Examples of Detailed Implementation Plan in a sentence
In preparation for such meetings, the current Detailed Implementation Plan shall be provided by the Service Provider to the Purchaser not less than five (5) Working Days in advance of each Implementation Meeting.
If the Purchaser rejects the draft Detailed Implementation Plan: the Purchaser shall inform the Service Provider in writing of its reasons for its rejection; and the Service Provider shall then revise the draft Detailed Implementation Plan (taking reasonable account of the Purchaser’s comments) and shall re-submit a revised draft Detailed Implementation Plan to the Purchaser for Purchaser approval within ten (10) Working Days of the date of the Purchaser’s notice of rejection.
The Service Provider shall submit a draft of the Detailed Implementation Plan to the Purchaser for approval within twenty (20) Working Days of the Commencement Date.
Following receipt of the draft Detailed Implementation Plan from the Service Provider, the Purchaser shall: review and comment on the draft Detailed Implementation Plan as soon as reasonably practicable; and notify the Service Provider in writing that it approves or rejects the draft Detailed Implementation Plan no later than ten (10) Working Days after the date on which the draft Detailed Implementation Plan is first delivered to the Purchaser.
If the Purchaser approves the draft Detailed Implementation Plan, it shall replace the Outline Implementation Plan from the date of the Purchaser’s notice of approval.