Time and Materials Change Orders Sample Clauses

Time and Materials Change Orders. TxDOT may at its discretion issue a Time and Materials Change Order whenever TxDOT determines that a Time and Materials Change Order is advisable. The Time and Materials Change Order shall instruct DB Contractor to perform the identified additional (or modified) Maintenance Services, indicating expressly the intention to treat the items as changes in the Maintenance Services, and setting forth the kind, character, and limits of the Maintenance Services as far as they can be ascertained, the terms under which changes to the Maintenance Price will be determined, and the estimated total change in the Maintenance Price anticipated thereunder. Upon final determination of the allowable costs, TxDOT shall issue a modified Change Order setting forth the final adjustment to the Maintenance Price.
AutoNDA by SimpleDocs
Time and Materials Change Orders. For a time-and-materials change, Owner shall determine the adjustment to the Contract Price on the basis of actual costs as follows:
Time and Materials Change Orders. For a time-and-materials change, County shall determine the adjustment to the Contract Price on the basis of actual costs as follows:
Time and Materials Change Orders. Owner may unilaterally, and in its sole discretion, issue a Change Order that is based on time and material costs, as described in this Article 14.13 (a “Time and Materials Change Order”) whenever Owner determines such a Change Order is advisable. In the event that payment for Work performed pursuant to an Owner-Directed Change is the basis of a dispute as provided in Article 14.10, such payment may be made pursuant to a Time and Materials Change Order pending formal resolution of the dispute under the “Claims” clause (Article 29). The Time and Materials Change Order shall instruct Contractor to perform the Work, indicating expressly the intention to treat the items as changes in the Work, and setting forth the kind, character, and limits of the Work as far as they can be ascertained, the terms under which changes to the Contract Amount will be determined and the estimated total change in the Contract Amount anticipated thereunder. Upon final determination of the allowable costs, Owner shall issue a modified Change Order setting forth the final adjustment to the Contract Amount. The following costs and xxxx-ups (and no others) shall be used for calculating the change in the Contract Amount. No direct compensation will be allowed for other miscellaneous costs for which no specific allowance is provided in this Article 14.13.
Time and Materials Change Orders a. The term Time and Materials means the sum of all costs reasonably and necessarily incurred and paid by Contractor for labor, materials, and equipment in the proper performance of Additional Work. Except as otherwise may be agreed to in writing by MTS, such costs shall be in amounts no higher than those prevailing in the locality of the Project, and shall include only the following items.
Time and Materials Change Orders. ‌ Authority may unilaterally, and in its sole discretion, issue a Change Order that is based on time and material costs, as described in this Article 16.16 (a “Time and Materials Change Order”) whenever Authority determines such a Change Order is advisable. In the event that payment for Work performed pursuant to an Authority- Directed Change is the basis of a dispute as provided in Article 16.13, such payment may be made pursuant to a Time and Materials Change Order pending formal resolution of the dispute under Article 32. The Time and Materials Change Order shall instruct Contractor to perform the Work, indicating expressly the intention to treat the items as changes in the Work, and setting forth the kind, character, and limits of the Work as far as they can be ascertained, the terms under which changes to the Contract Amount will be determined and the estimated total change in the Contract Amount anticipated thereunder. Upon final determination of the allowable costs, Authority shall issue a modified Change Order setting forth the final adjustment to the Contract Amount. The following costs and xxxx-ups (and no others) shall be used for calculating the change in the Contract Amount. No direct compensation will be allowed for other miscellaneous costs for which no specific allowance is provided in this Article 16.16.
Time and Materials Change Orders. The Agency may direct the Contractor to proceed with the Additional Work with payment to be made on the basis of actual cost of the labor and materials required to complete the Additional Work. If the Project is federally funded, a time and materials Change Order shall only be issued after a determination that no other Change Order is suitable and the Change Order shall include a ceiling price that the Contractor exceeds at its own risk.
AutoNDA by SimpleDocs

Related to Time and Materials Change Orders

  • Change Orders Any alteration or deviation from the Services mentioned or any other contractual specifications that result in a revision of this Agreement shall be executed and attached to this Agreement as a change order (“Change Order”).

  • Work Order (s) means a detailed scope of work for a Service required by Transnet, including timeframes, Deliverable, Fees and costs for the supply of the Service to Transnet, which may be appended to this Agreement from time to time.

  • Change Order (5) The Change Order is then submitted to the Project Manager who immediately processes the CO with OPC as required by Bulletin 3.5 and BGS’ Contracting Plan.

Time is Money Join Law Insider Premium to draft better contracts faster.