Suspension by Contractor Sample Clauses

Suspension by Contractor. The Contractor may order the Subcontractor in writing to suspend, delay or interrupt all or any part of the Subcontract Work for such period of time as may be determined to be appropriate for the convenience of the Contractor. Subcontract Work when required to be phased or interrupted shall not be deemed a suspension.
AutoNDA by SimpleDocs
Suspension by Contractor. Notwithstanding anything to the contrary in this Agreement, Contractor shall have the responsibility at all times to prosecute the Work diligently and shall not suspend, stop or cease performance hereunder or permit the prosecution of the Work to be delayed; provided, however, subject to Owner’s right to withhold or offset payment to Contractor under this Agreement, if Owner fails to pay undisputed amounts due and owing to Contractor and Owner has failed to cure such failure within thirty (30) Days following Contractor’s written notice to Owner to cure such failure, Contractor may suspend performance of the Work until Contractor receives such undisputed amounts.
Suspension by Contractor. The Contractor may order the Subcontractor in writing to suspend all or any part of the Subcontract Work for such period of time as may be determined to be appropriate for the convenience of the Contractor. Phased Work or interruptions of the Subcontract Work for short periods of time shall not be considered a suspension. The Subcontractor, after receipt of the Contractor's order, shall notify the Contractor in writing in sufficient time to permit the Contractor to provide timely notice to the Owner in accordance with the Owner-Contractor agreement of the effect of such order upon the Subcontract Work. The Subcontract Amount or Progress Schedule shall be adjusted by Subcontract Change Order for any increase in the time or cost of performance of this Agreement caused by such suspension. No claim under this Paragraph shall be allowed for any costs incurred more than fourteen (14) days prior to the Subcontractor's notice to the Contractor. Neither the Subcontract Amount nor the Progress Schedule shall be adjusted for any suspension, to the extent that performance would have been suspended, due in whole or in part to the fault or negligence of the Subcontractor or by a cause for which Subcontractor would have been responsible. The Subcontract Amount shall not be adjusted for any suspension to the extent that performance would have been suspended by a cause for which the Subcontractor would have been entitled only to a time extension under this Agreement.
Suspension by Contractor. The Contractor may, for its convenience, order Subcontractor in writing to suspend all or any part of the Work for such period of time as Contractor determines is appropriate. Phase Work or interruptions of the Work for short periods of time shall not be considered a suspension. Subcontractor, after receipt of Contractor’s written order, shall notify Contractor in writing the effect of such order upon the Work. The Subcontract Price and/or the time for performance shall be adjusted by Subcontract Change Order for any increase in the price or time of performance of the Work caused by such suspension. No claim under this Section shall be allowed for any costs incurred more than fourteen (14) days prior to Subcontractor’s written notice to Contractor. Neither the Subcontract Price nor the time for performance shall be adjusted for any suspension, to the extent that the suspension is due in whole or in part to the fault or negligence of Subcontractor or otherwise the responsibility of Subcontractor. If and to the extent the suspension is due to a cause for which Subcontractor would have been entitled only to a time extension under this Agreement, the Subcontract Price shall not be adjusted.
Suspension by Contractor. Notwithstanding anything to the contrary in this Agreement, Contractor shall have the responsibility at all times to prosecute the Work diligently and shall not suspend, stop or cease performance hereunder or permit the prosecution of the Work to be delayed; provided, however, subject to Owner’s right to withhold or offset payment to Contractor as specified in this Agreement, if Owner fails to pay undisputed amounts due and owing to Contractor and Owner has failed to cure such failure within [***] ([***]) Days beyond the date such amounts became due, then, following Contractor’s [***] ([***]) Day notice to Owner to cure such failure (which [***] ([***]) Days’ notice may be given during the [***] ([***]) Day window for non-payment), Contractor may suspend performance of the Work until Contractor receives such undisputed amounts. Contractor shall be entitled to a Change Order for any costs incurred by Contractor resulting from such suspension and shall be entitled to an extension in the applicable Key Dates to the extent permitted under Section 6.8.
Suspension by Contractor. 13.1) At any time prior to the daze of Substantial Completion, in the event of CUC's failure to pay Contractor any undisputed amounts when due pursuant to the terms of this Agreement or any change order issued pursuant to the reams of this Agreement, Contracxxx shall have the right to suspend the Work.
Suspension by Contractor. (a) Subject to Clause 26.15, if the Contractor wishes to suspend the whole or part of the Works, the Contractor must obtain the prior written approval of Tetra Tech.
AutoNDA by SimpleDocs
Suspension by Contractor. Contractor may suspend the performance of the Work under this Agreement if Owner fails to make payment to Contractor of any amounts that are not in dispute, within thirty (30) days after such undisputed payment is due, for Work performed by Contractor and accepted by Owner pursuant to the Contract Documents. In such event, Contractor may, upon seven (7) days written notice to Owner, suspend the performance of the Work under this Agreement. Unless such payment is thereafter received by Contractor within seven (7) days, the suspension shall take effect without further notice to Owner. In the event of a suspension of Work pursuant to this Section 7.5, Contractor shall have no liability to Owner for delay or damage caused to Owner because of suspension of the Work, and upon resuming performance, shall be entitled to a Change Order addressing increases in the cost of performance of the Work including profit on the increased cost of performance resulting from such suspension.
Suspension by Contractor. A. Suspension by Contractor for Owner’s Failure to Pay Undisputed Amounts Before the First Draw. Prior to the First Draw, if:
Suspension by Contractor. Contractor shall have the right to suspend the provision of Services, in part of whole, due to any of the following reasons not attributable to Contractor, without invalidating the other provisions of the Agreement. Contractor shall give a written notice of suspension to the IWD, IIT (BHU) in case IWD, IIT (BHU)