Common use of WORK PROGRAMME Clause in Contracts

WORK PROGRAMME. The Contractor shall submit to the Engineer a work programme showing how he proposes to carry out the Works by the intended Completion Date. The programme shall show the start and completion dates of the various activities, in order to complete the entire project by the Intended Completion Date. The Contractor will not start any activity, or part thereof, until and unless the Engineer has given his written approval. The Contractor shall submit a written request at least 48 hrs before concrete pour. If the Contractor falls behind the Contractual Programme he shall, within 14 days of the date of such default, submit for approval a revision of the programme showing the proposed measures, including plant, labour and material resources, to complete the Permanent Works on time.

Appears in 4 contracts

Samples: www.fao.org, www.fao.org, www.fao.org

AutoNDA by SimpleDocs
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!