Common use of Stop Work Orders Clause in Contracts

Stop Work Orders. Each JBE may, at any time, by Notice to Contractor, require Contractor to stop all or any part of the Work being provided to such JBE for a period up to ninety (90) days after the Notice is delivered to Contractor, and for any further period to which the JBE and the Contractor may agree (“Stop Work Order”). The Stop Work Order shall be specifically identified as such and shall indicate it is issued under this provision. Upon receipt of the Stop Work Order, Contractor shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the Work covered by the Stop Work Order during the period of stoppage. Within ninety (90) days after a Stop Work Order is delivered to Contractor, or within any extension of that period to which the parties shall have agreed, the JBE shall either (i) cancel the Stop Work Order; or (ii) terminate the Work covered by the Stop Work Order as provided for in this Agreement. If a Stop Work Order issued under this provision is canceled or the period of the Stop Work Order or any extension thereof expires, Contractor shall resume the performance of the Work. The JBE shall make an equitable adjustment in the delivery schedule and the applicable documentation shall be modified, in writing, accordingly, if:

Appears in 25 contracts

Samples: Master Agreement Agreement, Master Agreement, Master Agreement Agreement

AutoNDA by SimpleDocs

Stop Work Orders. Each JBE may, at any time, by Notice to Contractor, require Contractor to stop all or any part of the Work being provided to such JBE for a period up to ninety (90) days after the Notice is delivered to Contractor, and for any further period to which the JBE and the Contractor may agree (“Stop Work Order”). The Stop Work Order shall be specifically identified as such and shall indicate it is issued under this provision. Upon receipt of the Stop Work Order, Contractor shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the Work covered by the Stop Work Order during the period of stoppage. Within ninety (90) days after a Stop Work Order is delivered to Contractor, or within any extension of that period to which the parties shall have agreed, the JBE shall either (i) cancel the Stop Work Order; or (ii) terminate the Work covered by the Stop Work Order as provided for in this Agreement. If a Stop Work Order issued under this provision is canceled or the period of the Stop Work Order or any extension thereof expires, Contractor shall resume the performance of the Work. The JBE shall make an equitable adjustment in the delivery schedule and the applicable documentation Participating Addendum shall be modified, in writing, accordingly, if:

Appears in 8 contracts

Samples: Master Agreement, Master Agreement, Master Agreement

Stop Work Orders. Each The JBE may, at any time, by Notice to Contractor, require Contractor to stop all or any part of the Work being provided to such JBE Services for a period up to ninety (90) days after the Notice is delivered to Contractor, and for any further period to which the JBE and the Contractor parties may agree (“Stop Work Order”). The Stop Work Order shall be specifically identified as such and shall indicate it is issued under this provision. Upon receipt of the Stop Work Order, Contractor shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the Work Services covered by the Stop Work Order during the period of stoppage. Within ninety (90) days after a Stop Work Order is delivered to Contractor, or within any extension of that period to which the parties shall have agreed, the JBE shall either (i) cancel the Stop Work Order; or (ii) terminate the Work Services covered by the Stop Work Order as provided for in this Agreement. If a Stop Work Order issued under this provision is canceled or the period of the Stop Work Order or any extension thereof expires, Contractor shall resume the performance of the WorkServices. The JBE shall make an equitable adjustment in the delivery schedule schedule, the Contract Amount, or both, and the applicable documentation Agreement shall be modified, in writing, accordingly, if:

Appears in 2 contracts

Samples: Standard Agreement, www.sanmateo.courts.ca.gov

Stop Work Orders. Each JBE A. The JCC may, at any time, by Notice to Contractor, require Contractor to stop all or any part of the Work being provided to such JBE Services for a period up to ninety (90) days after the Notice is delivered to Contractor, and for any further period to which the JBE and the Contractor parties may agree (“Stop Work Order”). The Stop Work Order shall be specifically identified as such and shall indicate it is issued under this provision. Upon receipt of the Stop Work Order, Contractor shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the Work Services covered by the Stop Work Order during the period of stoppage. Within ninety (90) days after a Stop Work Order is delivered to Contractor, or within any extension of that period to which the parties shall have agreed, the JBE JCC shall either (i) cancel the Stop Work Order; or (ii) terminate the Work Services covered by the Stop Work Order as provided for in this Agreement. If a Stop Work Order issued under this provision is canceled or the period of the Stop Work Order or any extension thereof expires, Contractor shall resume the performance of the WorkServices. The JBE JCC shall make an equitable adjustment in the delivery schedule schedule, the Contract Amount, or both, and the applicable documentation Agreement shall be modified, in writing, accordingly, if:

