Suspension of unsafe Construction Works. 13.5.1 Upon recommendation of the Supervision Committee to this effect, the Authority may by notice require the Concessionaire to suspend forthwith the whole or any part of the Construction Works if, in the reasonable opinion of the Authority, such work threatens the ecology of the Project Site or its surrounding areas, local habitat, flora &fauna.

Appears in 2 contracts

Samples: Iii Concession Agreement, Concession Agreement

AutoNDA by SimpleDocs

Suspension of unsafe Construction Works. 13.5.1 13.3.1 Upon recommendation of the Supervision Committee to Independent Expert on any error or defect of a technical nature in the designs and Drawing without rectification of which the Project cannot be carried out as per this effectAgreement, the Authority may by notice require the Concessionaire to suspend forthwith the whole or any part of the Construction Works if, in the reasonable opinion of the Authority, such work threatens the ecology safety of any equipment, maintenance or any individual on or about the Project Site or its surrounding areasProject. Provided, local habitathowever, flora &faunathat in case of an emergency, the Authority may suo moto issue the notice referred to hereinabove.

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

Suspension of unsafe Construction Works. 13.5.1 13.14.1 Upon recommendation of the Supervision Committee Independent Engineer to this effect, the Authority may by notice require the Concessionaire to suspend forthwith the whole or any part of the Construction Works if, in the reasonable opinion of the Authority, such work threatens the ecology safety of the Project Site Users or its surrounding areasthe localities adjacent to the Service Area. Provided, local habitathowever, flora &faunathat in case of an emergency, the Authority may suo moto issue the notice referred to hereinabove.

Appears in 2 contracts

Samples: Escrow Agreement, Draft Concession Agreement

Suspension of unsafe Construction Works. 13.5.1 13.5.1. Upon recommendation of the Supervision Committee Independent Engineer to this effect, the Authority may by notice require the Concessionaire to suspend forthwith the whole or any part of the Construction Works if, in the reasonable opinion of the Authority, such work threatens the ecology safety of the Project Site Users or its surrounding areasany other person on or about the Airport. Provided, local habitathowever, flora &faunathat in case of an emergency, the Authority may suo moto issue the notice referred to hereinabove.

Appears in 1 contract

Samples: Concession Agreement

Suspension of unsafe Construction Works. 13.5.1 Upon recommendation of the Supervision Committee Independent Expert to this effect, the Authority may by notice require the Concessionaire to suspend forthwith the whole or any part of the Construction Works if, in the reasonable opinion of the Authority, such work threatens the ecology safety of any person or property. Provided, however, that in case of an emergency, the Project Site or its surrounding areas, local habitat, flora &faunaAuthority may suo moto issue the notice referred to hereinabove.

Appears in 1 contract

Samples: fci.gov.in

AutoNDA by SimpleDocs

Suspension of unsafe Construction Works. 13.5.1 Upon recommendation of the Supervision Committee to Independent Expert on any error or defect of a technical nature in the designs and Drawing without rectification of which the Project cannot be carried out as per this effectAgreement, the Authority may by notice require the Concessionaire to suspend forthwith the whole or any part of the Construction Works if, in the reasonable opinion of the Authority, such work threatens the ecology safety of any equipment, maintenance or any individual on or about the Project Site or its surrounding areasProject. Provided, local habitathowever, flora &faunathat in case of an emergency, the Authority may suo moto issue the notice referred to hereinabove.

Appears in 1 contract

Samples: Concession Agreement

Suspension of unsafe Construction Works. 13.5.1 Upon recommendation of the Supervision Committee Independent Expert to this effect, the Authority may by notice require the Concessionaire to suspend forthwith the whole or any part of the Construction Works if, in the reasonable opinion of the Authority, such work threatens the ecology safety of any equipment, maintenance or any individual on or about the Project Site or its surrounding areasProject. Provided, local habitathowever, flora &faunathat in case of an emergency, the Authority may suo moto issue the notice referred to hereinabove.

Appears in 1 contract

Samples: niti.gov.in

Time is Money Join Law Insider Premium to draft better contracts faster.