Substantial Performance. D18.1 The Contractor shall achieve Substantial Performance within sixty fifty (65) consecutive Working Days of the commencement of the Work as specified in D14 or by May 1, 2017.
Appears in 1 contract
Samples: www.winnipeg.ca
Substantial Performance. D18.1 D15.1 The Contractor shall achieve Substantial Performance within sixty fifty (6550) consecutive Working Days of the commencement of the Work as specified in D14 or by May 1D13. Notwithstanding the above, 2017the Contractor shall achieve Substantial Performance no later than April 30, 2006.
Appears in 1 contract
Samples: winnipeg.ca
Substantial Performance. D18.1 The Contractor shall achieve Substantial Performance within sixty fifty (6560) consecutive Working Days of the commencement of the Work as specified in D14 or by May 1September 29, 2017.
Appears in 1 contract
Samples: www.winnipeg.ca
Substantial Performance. D18.1 D17.1 The Contractor shall achieve Substantial Performance within sixty fifty one hundred twenty (65120) consecutive Working Days of the commencement of the Work as specified in D14 or by May 1, 2017D14.
Appears in 1 contract
Samples: www.winnipeg.ca
Substantial Performance. D18.1 D15.1 The Contractor shall achieve Substantial Performance within sixty fifty thirty (6530) consecutive Working Days of the commencement of the Work as specified in D14 or by May 1, 2017D14.
Appears in 1 contract
Samples: www.winnipeg.ca