Subsoil Conditions Sample Clauses

Subsoil Conditions. Many of the lots in the third and final phase of Highlander Estates back up to or are adjacent to natural wetlands. As frequently occurs in areas near wetlands, some of these lots contain saturated soils within the building pads. These soils may lack the bearing strength to support a typical foundation. Due to this potential condition, Highlander Estates LLC performed testing to determine which of these lots may require further engineering or structural modifications. The Developer shall reimburse all costs necessary in the event that these conditions are encountered. Soil reports are available upon request.
AutoNDA by SimpleDocs
Subsoil Conditions. Contractor does not assume any risk to subsoil conditions of the property and if any subsoil conditions which affect the work to be performed are encountered they will be dealt with at the Owner's expense pursuant to a change order. If any testing or an engineered footing is required, it will be at Owner's expense.
Subsoil Conditions. The subsoil and groundwater information at this site have been examined in relation to Section 4.1.8.4 of the OBC 2012. The subsoils generally consist of clayey silt to xxxxx silt fill, clayey silt till and xxxxx silt till. It is anticipated that the floor slab of the proposed structure will be founded on stiff to hard clayey silt till.

Related to Subsoil Conditions

  • Environmental Conditions A Phase I environmental site assessment (or update of a previous Phase I and or Phase II environmental site assessment) and, with respect to certain Mortgage Loans, a Phase II environmental site assessment (collectively, an “ESA”) meeting ASTM requirements conducted by a reputable environmental consultant in connection with such Mortgage Loan within 12 months prior to its origination date (or an update of a previous ESA was prepared), and such ESA (i) did not identify the existence of Recognized Environmental Conditions (as such term is defined in ASTM E1527-05 or its successor, hereinafter “Environmental Condition”) at the related Mortgaged Property or the need for further investigation, or (ii) if the existence of an Environmental Condition or need for further investigation was indicated in any such ESA, then at least one of the following statements is true: (A) an amount reasonably estimated by a reputable environmental consultant to be sufficient to cover the estimated cost to cure any material noncompliance with applicable Environmental Laws or the Environmental Condition has been escrowed by the related Mortgagor and is held or controlled by the related lender; (B) if the only Environmental Condition relates to the presence of asbestos-containing materials, radon in indoor air, lead based paint or lead in drinking water, the only recommended action in the ESA is the institution of such a plan, an operations or maintenance plan has been required to be instituted by the related Mortgagor that can reasonably be expected to mitigate the identified risk; (C) the Environmental Condition identified in the related environmental report was remediated, abated or contained in all material respects prior to the date hereof, and, if and as appropriate, a no further action, completion or closure letter or its equivalent, was obtained from the applicable governmental regulatory authority (or the Environmental Condition affecting the related Mortgaged Property was otherwise listed by such governmental authority as “closed” or a reputable environmental consultant has concluded that no further action or investigation is required); (D) an environmental policy or a lender’s pollution legal liability insurance policy that covers liability for the Environmental Condition was obtained from an insurer rated no less than “A-” (or the equivalent) by Xxxxx’x, S&P and/or Fitch; (E) a party not related to the Mortgagor was identified as the responsible party for the Environmental Condition and such responsible party has financial resources reasonably estimated to be adequate to address the situation; or (F) a party related to the Mortgagor having financial resources reasonably estimated to be adequate to address the situation is required to take action. To Seller’s knowledge, except as set forth in the ESA, there is no Environmental Condition at the related Mortgaged Property.

  • General Conditions (i) Each party will make each payment or delivery specified in each Confirmation to be made by it, subject to the other provisions of this Agreement.

  • SPECIAL CONDITIONS A submitted appeal must;

  • General Condition The Aircraft will:

  • Environmental Condition Except as set forth on Schedule 5.12 to the Information Certificate, (a) to each Loan Party’s knowledge, no properties or assets of any Loan Party or any of its Subsidiaries have ever been used by a Loan Party, its Subsidiaries, or by previous owners or operators in the disposal of, or to produce, store, handle, treat, release, or transport, any Hazardous Materials, where such disposal, production, storage, handling, treatment, release or transport was in violation, in any material respect, of any applicable Environmental Law, (b) to each Loan Party’s knowledge, after due inquiry, no Loan Party’s nor any of its Subsidiaries’ properties or assets have ever been designated or identified in any manner pursuant to any environmental protection statute as a Hazardous Materials disposal site, (c) no Loan Party nor any of its Subsidiaries has received notice that a Lien arising under any Environmental Law has attached to any revenues or to any Real Property owned or operated by a Loan Party or its Subsidiaries, and (d) no Loan Party nor any of its Subsidiaries nor any of their respective facilities or operations is subject to any outstanding written order, consent decree, or settlement agreement with any Person relating to any Environmental Law or Environmental Liability that, individually or in the aggregate, could reasonably be expected to result in a Material Adverse Change.

  • Subsurface Conditions Unless the Contract Documents stipulate specific quantities and units of rock or unsuitable soils, the Contractor shall assume material below the surface of the Earth to be earth and other material that can be removed by power shovel or similar equipment. Should conditions encountered below the surface of the ground be at variance to the number of unit requirements as indicated by drawings or specifications, and absent an agreed-upon unit price established prior to the bid by Addendum, or after contract execution by Change Order, the Contract Sum and/or time shall be adjusted as provided in the Contract Documents for changes in the work.

  • Additional Conditions For each mediation or arbitration:

  • Local Conditions The Design-Builder shall visit the site(s), become familiar with the local conditions, and correlate observable conditions with the requirements of the Contract Documents.

  • HHSC SPECIAL CONDITIONS The terms and conditions of these Special Conditions are incorporated into and made a part of the Contract. Capitalized items used in these Special Conditions and not otherwise defined have the meanings assigned to them in HHSC Uniform Terms and Conditions -Grant- Version 2.16.1

  • Mutual Conditions The respective obligations of each party to consummate the purchase and issuance and sale of the Purchased Units shall be subject to the satisfaction on or prior to the Closing Date of each of the following conditions (any or all of which may be waived by a party on behalf of itself in writing, in whole or in part, to the extent permitted by applicable Law):

Time is Money Join Law Insider Premium to draft better contracts faster.