Trip Schedule Sample Clauses

Trip Schedule. Full loads on B trains and two containers will be paid 100% for the first can and 50 % on the second loaded can. The following exceptions apply: B Trains & Combo Chassis (Full) 1st Can 2nd Can 3rd Can Same Location Different Location Empty Triple set 3 at same location 2 at one and 1 other location 3 at 3 diff. locations 100% 50% N/A 100% 100% N/A 100% 50% Free 100% 100% Free 100% 100% 100% Two Empty 1st Can 2nd Can 2 at same location 100% Free 2 at different locations 100% 50% A Trains- A Train Cans shall be paid at 100% for each Can Waiting Time- 1st hour free; $45.00 per hour, effective January 1, 2006 and, $50.00 per hour effective January 1, 2007; to be paid in 15 minute increments. (At Customers Location) (It will be a requirement of the Owner Operator to present a xxxx of lading identifying time in and time out that as the customer signature) Dead Calls- All Dead Calls shall be paid at $50.00 each unless a recovery trip can be assigned within 2 kilometres and within 15 minutes of arrival at the Dead Call. Scale Fee- Any time a customer requires an Owner Operator to scale a load, that Driver shall be paid an additional $50.00 Compensation - Owner Operators
AutoNDA by SimpleDocs

Related to Trip Schedule

  • RDO Schedule a) The Schedule of RDO’s to be observed each year will generally be as provided under the VBIA.

  • Shift Schedule The words "shift schedule" when used in this Agreement shall mean a timetable of the shifts and off days assigned to a position or group of positions which commences at the beginning of a pay period and includes one complete rotation of said shifts.

  • Master Schedule At the start of the schematic design phase, the Construction Administrator will be given a copy of the updated DAS initial schedule as described in the pre-design phase. The Construction Administrator will then create its master schedule based on the DAS’ initial schedule. Utilizing CPM-based software, the Construction Administrator will assign a duration and relationship to each task, add or delete tasks, identify the logic of interrelationships and milestones, and perform schedule management activities to identify the project's critical path and timeline. The master schedule shall include all tasks from the pre-design phase through design, construction, and project closeout. Items to be identified during subsequent refinements include milestones for departmental occupancy, shop drawing and Construction Administrator reviews, special support services, mobilization and demobilization, long lead item purchases, and float times.

  • Schedule The Work shall be performed as expeditiously as possible in conformity with the schedule requirements contained herein and in the Statement of Work. The draft and final versions of all deliverables shall be submitted by the dates specified in the Exhibit A Schedule and Project Period noted in Item No. 7 of this Agreement. It is understood and agreed that the delivery of the draft and final versions of such deliverables by the Contractor shall occur in a timely manner and in accordance with the requirements of the Exhibit A Schedule.

  • Daily Schedule 1. Double Bus Runs - Teachers shall be required to be on duty a total of seventy-five (75) minutes in grades K-6 and sixty (60) minutes in grades 7-12 before and after the published regular pupil's school day.

  • Fourth Schedule All petroleum as defined in the Xxxxxxxxx Xxx 0000 on or below the surface of the land the subject of this lease is reserved to the Crown in right of the State of Western Australia with the right of the Crown in right of the State of Western Australia and any person lawfully claiming thereunder or otherwise authorised to do so to have access to the land the subject of this lease for the purpose of searching for and for the operations of obtaining petroleum (as so defined) in any part of the land. FIFTH SCHEDULE (Date of commencement of the lease). SIXTH SCHEDULE (Any further conditions or stipulations).

  • Recovery Schedule If the initial schedule or any current updates fail to reflect the Work’s actual plan or method of operation, or a contractual milestone date is more than fifteen (15) days behind, Owner may require that a recovery schedule for completion of the remaining Work be submitted. The Recovery Schedule must be submitted within seven (7) calendar days of Owner’s request. The Recovery Schedule shall describe in detail Construction Contractor’s plan to complete the remaining Work by the required Contract milestone date. The Recovery Schedule submitted shall meet the same requirements as the original Construction Schedule. The narrative submitted with the Recovery Schedule should describe in detail all changes that have been made to meet the Contract milestone dates.

  • Time Schedule 4.1. A project schedule is included in Appendix A.

  • Wage Schedule ‌ The pay rate (including increments and stated extras) as agreed to and hereinafter in this Schedule provided, shall be in effect during the term of the Agreement, from April 1, 2019 to March 31, 2022.

  • PROGRESS SCHEDULE The Contractor, within ten (10) working days of receiving notice of the award of the contract, shall prepare and submit for the State's and Architect's information an estimated progress schedule for the Work. The progress schedule shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.