Common use of Utility Adjustment Risk Clause in Contracts

Utility Adjustment Risk. 21 5.10.4.1 Except with respect to Developer’s rights to claim a Relief 22 Event for Utility Company Delays pursuant to Section 14.4.4, for Inaccurate Utility 23 Information pursuant to Section 14.4.5, or for ADOT-Caused Delay respecting ADOT 24 Utility Adjustments, Developer shall not be entitled to submit a Claim for Extra Work 25 Costs, Delay Costs, Completion Deadline adjustment or other relief related to the Utility 26 Adjustment Work, inaccuracy of the Utility Information or Utilities located within or 27 outside the Project ROW or otherwise impacted by, or having an impact on, the Project 28 or the Work.

Appears in 2 contracts

Samples: apps.azdot.gov, apps.azdot.gov

AutoNDA by SimpleDocs

Utility Adjustment Risk. 21 5.10.4.1 Except with respect to Developer’s rights to claim a Relief 22 Event for Utility Company Delays pursuant to Section 14.4.4, for Inaccurate Utility 23 Information pursuant to Section 14.4.5, or for ADOT-Caused Delay respecting ADOT 24 Utility Adjustments, Developer shall not be entitled to submit a Claim for Extra Work 25 Costs, Delay Costs, Completion Deadline adjustment or other relief related to the Utility 26 Adjustment Work, inaccuracy of the Utility Information or Utilities located within or 27 outside the Project ROW or otherwise impacted by, or having an impact on, the Project 28 or the Work.

Appears in 1 contract

Samples: Design Build Maintain Agreement

Utility Adjustment Risk. 21 14 5.10.4.1 Except with respect to Developer’s rights to claim a Relief 22 15 Event for Utility Company Delays pursuant to Section 14.4.4, for Inaccurate Utility 23 16 Information pursuant to Section 14.4.5, or for ADOT-Caused Delay respecting ADOT 24 17 Utility Adjustments, Developer shall not be entitled to submit a Claim for Extra Work 25 18 Costs, Delay Costs, Completion Deadline adjustment or other relief related to the Utility 26 19 Adjustment Work, inaccuracy of the Utility Information or Utilities located within or 27 outside 20 the Project ROW or otherwise impacted by, or having an impact on, the Project 28 or the Work.the

Appears in 1 contract

Samples: apps.azdot.gov

Utility Adjustment Risk. 21 27 5.10.4.1 Except with respect to Developer’s rights to claim a Relief 22 28 Event for Utility Company Delays pursuant to Section 14.4.4, for Inaccurate Utility 23 29 Information pursuant to Section 14.4.5, or for ADOT-Caused Delay respecting ADOT 24 30 Utility Adjustments, Developer shall not be entitled to submit a Claim for Extra Work 25 31 Costs, Delay Costs, Completion Deadline adjustment or other relief related to the Utility 26 32 Adjustment Work, inaccuracy of the Utility Information or Utilities located within or 27 outside 33 the Project ROW or otherwise impacted by, or having an impact on, the Project 28 or the Work.the

Appears in 1 contract

Samples: azdot.gov

AutoNDA by SimpleDocs

Utility Adjustment Risk. 21 24 5.10.4.1 Except with respect to Developer’s rights to claim a Relief 22 25 Event for Utility Company Delays pursuant to Section 14.4.4, for Inaccurate Utility 23 26 Information pursuant to Section 14.4.5, or for ADOT-Caused Delay respecting ADOT 24 27 Utility Adjustments, Developer shall not be entitled to submit a Claim for Extra Work 25 28 Costs, Delay Costs, Completion Deadline adjustment or other relief related to the Utility 26 29 Adjustment Work, inaccuracy of the Utility Information or Utilities located within or 27 30 outside the Project ROW or otherwise impacted by, or having an impact on, the Project 28 31 or the Work.

Appears in 1 contract

Samples: apps.azdot.gov

Time is Money Join Law Insider Premium to draft better contracts faster.