Submittals The Sample Clauses

Submittals The. Subcontractor shall promptly submit for approval to the Contractor all shop drawings, samples, product data, manufacturers' literature and similar submittals required by the Sub- contract Documents. The Subcontractor shall prepare and deliver its submittals to the Contractor in a manner consistent with the Sched- ule of Work and in such time and sequence so as not to delay the Contractor or others in the performance of the Work. When its sub- mittals are delivered to the Contractor, the Subcontractor shall ad- vise the Contractor in writing of any deviations in the submittals from the requirements of the Subcontract Documents and shall note such deviations in its submittals. In the absence of any such notifications, The Subcontractor shall notify the Contractor in writing if it intends to change the Designer. The Subcontractor warrants the design fur- nished by the Designer will be in conformance with the information given and the design concept expressed in the Subcontract Docu- ments. The Subcontractor shall not be responsible for the adequacy of the performance or design criteria required by the Subcontract Documents furnished by the Owner, Architect/Engineer or Contrac- tor.
AutoNDA by SimpleDocs

Related to Submittals The

  • Submittal Reports, plans, surveys, field notes, original drawings, computer tapes, graphic files, tracings, calculations, analyses, reports, specifications, data, sketches and/or schematics prepared by A/E and supporting documents (collectively referred to hereinabove and hereinafter as the "A/E Work Product(s)"), shall be submitted by A/E on or before the dates specified for completion, as set out in the Production Schedule set forth in Exhibit C.

  • Submittals Submittals required by the Contract Documents shall be prepared specifically for the Work by the Contractor to illustrate some portion of the Work. Submittals are not Contract Documents.

  • Submittal Schedule Within sixty days after the Effective Date of the Contract, the Contractor shall prepare and submit a Submittal Schedule for review and approval of the Design Professional. In establishing the Submittal Schedule the Contractor shall take into account large submittal documents that will require longer review times, e.g., submittals with over fifty sheets of drawings. The Design Professional’s approval shall be based on conformance of the Submittal Schedule with the Overall Project Schedule, subject to change from time to time in accordance with the progress of the Work.

  • Order to Stop Work The Procurement Officer, may, by written order to Contractor at any time, and without notice to any surety, require Contractor to stop all or any part of the work called for by this contract. This order shall be for a specified period not exceeding 90 days after the order is delivered to Contractor, unless the parties agree to any further period. Any such order shall be identified specifically as a stop work order issued pursuant to this clause. Upon receipt of such an order, Contractor shall forthwith comply with its terms and take all reasonable steps to minimize the occurrence of costs allocable to the work covered by the order during the period of work stoppage. Before the stop work order expires, or within any further period to which the parties shall have agreed, the Procurement Officer shall either:

  • SUBMITTAL LABEL In an effort to help promote social distancing measures during the COVID-19 Public Health Emergency, electronic submissions will be accepted by the County. Firms are strongly encouraged to submit responses electronically. Firms will not be permitted to fax or email offers. To maintain a secured sealed process electronic submissions may be made through the Negometrix platform only at: xxxxx://xxx.xxxxxxxxxx.xxx/buyer/691 DO NOT OPEN - SE ALED RESPONSES - DO NOT OPEN RESERVED FOR PUBLIC BID OPENING Company : Contact Name: Contact Phone/ Email: Address: CONTACT: IFB NUMBER: TITLE: XXXXXX XXXXXXX Y 20 - 1058 - MV HEAVY EQUIPMENT PARTS AND LABOR BID DUE DATE: D ELIVER T O : ORANGE COUNTY PROCUREMENT DIVISION INTERNAL OPERATIONS CENTRE II 000 X. XXXXX XXXXXX, 0XX XXXXX XXXXXXX, XX 00000. If submitting via mail or hard copy, use the hard-copy label below and place on front of their outermost sealed envelope/package.

  • Submittal Review 7.10.1 The A/E shall review Submittals such as Shop Drawings, Product Data, and Samples for conformity with design intent and conformity with the Contract Documents within 14 days of receiving Submittals or in accordance with the approved submittal schedule, or other period as mutually agreed by the A/E and Contractor.

  • Invoice Submittal DEO shall reimburse Subrecipient in accordance with Section 6, above. In accordance with the Funding Requirements of s. 215.971(1), F.S. and Section 21 of this Agreement, Subrecipient and its subcontractors may only expend funding under this Agreement for allowable costs resulting from obligations incurred during this Agreement. To be eligible for reimbursement, costs must be in compliance with laws, rules and regulations applicable to expenditures of State funds, including, but not limited to, the Reference Guide for State Expenditures (xxxxx://xxx.xxxxxxxxxxxx.xxx/Division/AA/Manuals/documents/ReferenceGuideforStateExpenditures.pdf).

  • Required Submittals Complete shop drawings and manufacturer’s catalog data shall be submitted to the State and approved by the State prior to start of any construction work. Power and lighting panel configuration shall be complete with schedule of branch panels, separate disconnects, and circuit breakers, based on calculated and estimated motor, resistive and lighting loads. All circuits shall be labeled at the panel and at the outlet/power pole for future reference. Location of all electrical receptacles and telephone outlets (including power drops for the systems furnishings) shall be designated on a block floor plan showing the systems furnishings layout provided by the State. Said block floor plan shall be furnished by the State to the Owner/Lessor no later than 4 weeks after approved construction plans are received by the State.

  • Contractor’s Submittals The Contract shall submit with reasonable promptness consistent with the Work Project Schedule and in orderly sequence all Shop Drawings, Samples, or other information required by the Contract Documents, or subsequently required by Change Order. Prior to submitting, the Contractor shall review each submittal for compliance with the Contract Documents and certify its approval by an approval stamp affixed to each copy. Submittal data presented without the Contractor’s certification will be returned without review or comment, and any delay resulting from such certification is the Contractor's responsibility.

  • Certification Regarding Sales and Use Tax By executing the Contract the Contractor certifies it is either (a) registered with the State Department of Revenue, collects, and remits State sales and use taxes as required by Georgia law, including Chapter 8 of Title 48 of the O.C.G.A.; or (b) not a “retailer” as defined in O.C.G.A. Section 48-8-2. The Contractor also acknowledges that the State may declare the Contract void if the above certification is false. The Contractor also understands that fraudulent certification may result in the State Entity or its representative filing for damages for breach of contract.

Time is Money Join Law Insider Premium to draft better contracts faster.