Examples of Development Cure Period in a sentence
Notwithstanding anything to the contrary, no extension shall be given under the Development Cure Period for a Force Majeure Event if the delay was due to Seller’s failure to take commercially reasonable actions to meet its requirements and deadlines or does not otherwise satisfy the requirements of a Force Majeure Event, including the notice and documentation requirements under Section 10.3.
Seller shall cause Commercial Operation for the Facility to occur by the Expected Commercial Operation Date (as such date may be extended by the Development Cure Period (defined below), the “Guaranteed Commercial Operation Date”).
In addition to extensions pursuant to a Development Cure Period, Seller may extend the Guaranteed Construction Start Date for all purposes hereunder, including Section 11.1(b)(ii), by paying Daily Delay Damages to Buyer for each day Seller desires to extend the Guaranteed Construction Start Date, not to exceed a total of one hundred twenty (120) days of extensions by such payment of Daily Delay Damages.
In addition to extensions pursuant to a Development Cure Period, Seller may extend the Guaranteed Commercial Operation Date for all purposes hereunder, including Section 11.1(b)(ii), by paying Commercial Operation Delay Damages to Buyer for each day Seller desires to extend the Guaranteed Commercial Operation Date, not to exceed a total of ninety (90) days of extensions by such payment of Commercial Operation Delay Damages.
If Seller achieves Commercial Operation on or before the Guaranteed Commercial Operation Date (not including any extensions to such date resulting from Seller’s payment of Commercial Operation Delay Damages, but as may be extended pursuant to a Development Cure Period), then Buyer shall refund to Seller all Daily Delay Damages paid by Seller and not previously refunded by Buyer.
Seller shall cause Commercial Operation for the Facility to occur by [_________] (as such date may be extended by the Development Cure Period (defined below), the “Guaranteed Commercial Operation Date”).
Seller shall cause construction to begin on the Facility by [_____________], (as such date may be extended by the Development Cure Period, the “Guaranteed Construction Start Date”).
We have limited data on the numbers of trees on Babergh land (current estimate 10,000 trees) and even less information about the trees that cover the rest of the district.
No extension shall be given under the Development Cure Period (a) if the delay was due to Seller’s failure to take commercially reasonable actions to meet its requirements and deadlines, (b) Seller does not satisfy the requirements of a Force Majeure Event, including the notice and documentation requirements under Section Error: Reference source not found.
Notwithstanding anything in this Agreement to the contrary, the cumulative extensions granted under the Development Cure Period (other than the extensions granted pursuant to clause 4(b) above) shall not exceed one hundred twenty (120) days, for any reason, including a Force Majeure Event, and no extension shall be given if the delay was the result of Seller’s failure to take all commercially reasonable actions to meet its requirements and deadlines.