Utility Locates Sample Clauses

Utility Locates. Contractor will be responsible to locate existing utilities and underground facilities that are indicated in the Contract Documents or that are known or reasonably should be known to exist in proximity to the Work. Contractor shall provide timely notice and locate requests with any affected utility or through contact with appropriate notification centers before commencing excavation or demolition Work that Contractor knows or reasonably should know is in proximity to such utilities or facilities. Contractor assumes the sole risk and will be responsible for all delay and expense arising out of Contractor’s failure to do so.
AutoNDA by SimpleDocs
Utility Locates. CP: CP Call-Before-You-Dig 0-000-000-0000: Must be called no less than 5 Working Days (excludes Saturday, Sunday and holidays observed by CP) prior to date on that Work is to be performed.
Utility Locates. CM/GC will be responsible to locate existing utilities and underground facilities that are indicated in the Contract Documents or that are known or reasonably should be known to exist in the proximity to the Work. CM/GC shall provide timely notice and locate requests with any affected utility or through contact with appropriate notification centers before commencing excavation or demolition Work that CM/GC knows, or reasonably should know, is in proximity to such utilities or facilities. CM/GC assumes the sole risk and will be responsible for all delay and expense arising out of CM/GC’s failure to do so.
Utility Locates. R&E and/or NWS shall call the state “dial-before-you-dig” contractor number to determine utility locations prior to the design survey. However, “dial-before-you-dig” locators do not check utilities outside of the public right of way, and in some cases do not perform locates for design purposes or in a timely manner. R&E will contract with a private locating company for utility locates outside of the public right of way and for utilities not located for design purposes.
Utility Locates. Xxxxx Inc is not responsible for determining and marking the location of any underground pipes, wires, conduits, cables, or structures such as gas lines, fiber optics, irrigation or septic systems or any other items which may exist below the surface of the ground.
Utility Locates. 13.1 Contractors completing any excavation work are required by law to notify Iowa One Call (000-000-0000 or 811) for locates of utilities at least 48 hours prior to ALL excavations (not including weekends and holidays). No excavation work can commence until after this 48 hour time-period commencing with the issuance of a locate request or dig number from Iowa One Call has transpired.
Utility Locates. Contact Utility Notification Center of Colorado at or 8-1-1 or 1-800-922- 1987 prior to any excavation, for the marking of underground member utilities. The indication of utilities on the Drawings does not relieve the Service Provider of the responsibility for utility location. Service Provider is responsible for potholing all utility locations to verify the depth and locations. Potholing related to irrigation installation shall be considered incidental to irrigation installation and will not be paid separately. Route trenches to avoid existing utilities. Verify with the Project Manager any required relocation prior to installation. Repair any underground utilities damaged during construction. Make repairs at no additional cost to the contract price.
AutoNDA by SimpleDocs
Utility Locates. Prior to site activities, the Indiana Underground Plant Protection Services (IUPPS) will be utilized to locate public utility lines in the vicinity of the site. Locates will be requested from IUPPS a minimum of 48 hours prior to commencement of field investigations. IUPPS will not identify private utilities that service the site, buried storage tanks, or other subsurface appurtenances that may be present. Therefore, a private utility locate service will be included as part of this scope. Identified subsurface utility lines will be included on a site plan for inclusion in the Phase II report deliverable.
Utility Locates. This work will be done by a subcontractor. Utility Locates < 10-ft depth will be performed by a firm registered to perform utility locates at the PBWTP and JKWTP applicable to the proposed areas of construction for this Project. A maximum of 5 days (total) of utility locates are assumed for the two sites.
Utility Locates. Two (2) business days. If the Contractorfails to respond within the specified times, theCounty may charge for non-performance as set forth in Part 3 of this contract. The County may exercise the option to enlist the services of another contractor to complete necessary repairs. TheContractor will be charged the cost incurred plus an administrative fee of 10%. The Program Managershall approve all response maintenance calls during weekday hours. It is theContractor's responsibility to acquire the required Program Manager's approval before proceeding to work. Response times for afte-rhours service calls (1631 hours- 0759 hours) and weekends/holidays shall be reviewed and initiated by theContractor's Level II Traffic Signal Technician who shall be responsible to respond within two hours unless an exception is present. (See below.) The Contractor shall provide the Program Managerwith daily report by close of business the following business day of all afte-rhour services. The following are typical applications for response times: Two-Hour Response Time: