Interim Milestone definition

Interim Milestone means each of the critical path milestones set forth in the Project Schedule (other than Substantial Completion and the Substantial Completion Payment Date).
Interim Milestone has the meaning ascribed thereto in subsection 15.2.
Interim Milestone shall have the meaning provided in Section 13.4 of this Agreement.

Examples of Interim Milestone in a sentence

  • The Project Schedule includes an agreed upon Design and Permit Schedule setting forth time periods for Owner to provide Drawings and Major Permits to Contractors, and an agreed upon construction schedule setting forth Interim Milestone Dates for Contractor to achieve certain construction completion milestones.

  • Contractor and Owner acknowledge that TIME IS OF THE ESSENCE with respect to their respective obligations under the Contract Documents, and that Owner’s business interests will suffer substantial losses in the event that the Project is not completed within the Interim Milestone Dates and/or the Contract Time in accordance with and subject to the terms of this Agreement.

  • Following the completion of Milestone Testing with respect to a SFINCS Interim Milestone, Vendor shall issue a report of the Milestone Test results to Vendor.

  • Design-Builder understands that if Substantial Completion or Interim Milestones and/or Substantial Completion of identified portions of the Work are not attained by the Scheduled Substantial Completion Date or applicable Interim Milestone Date, respectively), Owner will suffer damages which are difficult to specify accurately and ascertain.

  • SFINCS Interim Milestone Tests The following applies to (1) [*] and (2) [*] (each, a “SFINCS Interim Milestone”): Following Vendor’s development of a testing protocol for a SFINCS Interim Milestone, Vendor shall make such protocol available to Owner and Owner’s designee(s) for review and comment.

  • Vendor shall conduct SFINCS Interim Milestone testing (“Milestone Testing” or a “Milestone Test”) at its facilities in the State of Israel, which Milestone Testing may be monitored by Owner or its designee(s) at Owner’s request.

  • Interim Milestone – August 15, 2011 - 2012 Performance – March 3, 2013 * The above number of PSUs granted is subject to change based on the attached performance metrics set forth in the 2010 Growth Xxxxx Xxxx Term Incentive Program document, attached as Exhibit B and the terms of Form of Xxxxxx Express Corporation Long Term Incentive Program 2010 Growth Grant Performance-Based Restricted Stock Unit Award Agreement the Award Agreement.

  • The Original Project Schedule shall include an agreed upon design schedule setting forth time periods for Contractor to require Architect/Engineer to produce Drawings for the Original Project Work, time periods when Owner’s Consultants and Owner’s Contractors on the Original Project must provide their respective documents and services, and an agreed upon construction schedule setting forth the Original Project Interim Milestone Dates.

  • Contractor and Owner acknowledge that TIME IS OF THE ESSENCE with respect to their respective obligations under the Contract Documents, and that Owner’s business interests will suffer substantial losses in the event that any Interim Milestone is not achieved by the applicable Interim Milestone Date and/or Substantial Completion is not achieved by the Guaranteed Date of Substantial Completion in accordance with and subject to the terms of this Agreement.

  • The Project Schedule shall include an agreed upon Design Schedule setting forth time periods for Contractor to require Architect/Engineer to produce Drawings, time periods when Owner’s Consultants and Owner’s Contractors on the Project must provide their respective documents and services, and an agreed upon construction schedule setting forth the Interim Milestone Dates.


More Definitions of Interim Milestone

Interim Milestone means any Milestone other than a Key Milestone;
Interim Milestone means satisfaction of each of the following events: (a) no Default or Event of Default shall have occurred and be continuing; and (b) the delivery by Borrower of written notice to Agent that Xxxxxxxx has conducted an analysis of interim efficacy data from the clinical evaluation of EG-70 in the Phase 2 LEGEND clinical study (NCT04752722) in patients with BCG-nonresponsive NMIBC which supports progression of the study toward its final primary endpoint readout which, if positive, is expected to support the filing of a Biologics License Application with the FDA as the next immediate step in development, subject to Agent’s reasonable verification.

Related to Interim Milestone

  • Project Milestone means the project milestone set forth in Schedule-J;

  • Milestone means an event or task described in the Implementation Plan which must be completed by the corresponding date set out in such plan;

  • Milestones means control points in the project that help to chart progress. Milestones may correspond to the completion of a key deliverable, allowing the next phase of the work to begin. They may also be needed at intermediary points so that, if problems have arisen, corrective measures can be taken. A milestone may be a critical decision point in the project where, for example, the consortium must decide which of several technologies to adopt for further development.

  • Milestone Failure means a failure by the Grant Recipient fully to achieve any Milestone by the relevant Milestone Date;

  • Scheduled Completion Date shall be the date set forth in Clause 10.3;

  • Successful Completion means that in the reasonable opinion of the Customer, Deliverables completed by the Supplier are fit for purpose, completed on time and otherwise meet all the criteria defined under this Contract;

  • Final Completion means the date determined and certified by A/E and Owner on which the Work is fully and satisfactorily complete in accordance with the Contract.