Examples of Interregional Transmission Project in a sentence
Interregional Transmission Project shall mean transmission facilities that would be located within two or more neighboring transmission planning regions and are determined by each of those regions to be a more efficient or cost effective solution to regional transmission needs.
COORDINATION WITH THIRD PARTIES 12 4.1. Interconnection Requirements for Transmission Project 12 4.2. Interconnection with Affected System 13 4.3. Coordination of Interregional Transmission Project 13 ARTICLE 5.
The formula is applicable to the ISO’s share of the costs of an Interregional Transmission Project proposed as a regulated transmission solution to an identified Short Term Reliability Process Need in accordance with Section 38.4.2.5 of Attachment FF.
The ISO’s share of the cost of an Interregional Transmission Project selected pursuant to this Attachment Y to meet a Reliability Need, constraint(s) on the BPTFs identified in the Economic Planning Process, or a Public Policy Transmission Need shall be eligible for cost allocation consistent with the cost allocation methodology applicable to the type of regional transmission project that would be replaced through the construction of such Interregional Transmission Project.
The draft Public Policy Transmission Planning Report shall include a comparison of a proposed Public Policy Transmission Project to an Interregional Transmission Project proposed in the Public Policy Transmission Planning Process, if any, identified and evaluated under the “Analysis and Consideration of Interregional Transmission Projects” section of the Interregional Planning Protocol.
COORDINATION WITH THIRD PARTIES 12 4.1. Interconnection Requirements for Transmission Project 12 4.2. Interconnection with Affected System 12 4.3. Coordination of Interregional Transmission Project 12 ARTICLE 5.
An Interregional Transmission Project proposed in the ISO’s Public Policy Transmission Planning Process may be selected as a regulated Public Policy Transmission Project under the provisions of this process.
The XXXXX process shall determine whether to approve an Interregional Transmission Project, identified and evaluated under the “Analysis and Consideration of Interregional Transmission Projects” section of the Interregional Planning Protocol, if any, and proposed in the NYISO’s economic planning process, as an economic transmission project in lieu of a proposed regional economic transmission project for regulated cost allocation and recovery under the ISO Tariff.
The Economic Planning Process shall determine whether to approve an Interregional Transmission Project, identified and evaluated under the “Analysis and Consideration of Interregional Transmission Projects” section of the Interregional Planning Protocol, if any, and proposed in the ISO’s Economic Planning Process, as an economic transmission project in lieu of a proposed regional Regulated Economic Transmission Project for regulated cost allocation and recovery under the ISO Tariff.
DEVELOPER By: Name: Title: Developer is (check one): ___ Non-Incumbent Transmission Developer ___ Merchant Transmission Developer ___ Interregional Transmission Project (ITP) Proponent AVISTA CORPORATION By: Name: Title: IDAHO POWER COMPANY By: Name: Title: MATL LLP By: Name: Title: NORTHWESTERN CORPORATION By: Name: Title: PACIFICORP By: Name: Title: PORTLAND GENERAL ELECTRIC COMPANY By: Name: Title: PUGET SOUND ENERGY, INC.