Sole Remedy for Correction of Defect Sample Clauses

Sole Remedy for Correction of Defect. If at any time and from time to time following the Take-over Date, any part of the Work are found to be defective, the sole liability of the Contractor and the exclusive remedy of OPG with respect to the correction of such defective or deficient part, will be limited to the warranty remedies set out in this Section 7, provided that nothing in this Section 7 will serve to limit the Contractor’s liabilities or OPG’s remedies otherwise provided for under this Contract that do not pertain to the correction of such defective and deficient part.
AutoNDA by SimpleDocs
Sole Remedy for Correction of Defect. If at any time and from time to time following the delivery of the Services, any part of the Services are found to be defective, the sole liability of the Contractor and the exclusive remedy of OPG with respect to the correction of such defective or deficient part, will be limited to the warranty remedies set out in this Section 7, provided that nothing in this Section 7 will serve to limit the Contractor’s liabilities or OPG’s remedies otherwise provided for under this Contract that do not pertain to the correction of such defective or deficient part.

Related to Sole Remedy for Correction of Defect

  • Correction of Defects 35.1 The Engineer shall give notice to the Contractor of any Defects before the end of the Defects Liability Period, which begins at Completion and is defined in the Contract Data. The Defects Liability Period shall be extended for as long as Defects remain to be corrected.

  • RECTIFICATION OF DEFECTS 27.1 The Purchaser shall within 14 (fourteen) days after the Contractual Occupation Date notify the Seller in writing by way of a snaglist of all or any defects in the Unit, failing which the Purchaser shall be deemed to have accepted the Unit in good order and condition. Only ONE snaglist shall be considered. The Seller shall within a reasonable time thereafter at its cost repair all such defects and the Seller undertakes to rectify all latent and/or patent defects which become apparent to the Purchaser within 3 (three) calendar months from the Contractual Occupation Date and which is the result of defective materials and/or workmanship.

  • Correction of Defective Work 2.10.1 Design-Builder agrees to correct any Work that is found to not be in conformance with the Contract Documents, including that part of the Work subject to Section 2.9 hereof, within a period of one (1) year from the date of Final Acceptance of the Work or any portion of the Work, or within such longer period to the extent required by the Contract Documents or applicable Legal Requirements or Government Approvals.

  • Sole Remedy This Section 2.7 states the sole remedy available to Noteholders for the replacement or payment of mutilated, destroyed, lost or stolen Notes.

  • Liability for defects Aptum is dependent on manufacturers and developers of the Branded Products for updates and patches, including security patches, and will have no liability to Customer, Customer’s Users or any third party with respect to security vulnerabilities inherent in the applicable Branded Products.

  • Remedy for failure to insure If the Concessionaire shall fail to effect and keep in force all insurances for which it is responsible pursuant hereto, the Authority shall have the option to either keep in force any such insurances, and pay such premia and recover the costs thereof from the Concessionaire, or in the event of computation of a Termination Payment, treat an amount equal to the Insurance Cover as deemed to have been received by the Concessionaire.

  • Notice of Defects If, based on Consulting Engineer/Architect's involvement during the construction phase, Consulting Engineer/Architect observes or otherwise becomes aware of any defect in the work, he shall give prompt written notice to City of such defects and their approximate location on the Project. However, Consulting Engineer/Architect shall not have control over or charge of and shall not be responsible for construction means, methods, techniques, sequences or procedures, or for safety precautions, inspections and programs in connection with the work, since these are solely the Contractor's responsibility under the contract for construction. Consulting Engineer/Architect shall not be responsible for the Contractor's schedules or failure to carry out the work in accordance with the Contract Documents. Consulting Engineer/Architect shall not have control over or charge of acts or omissions of the Contractor, Contractor's subcontractors, or their agents or employees.

  • Correction of Deficiencies The contractor must correct promptly any work of his/her own or his/her subcontractors found to be defective or not complying with the terms of the contract.

  • Exclusive Remedy The foregoing shall constitute the Parties' sole and exclusive remedies and obligations with respect to a third party claim of intellectual property infringement arising out of the conduct of business under this Agreement.

  • Limitation of Liability in Event of Breach An Interconnection Party (“Breaching Party”) shall have no liability hereunder to the other Interconnection Parties, and the other Interconnection Parties hereby release the Breaching Party, for all claims or damages that either of them incurs that are associated with any interruption in the availability of the Customer Facility, Interconnection Facilities, Transmission System or Interconnection Service or damages to an Interconnection Party’s facilities, except to the extent such interruption or damage is caused by the Breaching Party’s gross negligence or willful misconduct in the performance of its obligations under this Interconnection Service Agreement (including Appendix 2).

Time is Money Join Law Insider Premium to draft better contracts faster.