Critical Path definition

Critical Path means those Trade Contractor Work activities identified on the Construction Schedule which, if delayed, will cause a corresponding Delay in the Substantial Completion Date.
Critical Path means the sequence of activities from the start of the Work to Substantial Completion of the Project for which any delay in the completion of these activities will delay achieving Substantial Completion.
Critical Path means the path through the project schedule indicating the minimum time in which it is possible to complete the Work, and the tasks that, if delayed, will delay Substantial Completion of the Work."

Examples of Critical Path in a sentence

  • Format: Use the Critical Path Method to schedule and monitor job progress.

  • For submittals on the critical path, at the time of submission mark transmittal in red with the words "Critical Path".

  • The recommendation will include a copy of the Daily Work Report and the Work Plan - Controlling Item of Work, Form No. 700-010-15 as back-up if a Critical Path Method schedule is not a contract requirement.

  • Project Risk Management, Responsibility Sharing Matrix, Critical Chain Project Management – Critical Path vs Critical Chain, Concept of Buffers – Project buffer, resource buffer, feeding buffer.,9 Sr.No. References:Text Books Recommended:1 Narendra Singh; Project Management & Control; Himalaya Publishing House, Mumbai2 S.

  • The Contractor shall provide a Critical Path Method (CPM) schedule (“Project Schedule”) covering the duration of the Work, beginning with the receipt of the signed Agreement and concluding with Substantial Completion.


More Definitions of Critical Path

Critical Path means the activities and durations associated with the longest chain(s) of
Critical Path means the longest sequence of activities in a project plan which must be completed on time for that project to complete by the stated due date.
Critical Path. The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no total float.
Critical Path means the sequence of activities yielding the longest path in a critical path method (CPM) schedule.
Critical Path means the sequence of activities from the start of the Work to the Substantial Completion of the Project. Any delay in the completion of these activities will extend the Substantial Completion date.
Critical Path means the sequential construction tasks (each of a particular duration) that results in the least amount of time required to complete a project.
Critical Path means each path shown on the Baseline Schedule that contains the longest path from NTP to Substantial Completion for which there is zero float. It also includes paths that, due to constrained dates, contain zero float.