Examples of Final Commissioning of the Development in a sentence
The consent is for a period from the date this consent is granted until the date occurring 25 years after the Final Commissioning of the Development.
Written confirmation of the date of the Final Commissioning of the Development must be provided by the Company to the Scottish Ministers, the Planning Authority, the JNCC and SNH no later than one calendar month after the Final Commissioning of the Development.
The ECoW must be appointed in time to review and approve the final draft version of the first plan or programme submitted under this consent to the Scottish Ministers for approval, until the Final Commissioning of the Development.
The operational lifespan of the Development from the Final Commissioning of the Development until the cessation of electricity generation (environmental management during decommissioning is addressed by the Decommissioning Programme provided for by condition 3).
The Company must, no later than 3 months prior to the Final Commissioning of the Development, submit an updated EMP, in writing, to cover the operation and maintenance activities for the Development to the Scottish Ministers for their written approval.
Within 2 months of the date of the Final Commissioning of the Development, an indicative scheme for the ultimate reinstatement of the site, including the removal of all wind turbines and ground reinstatement, shall be submitted for the prior written approval of the Planning Authority in consultation with SNH and SEPA.
Prior to the Commencement of the Development, a Fisheries Liaison Officer (“FLO”), approved in writing by Scottish Ministers, in consultation with the FTOWDG- CFWG, must be appointed by the Company for the period from Commencement of the Development until the Final Commissioning of the Development.
Written confirmation of the date of Final Commissioning of the Development shall be provided by the Company to the Planning Authority, National Air Traffic Services and to Scottish Ministers no later than 1 calendar month after that event.
The Company must, within 1 month of the Final Commissioning of the Development, provide co-ordinates accurate to three decimal places of minutes of arc for each WTG position and maximum heights of the WTGs to the UKHO for aviation and nautical charting purposes.