Customer entering the New Services Queue on or after October 1, 2012 with a proposed new Customer Facility that has a Maximum Facility Output equal to or greater than 100 MW shall install and maintain, at its expense, phasor measurement units (PMUs).
A Project Developer entering the New Services Queue on or after October 1, 2012, with a proposed new Generating Facility that has a Maximum Facility Output equal to or greater than 100 MW shall install and maintain, at its expense, phasor measurement units (“PMUs”).
New Services Queue Closing Date: Each January 31, April 30, July 31, and October 31 shall be the Queue Closing Date for the New Services Queue comprised of Interconnection Requests, Completed Applications, and Upgrade Requests received during the three-month period ending on such date.
New Services Queue: All Interconnection Requests, Completed Applications, and Upgrade Requests that are received within each three-month period ending on January 31, April 30, July 31, and October 31 of each year shall collectively comprise a New Services Queue.
Interconnection Customer requests are studied as a single study for all active projects in an individual New Services Queue.
The following provision applies to Interconnection Requests which have entered the New Services Queue prior to February 1, 2011: DocuSign Envelope ID: 3CE6333E-2E42-48C4-9B8D-9F7EE0C6DD21 and the Interconnected Transmission Owner and Transmission Provider shall have the right to attend and observe, and to obtain the written results of, such testing.
In the event PJM determines that the revised Solicitation Schedule materially deviates from the Solicitation Schedule set forth in Appendix A in a manner that may adversely impact the New Services Queue, PJM and NJ BPU shall meet to agree upon a solution.