Examples of Milestone Schedule in a sentence
At a minimum, the system must include the Milestone Schedule, collaboratively created phase plans per Section 11.4.1, make-ready work plans per Section 11.4.2, and a method for measuring, recording, and improving planning reliability.
During the Validation Phase, the IPD Team, under the direction of the PMT, will prepare a Validation Study that defines the Base Program, Target Cost, and a Milestone Schedule for approval and acceptance by the Owner.
The Validation Study together with Target Value Design will define the Base Program, Target Cost, and the Milestone Schedule.
The Contract Time is the time allotted in the Milestone Schedule to achieve Project Final Completion.
Phase plans must be based on collaborative planning through direct communications by all IPD Team Members performing Work in a particular phase, who, working backwards from the most current approved Milestone Schedule, create collaborative phase schedules indicating when their portion of the Work will be completed.