Excused Delay definition

Excused Delay means any possible extension in project implementation schedule due to any delay, intentional or unintentional, caused by USF, Force Majeure or other relevant public authorities, under the Contract. An extension in the overall implementation schedule shall be granted accordingly and the duration of such extension shall be at the discretion of USF.
Excused Delay means a delay directly caused by and attributable to Force Majeure;
Excused Delay means a delay or suspension of the construction of the Supply Chain Facility caused by (i) an act or omission of NYSERDA including, without limitation, a failure to respond or comply with any time period(s) required of such party to a written request for consent or approval; (ii) a Change in Law that results in a delay or suspension of construction of the Supply Chain Facility, if such delay or suspension cannot be overcome or avoided through commercially reasonable efforts of Grant Recipient; or (iii) actions taken by a permitting authority that affect the Supply Chain Facility but also apply to the Supply Chain Facility Activity industry as a whole.

Examples of Excused Delay in a sentence

  • Contractor fails, except in cases of Excused Delay, to make progress on the Work substantially in accordance with the Milestone Schedule.

  • Contractor fails, except in cases of Excused Delay, to commence the Work in accordance with the Milestone Schedule.

  • Contractor fails, except in cases of Excused Delay, to supply an adequate amount of properly skilled workers, materials, or equipment to complete the Work in accordance with the requirements of the Contract Documents.

  • Contractor fails, except in cases of Excused Delay, to prosecute the Work to Substantial Completion and Final Completion in a diligent, efficient, workmanlike, skillful, and careful manner in accordance with the provisions of the Contract Documents.

  • To the extent an Unexcused Delay is concurrent with an Excused Delay, the Excusable Delay shall be conclusively deemed an Unexcused Delay.


More Definitions of Excused Delay

Excused Delay means, individually or collectively, any (a) Buyer and Buyer’s Customer Delay, or (b) any delay in performance or completion of the goods or services to the extent (i) attributable to Force Majeure or (ii) addressed and resolved in a Change Order extending the Scheduled Delivery Date of the contract. However, Buyer has the right, at any time, to change the place and/or time of delivery. Any claim by Seller for adjustment because of a change in place and/or time of delivery will be deemed waived unless asserted in writing within 10 days after receipt by Seller of the request for change.
Excused Delay means the failure of Seller to achieve Commercial Operation on or before the Scheduled Commercial Operation Date, but only to the extent such failure is caused by an event of Force Majeure or an Event of Default by PacifiCorp, a default by PacifiCorp under the Generation Interconnection Agreement or related interconnection study agreement(s) for Seller’s Facility, including a default resulting from any breach by PacifiCorp of any obligation to meet a material deadline included in such agreement(s), or PacifiCorp’s violation of applicable tariff provisions governing the interconnection of Seller’s Facility; provided that the duration of any Excused Delay shall not extend to any period of delay that could have been prevented had Seller taken mitigating actions using commercially reasonable efforts.
Excused Delay. Notwithstanding anything to the contrary contained herein, if the Yard’s performance of any term or obligation is impacted by an “Excused Delay”, the Yard may extend the time for performance of its term or obligation and the Yard shall be entitled to perform such term or obligation within an appropriate time period after the expiration of the period of such delay. As used herein, an “Excused Delay” means a delay directly or indirectly caused by an Act of God, declared state of emergency or public health emergency, pandemic (specifically including COVID-19), government mandated quarantine, war, acts of terrorism, and/or order of government or civil or military authorities, fire, flood, earthquake or similar natural disasters, extreme weather events, riot, terrorism, civil strife, labor disputes or disturbances or other extraordinary events outside the control of the Yard. For the General Security of the Owner’s property, it is requested that all Owners of vessels stored inside, log in at the Office prior to entering any storage shed and log out upon leaving the shed. It is also mandatory that the NO SMOKING regulations be observed throughout the Yard. No terms or conditions herein may be changed or modified unless in writing, signed by the Parties. A 50% DEPOSIT OF ALL STORAGE FEES IS REQUIRED WITH THIS CONTRACT. THE BALANCE OF STORAGE FEES WILL BE INVOICED TO YOU UPON HAUL OF THE VESSEL. ALL INVOICES ARE DUE IMMEDIATELY UPON RECEIPT. Also, please sign 2021 Decommissioning Checklist and 2021-2022 Service Work Checklist. MYSTIC SHIPYARD WILL NOT LAUNCH ANY VESSEL UNLESS BATTERIES AND DOCKLINES ARE ON BOARD; STEERING AND ENGINE ARE OPERATIONAL; AND THE BILGE PUMP IS IN WORKING ORDER. WE ACCEPT: MASTERCARD / VISA / DISCOVER Please call the office with Credit Card information. Please do not write credit card information on this contract. I HAVE READ THE FOREGOING AND ACCEPT ALL TERMS AND CONDITIONS. Signature of Owner Date
Excused Delay means any actual delay in delivery of the Premises to Tenant caused by: (i) changes to the scope of the work requested by Tenant; (ii) any negligent act or willful misconduct or willful failure to act by Tenant or any of the Tenant Parties; (iii) Tenant's failure to furnish information or to respond to any request by Landlord for any approval of information within five (5) days of such request; (iv) Tenant's failure to approve the final drawings of the Improvements within ten (10) business days of the date hereof; (v) any breach by Tenant of its obligations under this Lease; (vi) any request by Tenant that Landlord delay the completion of any of the Improvements; or (vii) Force Majeure (as hereinafter defined).
Excused Delay means any delay caused by strike, lockout or labor trouble; civil disorder; inability to procure materials, provided that failure to order materials in a commercially reasonable and timely manner shall not be deemed to be inability to procure such materials; failure of power; restrictive governmental laws and regulations not in effect on the date the Lease is executed; riots, insurrections or war; fuel shortages; accidents; casualties; acts of God; or any other cause beyond the reasonable control of Landlord.
Excused Delay means, collectively or individually, an Amdocs Excused Delay and a Company Excused Delay, as the context so requires.