Appears in 2 contracts

Samples: July 2017 Agreement, July 2017 Agreement

Stop Work Orders. 3.9.1 Each JBE may, at any time, by Notice to Contractor, require Contractor to stop all or any part of the Work being provided to such JBE for a period up to ninety (90) days after the Notice is delivered to Contractor, and for any further period to which the JBE and the Contractor may agree (“Stop Work Order”). The Stop Work Order shall be specifically identified as such and shall indicate it is issued under this provision. Upon receipt of the Stop Work Order, Contractor shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the Work covered by the Stop Work Order during the period of stoppage. Within ninety (90) days after a Stop Work Order is delivered to Contractor, or within any extension of that period to which the parties shall have agreed, the JBE shall either (i) cancel the Stop Work Order; or (ii) terminate the Work covered by the Stop Work Order as provided for in this Agreement. If a Stop Work Order issued under this provision is canceled or the period of the Stop Work Order or any extension thereof expires, Contractor shall resume the performance of the Work. The JBE shall make an equitable adjustment in the delivery schedule and the applicable documentation Participating Addendum shall be modified, in writing, accordingly, if:

Appears in 2 contracts

Samples: Master Agreement, Master Agreement

AutoNDA by SimpleDocs

Stop Work Orders. Each The JBE may, at any time, by Notice to Contractor, require Contractor to stop all or any part of the Work being provided to such the JBE for a period up to ninety (90) days after the Notice is delivered to Contractor, and for any further period to which the JBE and the Contractor may agree (“Stop Work Order”). The Stop Work Order shall be specifically identified as such and shall indicate it is issued under this provision. Upon receipt of the Stop Work Order, Contractor shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the Work covered by the Stop Work Order during the period of stoppage. Within ninety (90) days after a Stop Work Order is delivered to Contractor, or within any extension of that period to which the parties shall have agreed, the JBE shall either (i) cancel the Stop Work Order; or (ii) terminate the Work covered by the Stop Work Order as provided for in this Agreement. If a Stop Work Order issued under this provision is canceled or the period of the Stop Work Order or any extension thereof expires, Contractor shall resume the performance of the Work. The JBE shall make an equitable adjustment in the delivery schedule and the applicable documentation shall be modifiedschedule, in writing, accordingly, if:

Appears in 1 contract

Samples: Master Agreement

Stop Work Orders. Each JBE may, at any time, by Notice to Contractor, require Contractor to stop all or any part of the Work being provided to such JBE for a period up to ninety (90) days after the Notice is delivered to Contractor, and for any further period to which the JBE and the Contractor may agree (“Stop Work Order”). The Stop Work Order shall be specifically identified as such and shall indicate it is issued under this provision. Upon receipt of the Stop Work Order, Contractor shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the Work covered by the Stop Work Order during the period of stoppage. Within ninety (90) days after a Stop Work Order is delivered to Contractor, or within any extension of that period to which the parties shall have agreed, the JBE shall either (i) cancel the Stop Work Order; or (ii) terminate the Work covered by the Stop Work Order as provided for in this Agreement. If a Stop Work Order issued under this provision is canceled or the period of the Stop Work Order or any extension thereof expires, Contractor shall resume the performance of the Work. The JBE shall make an equitable adjustment in the delivery schedule and the applicable documentation Participating Addendum shall be modified, in writing, accordingly, if:: The Stop Work Order results in an increase in the time required for performance of any part of the Participating Addendum; and Contractor requests an equitable adjustment within thirty (30) days after the end of the period of stoppage. The JBEs shall not be liable to Contractor for loss of profits because of a Stop Work Order issued under this provision.

Appears in 1 contract

Samples: Master Agreement Agreement Number [Agreement

Stop Work Orders. Each JBE may, at any time, by Notice to Contractor, require Contractor to stop all or any part of the Work being provided to such JBE for a period up to ninety (90) days after the Notice is delivered to Contractor, and for any further period to which the JBE and the Contractor may agree (“Stop Work Order”). The Stop Work Order shall be specifically identified as such and shall indicate it is issued under this provision. Upon receipt of the Stop Work Order, Contractor shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the Work covered by the Stop Work Order during the period of stoppage. Within ninety (90) days after a Stop Work Order is delivered to Contractor, or within any extension of that period to which the parties shall have agreed, the JBE shall either (i) cancel the Stop Work Order; or (ii) terminate the Work covered by the Stop Work Order as provided for in this Agreement. If a Stop Work Order issued under this provision is canceled or the period of the Stop Work Order or any extension thereof expires, Contractor shall resume the performance of the Work. The JBE shall make an equitable adjustment in the delivery schedule and the applicable documentation Purchase Order shall be modified, in writing, accordingly, if:

Appears in 1 contract

Samples: Master Agreement