WORK SEQUENCE Sample Clauses

WORK SEQUENCE. Contractor shall be responsible for the work, means, methods, sequence and scheduling of all work to complete the project.
AutoNDA by SimpleDocs
WORK SEQUENCE. The work of laying or jacking of the distribution pipeline or casing pipe beneath the railway tracks, including construction of the RCC xxxxxxxx, shall be undertaken prior to installation of the distribution mains on either side of the railway in the vicinity of the railway crossing. All work shall be carried out under the supervision of the representative from the Railway Authority and Employer’s Representative. Technical Specifications Subsection 6Road Works
WORK SEQUENCE a) MPS will occupy the premises during entire period of construction for the conduct of normal operations. The Contractors must fully cooperate with MPS’ personnel to minimize conflict, and to facilitate the building's operations.
WORK SEQUENCE. A. Construct Work in stages to accommodate the CITY’s use of premises during construction period and in accordance with the limitations on the sequence of construction specified. Coordinate construction schedules and operations with CONSULTANT.
WORK SEQUENCE. The Contractor shall schedule the work to minimize inconvenience to the City and to adjacent property owners and to minimize interruptions to utility service. This shall include minimizing obstruction to local traffic especially on dead end streets. Work shall be scheduled so as to minimize disruptions to local mail delivery.
WORK SEQUENCE. A. This project includes the installation of a continuous FM through the Oak Grove subdivision that will connect to an existing 10” FM. The contractor shall anticipate timing and sequence of the new FM to ensure the least amount of disruption to the existing residence.
WORK SEQUENCE. A. Contractor shall submit a schedule with monthly updates outlining the start and completion of major tasks.
AutoNDA by SimpleDocs
WORK SEQUENCE. A. Sequencing of Work is specific to each Task Order and shall be coordinated with the City’s Public Works Department at the initiation of each Task Order Agreement. A schedule for each Task Order shall be submitted to and approved by the City prior to commencing work.
WORK SEQUENCE. A. The Project has work sequencing requirements to ensure that critical facility operations remain in effect during construction activities. Work sequencing requirements are detailed on the drawings.
WORK SEQUENCE. The MCC replacement project will be initiated before the SWITCHGEAR replacement project. The SWITCHGEAR replacement project shall begin following completion of the MCC replacement project. Coordinate Work of all Sub-CONTRACTORs.