Synchronisation Commissioning and Commercial Operation Sample Clauses

Synchronisation Commissioning and Commercial Operation. 8.1 The Developer shall provide at least sixty (60) days advanced preliminary written notice and at least thirty (30) days advanced final written notice to ESCOM of the date on which it intends to synchronize the Power Project to the Grid System.
AutoNDA by SimpleDocs
Synchronisation Commissioning and Commercial Operation. 8.1 The Solar Power Developer shall provide at least forty (40) days advanced preliminary written notice and at least twenty (20) days advanced final written notice to ESCOM of the date on which it intends to synchronize the Power Project to the Grid System.
Synchronisation Commissioning and Commercial Operation. 5.1.1 The SPP shall give the concerned UPLDC / SLDC and Procurer and UPNEDA at least sixty (60) days advanced preliminary written notice and at least thirty (30) days advanced final written notice, of the date on which it intends to synchronise the Power Project to the Grid System.
Synchronisation Commissioning and Commercial Operation. ‌ Synchronisation, Commissioning and Commercial Operation‌ The SPD shall give the concerned SLDC and MePDCL at least sixty (60) days advanced preliminary written notice and at least thirty (30) days advanced final written notice, of the date on which it intends to synchronize the Power Project to the Grid System. Subject to Article 5.1.1, the Power Project may be synchronized by the SPD to the Grid System when it meets all the connection conditions prescribed in Meghalaya Grid Code then in effect and otherwise meets all other Indian/ State legal requirements for synchronization to the Grid System. The synchronization equipment shall be installed by the SPD at its generation facility of the Power Project at its own cost. The SPD shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned sub-station/ Grid System of MePDCL and checking/ verification is made by the concerned Transco and Discoms Authorities of the Grid System. The SPD shall immediately after each synchronization /tripping of generator, inform the sub- station of the Grid System to which the Power Project is electrically connected in accordance with State Grid Code. The SPD shall commission the project within 15 months for MW power plant.
Synchronisation Commissioning and Commercial Operation. 8.1 The SPG shall provide at least thirty (30) days advance preliminary written notice and at least fifteen (15) days advance final written notice to ESCOM of the date on which it intends to synchronize the Power Project to the Grid System.
Synchronisation Commissioning and Commercial Operation. 4.1Synchronization The Power Producer shall give the concerned Discom, Nodal Agency and Procurer at least [insert number of days in words] (XX) Days advanced preliminary written notice and at least [insert number of days in words] (XX) Days advanced final written notice, of the date on which it intends to synchronize the Project. Subject to Article 4.1.1, the Project may be synchronized by the Power Producer when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid. Prior to synchronization of the Project, the Power Producer shall be required to get the Project certified for the requisite acceptance/ performance test as may be laid down by Central Electricity Authority or an agency identified by the central government / state government to carry out testing and certification for the solar rooftop projects. The synchronization equipment shall be installed by the Power Producer at its generation facility of the Project at its own cost. The Power Producer shall synchronize its system with the utility system only after the approval of synchronization scheme is granted by the concerned Discom and checking/verification is made by the concerned authorities of the Discom.
Synchronisation Commissioning and Commercial Operation. 5.1 Synchronization, Commissioning and Commercial Operation
AutoNDA by SimpleDocs
Synchronisation Commissioning and Commercial Operation. 5.1.1 The SPD shall give the concerned RLDC/SLDC and NVVN at least sixty (60) days advanced preliminary written notice and atleast thirty (30) days advanced final written notice, of the date on which it intends to synchronise the Power Project to the Grid System.
Synchronisation Commissioning and Commercial Operation 

Related to Synchronisation Commissioning and Commercial Operation

  • Synchronization, Commissioning and Commercial Operation 4.1.1 The Power Producer shall give at least thirty (30) days written notice to the SLDC and GUVNL, of the date on which it intends to synchronize the Power Project to the Grid System.

  • Commercial Operation (i) On or before December 31, 2021, Interconnection Customer must demonstrate commercial operation of all generating units. Demonstrating commercial operation includes achieving Initial Operation in accordance with Section 1.4 of Appendix 2 to this ISA and making commercial sales or use of energy, as well as, if applicable, obtaining capacity qualification in accordance with the requirements of the Reliability Assurance Agreement Among Load Serving Entities in the PJM Region.