Unit Price Changes Sample Clauses

Unit Price Changes. If a change is ordered in an item of work covered by a Contract Unit Price, and such change does not involve substantial change in character of the work from that shown on the Plans or Special Provisions, then an adjustment in payment will be made. This adjustment will be based upon the increase or decrease in quantity and the Contract Unit Price. If the actual quantity of an item of work covered by a Contract Unit Price and constructed in conformance with the Plans and Special Provisions varies from the Bid quantity by 25% or less, payment will be made at the Contract Unit Price. If the actual quantity of the item of work varies from the Bid quantity by more than 25%, then payment will be made as described in Subsection (a) “Increases of More than 25%,” or Subsection (b) “Decreases of More than 25%,” below, as appropriate. If a change is ordered in an item of work covered by a Contract Unit Price, and such change involves a substantial change in the character of the work from that shown on the Plans or Special Provisions, an adjustment in payment will be made as described in Subsection (c) “Substantial Change in Character of the Work,” below.
AutoNDA by SimpleDocs
Unit Price Changes. Unit price Change Orders shall be based on the unit prices identified in the Contractor's bid, which include the Contractor's overhead and profit for the Work performed on the unit price basis. The above-mentioned percentages shall not be applied to unit price changes.
Unit Price Changes. If a change is ordered in an item of work covered by a Contract Unit Price, and such change does not involve substantial change in character of the work from that shown on the Plans or Special Provisions, then an adjustment in payment will be made. This adjustment will be based upon the increase or decrease in quantity and the Contract Unit Price. If the actual quantity of an item of work covered by a Contract Unit Price and constructed in conformance with the Plans and Special Provisions varies from the Bid quantity by 25% or less, payment will be made at the Contract Unit Price. If the actual quantity of the item of work varies from the Bid quantity by more an item of work covered by a Contract Unit Price, and such change involves a substantial change in the character of the work from that shown on the Plans or Special Provisions, an adjustment in
Unit Price Changes. Except for unit prices included in the GMP Amendment, for proposed changes in the Work performed on a unit price basis, Construction Manager shall submit an itemized list of quantities with the applicable unit cost and extended price for each, in such form and detail as reasonably required by Owner. The accepted unit prices shall include all subcontractors’ overhead/ profit and shall be applied for both additive and deductive Change Orders.

Related to Unit Price Changes

  • Price Changes Our storage charges will be as quoted to You for the first 26 weeks of storage. After 26 weeks, We may change the storage charges from time to time on giving 28 days’ written notice to You.

  • Unit Prices If unit prices are stated in the Contract Documents or subsequently agreed upon, and if the quantities originally contemplated are so changed in a Change Order that application of the agreed unit prices to the quantities of work proposed will cause substantial inequity to the Owner or the Contractor, the applicable unit prices shall be equitably adjusted as provided in the Special Conditions or as agreed to by the parties and incorporated into the Change Order.

  • Unit Price Unless the bidder clearly indicates that the price is based on consideration of being awarded the entire lot and that an adjustment to the price was made based on receiving the entire bid, any difference between the unit price correctly extended and the total price shown for all items shall be offered shall be resolved in favor of the unit price.

  • Unit Price Work Work to be paid for on the basis of unit prices as defined and described in the Contract Documents. A percentage markup for overhead or profit shall be included in all unit prices.

  • Contract Price Adjustment The basis upon which the Contract Price shall be adjusted is as set out in paragraph 9.2 of Schedule IVB.

  • Service Changes PBI may modify its Service by giving written notice to you (a “Service Change Notice”), which will state whether the change is material. After receiving a Service Change Notice, if the change is material, you may terminate Service by giving us a termination notice at the address indicated in Section 21 or you may create a case at xxxxxxxxxxx.xxx/xx/xxxxxxx-xx.xxxx (follow the instructions under “how to create a case”).

  • ECONOMIC PRICE ADJUSTMENT is the adjustment to the Aircraft Basic Price (Base Airframe, Engine and Special Features) as calculated pursuant to Exhibit D.

  • Non pre-priced Adjustment Factor To be applied to Work deemed not to be included in the CTC but within the general scope of the work:

  • Price Increases This section applies to pricing not Benchmarked to GSA Supply Schedule. Additionally, where pricing submitted for Services is not benchmarked to an approved GSA Supply Schedule:

  • CONTRACT PRICE/PRICE LIMITATION/ PAYMENT 5.1 The contract price, method of payment, and terms of payment are identified and more particularly described in EXHIBIT C which is incorporated herein by reference.