Stand Alone System Upgrade Facilities Sample Clauses

Stand Alone System Upgrade Facilities. The Developer will perform the following modifications to the protection systems at the NYSEG Xxxxxxxxx 115kV Substation:  Connect Developer’s generation breaker B4-72 into Connecting Transmission Owner’s 115kV linear coupler bus differential;  Isolate B4-72 breaker control and Bank #4 protective relay control systems between the NYSEG Xxxxxxxxx 115kV Substation and Developer’s generation equipment using fiber and SEL-2411 units (note that Bank #4 protection resides in Connecting Transmission Owner’s 115kV control house and can remain there and be reconnected provided this isolation is installed);  Separate Developer’s generation B4-72 and Bank #4 protection DC systems (these need to be supplied and controlled from Developer’s generation DC system); and  Separate Developer’s generation B4-72 AC feed from the Connecting Transmission Owner’s AC system so that it is supplied from the Developer’s generation AC system. The Developer will perform its modifications in accordance with Connecting Transmission Owner’s Bulletin 86-01, to the extent not inconsistent with the terms of this Agreement or the NYISO OATT. The Connecting Transmission Owner will provide project management and construction oversight.
AutoNDA by SimpleDocs
Stand Alone System Upgrade Facilities. The Developer shall engineer, design, and procure all materials, and construct and install a new 69 kV, three breaker bus (“8CS Xxxxxx Street Substation”) on the Connecting Transmission Owner’s XXXX-XX 00 kV line, approximately 2.1 miles from the Ridge Substation and 3.5 miles from the Wildwood Substation. The Developer shall perform this work in accordance with the Connecting Transmission Owner’s requirements as described above in Section 1(a) of this Appendix A. The Connecting Transmission Owner shall perform design review, oversee construction, testing, and commissioning of the Stand-Alone SUF constructed by the Developer. Xxx 0XX Xxxxxx Xxxxxx Substation will include the following major electrical and physical equipment: • Three (3) 72.5 kV, 2000 A, 43 kA, 350kV BIL SF6 breakers, equipped with 2 sets of 2000:5 MR, C800 CTs on each bushing, ABB 72PM43-20; • Six (6) 72.5 kV, 2000 A, 350kV BIL, TPST, center break “V”, manually operated disconnect switches, Type V2-CA, manufactured by Xxxxxxxxxx Price; • Two (2) 72.5kV ground switches, manually operated; • Three (3) single phase 69 kV voltage transformers, 40250/69000-67.08/115 Volts, type VTO-SB-350, manufactured by ITEC; • Six (6) 48 kV MCOV station class surge arrestors; • One (1) single phase station service transformer, 69 kV- 120/240 V, 75 kVA manufactured by Uptegraff, style number HD65; • One (1) 69 kV disconnect fuse for station service; • One (1) 72.5 kV, 2000 A, 350 kV BIL, vertical break single phase disconnect switch, manually operated (for station service);

Related to Stand Alone System Upgrade Facilities

  • System Upgrade Facilities Transmission Owner shall design, procure, construct, install, and own the System Upgrade Facilities described in Appendix A hereto. The responsibility of the Developer for costs related to System Upgrade Facilities shall be determined in accordance with the provisions of Attachment S to the NYISO OATT.

  • Generating Facility The Interconnection Customer’s device for the production of electricity identified in the Interconnection Request, but shall not include the Interconnection Customer’s Interconnection Facilities.

  • System Upgrade Facilities and System Deliverability Upgrades Connecting Transmission Owner shall design, procure, construct, install, and own the System Upgrade Facilities and System Deliverability Upgrades described in Appendix A hereto. The responsibility of the Developer for costs related to System Upgrade Facilities and System Deliverability Upgrades shall be determined in accordance with the provisions of Attachment S to the NYISO OATT.

  • Communications Equipment Members of the board of directors or any committee thereof may participate in and act at any meeting of such board or committee through the use of a conference telephone or other communications equipment by means of which all persons participating in the meeting can hear each other, and participation in the meeting pursuant to this section shall constitute presence in person at the meeting.

  • Verizon OSS Facilities Any gateways, interfaces, databases, facilities, equipment, software, or systems, used by Verizon to provide Verizon OSS Services to CBB.

  • Interconnection Facilities 4.1.1 The Interconnection Customer shall pay for the cost of the Interconnection Facilities itemized in Attachment 2 of this Agreement. The NYISO, in consultation with the Connecting Transmission Owner, shall provide a best estimate cost, including overheads, for the purchase and construction of its Interconnection Facilities and provide a detailed itemization of such costs. Costs associated with Interconnection Facilities may be shared with other entities that may benefit from such facilities by agreement of the Interconnection Customer, such other entities, the NYISO, and the Connecting Transmission Owner.

  • Interconnection Customer Interconnection Facilities Interconnection Customer shall design, procure, construct, install, own and/or control Interconnection Customer Interconnection Facilities described in Appendix A, Interconnection Facilities, Network Upgrades and Distribution Upgrades, at its sole expense.

  • Contractor’s Equipment Payment for required equipment owned by the Construction Manager or an affiliate of the Construction Manager will be based solely on an hourly rate derived by dividing the current appropriate monthly rate by 176 hours. No payment will be made under any circumstances for repair costs, freight and transportation charges, fuel, lubricants, insurance, any other costs and expenses, or overhead and profit. Payment for such equipment made idle by delays attributable to the Government will be based on one-half the derived hourly rate under this subsection.

  • Information regarding Interconnection Facilities 4.2.1 The SPD shall be required to obtain all information from the STU/CTU/concerned authority with regard to the Interconnection Facilities as is reasonably necessary to enable it to design, install and operate all interconnection plant and apparatus on the SPD’s side of the Delivery Point to enable delivery of electricity at the Delivery Point. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost.

  • System Upgrades The Connecting Transmission Owner shall procure, construct, install, and own the System Upgrade Facilities and System Deliverability Upgrades described in Attachment 6 of this Agreement. To the extent that design work is necessary in addition to that already accomplished in the Class Year Interconnection Facilities Study for the Interconnection Customer, the Connecting Transmission Owner shall perform or cause to be performed such work. If all the Parties agree, the Interconnection Customer may construct System Upgrade Facilities and System Deliverability Upgrades.