Authorization to Interconnect definition

Authorization to Interconnect means an official written notification provided by the Company to the Interconnecting Customer, authorizing the Interconnecting Customer to activate and operate the Facility subject to the terms of the Interconnection Service Agreement.
Authorization to Interconnect means an official written notification provided by the Company to the Interconnecting Customer, authorizing the

Examples of Authorization to Interconnect in a sentence

  • The Company shall issue the Authorization to Interconnect within 5 Business Days from the Interconnecting Customer’s satisfaction of the connection requirements (i.e. the wiring inspection, all Compliance Documentation, and the Witness Test) and the Company’s installation of the required meter, whichever occurs later.

  • If the wiring inspection, Compliance Documentation and/or Witness Test are not satisfactory, the Company has the right to disconnect the Facility, and will provide information to the Interconnecting Customer describing clearly what is required to receive the Authorization to Interconnect.

  • Assuming the wiring inspection, all Compliance Documentation and/or Witness Test are satisfactory, the Company notifies the Interconnecting Customer in writing that interconnection is authorized and issues the Authorization to Interconnect.

  • The Interconnecting Customer has no right to operate in parallel until they have received the Authorization to Interconnect.

  • Proof of Authorization to Interconnect (Projects that interconnect with the electrical grid) Host Customers and/or System Owners will be required to execute certain documents such as, but not limited to, an “Application to Interconnect a Generating Facility” and a “Generating Facility Interconnection Agreement” with the local Electric Utility.

  • The Interconnecting Customer has no right to operate in parallel until it has received the Authorization to Interconnect.

  • Authorization to Interconnect will be provided once the Interconnecting Customer has met all terms of the interconnection process as outlined below.

  • In addition, the Interconnecting Customer will be required to have a load monitoring system in place to prevent the 1/15th minimum load from being exceeded pursuant to Section 6.3 and to provide annual test results of the system pursuant to Section 6.4.3.The Interconnecting Customer has no right to operate in parallel until they have received the Authorization to Interconnect.

  • For facilities located in Rhode Island, a copy of National Grid’s Authorization to Interconnect letter would also be sufficient.

  • If the Witness Test is not satisfactory, the Company has the right to disconnect the Facility, and will provide information to the Interconnecting Customer describing clearly what is required to receive the Authorization to Interconnect.

Related to Authorization to Interconnect

  • Service Authorization means that Open Ecosystem Partner needs to meet specific qualification requirements for the products included in a “Service” Product Family that Open Ecosystem Partner wants to promote and offer Services for as set out in detail in the Open Ecosystem Program Guide.

  • Generation Interconnection Agreement means the generation interconnection agreement to be entered into separately between Seller and PGE, providing for the construction, operation, and maintenance of interconnection facilities required to accommodate deliveries of Seller's Net Output.

  • Authorization Letter means a letter agreement executed by Borrower in the form of EXHIBIT A.

  • cogeneration means the simultaneous generation in one process of thermal energy and electrical or mechanical energy;

  • Interconnection Agreement means the interconnection agreement entered into by Seller pursuant to which the Facility will be interconnected with the Transmission System, and pursuant to which Seller’s Interconnection Facilities and any other Interconnection Facilities will be constructed, operated and maintained during the Contract Term.

  • Authorization Form means a form specified in s. 440.73.

  • Service Authorization Request means a Provider’s or Enrollee’s request to the Contractor for the provision of a service.

  • General air quality operating permit or "general permit" means an air quality operating permit that meets the requirements of ARM 17.8.1222, covers multiple sources in a source category, and is issued in lieu of individual permits being issued to each source.

  • Prior authorization means that we must approve the Services in advance in order for the Services to be covered.

  • Interconnection Service Agreement means an agreement among the Transmission Provider, an Interconnection Customer and an Interconnected Transmission Owner regarding interconnection under Tariff, Part IV and Tariff, Part VI. List of Approved Contractors: