SEQUENCE OF WORK Sample Clauses

SEQUENCE OF WORK. 13.9.1 A schedule of the Contractor's work shall be submitted to the City for approval as required under Article V of the Agreement. It shall contain a listing of the order in which the Contract items will be constructed and the approximate dates for starting and finishing each Contract item.
AutoNDA by SimpleDocs
SEQUENCE OF WORK. Excavation, cleaning, laying, jointing and backfilling shall be kept up as closely as is possible so as to progress in a uniform, workmanlike manner. In no case shall pipe be left in the trench overnight, without completing jointing. The completed pipe line shall not be left exposed in the trench unnecessarily and the Contractor will be required to backfill and compact the trench as soon as possible after jointing and laying is completed. The Contractor shall keep exposed ends of pipe properly plugged during laying to prevent dirt and other materials entering the line. Each day at the close of work, and at all times when laying is not in progress the exposed end of the pipe line in the trench shall be closed by the use of an approved header or barrier of wood or metals. If at any time it becomes necessary to cover the ends of an uncompleted pipe line with backfill, the end of such pipe line shall be closed, using a header with mechanical joint plug.
SEQUENCE OF WORK. Contract specifications shall be completed and inspected on a unit-by-unit basis. No work shall be done on a succeeding block until acceptance of work on the preceding unit, unless agreed to in writing by the Officer-in-Charge ** Work shall not start in blocks located within wildlife restriction buffer areas until after August 1st. or as approved by Wildlife Department. Tribal –specified sequence of work is as follows: Priority Block Acres Restriction Estimated Start Date # Calendar Days Allowed na PC/BRKSS5/75 24.3 None 24 na PC/SS5-1/71 101.5 None 100 na PC/SS5-2/71 87.9 None 86 Totals: 213.7 210 The Contractor shall notify the Tribe prior to starting work on any unit. By this notification, spacing requirements, stream courses, slash treatment, and other items may be discussed prior to the start of work on each unit. The Tribe may specify a priority of work by unit.
SEQUENCE OF WORK. 3.1.1 Carry out work of this section sequentially. Complete each activity before proceeding to the next.
SEQUENCE OF WORK. If required by the special provisions, the Contractor shall start construction operations on that part of the project designated by the Public Works Director.
SEQUENCE OF WORK. The Contractor shall make every effort to complete the work in a manner and fashion that minimizes closures and inconveniences to the public. Once barricades are placed, the CONTRACTOR shall show progress of work during normal working days and hours. The contract documents are compiled to support the efficient operations of the Contractor and are not intended to supplant the Contractor's responsibility of superintendence. Special consideration regarding schedules and/or work sequences necessary or anticipated during the course of the project will be identified in the Special Provisions. Exhibit E SPECIFICATIONS THE STANDARD SPECIFICATIONS GOVERNING THIS PROJECT SHALL BE THE "CITY OF CHEYENNE/BOARD OF PUBLIC UTILITIES CONSTRUCTION SPECIFICATIONS AND STANDARD DRAWINGS, 2007" WITH APPROVED AMENDMENTS ISSUED BY THE CITY ENGINEER AT THE TIME OF THIS CONTRACT. IT IS THE CONTRACTOR'S RESPONSIBILITY TO KEEP CURRENT ON THESE AMENDMENTS. COPIES OF THESE AMENDMENTS ARE AVAILABLE IN THE OFFICE OF THE CITY ENGINEER.
SEQUENCE OF WORK. 13.1 The Parties’ obligations under this EPC Contract related to the performance of the Work shall begin on the date that Owner delivers the NTP to EPC Contractor (the “NTP Date”). Owner shall be required to issue and deliver the NTP to EPC Contractor upon the closing of the Acquisition and the delivery of proof of all insurance coverage required under ARTICLE 39.
AutoNDA by SimpleDocs
SEQUENCE OF WORK. The following sequence of work is to be performed in series for each of the four towers.  Remove and dispose of existing packing material in the tower.  Pressure wash interior of the tower.  Clean bottom of the unit below the lower grating, remove blind flange and clean piping on the second floor.  Assist County Staff, as needed, with inspection of the unit prior to reinstallation of the man-ways.  Install approximately twelve (12) bags of new media.  Place the unit back into service.  Proceed to step one for the second, third and fourth towers.
SEQUENCE OF WORK. OWNER reserves the right to schedule sequence of construction; that is, which portion of the project will be constructed first. The contractor may perform construction operations during daylight hours only, unless written approval is given by the ENGINEER and the OWNER. All existing utilities to remain operational during all construction activities.
SEQUENCE OF WORK. It is understood that the sequence of construction for the Project will require that the Building be erected and completed from the administrative office toward column line 28. · Tenant should have the ability to occupy and use the administrative offices prior to the completion of the warehouse. This would mean that a temporary certificate of occupancy is received for this space. · The warehouse racks will start at column line seven and proceed to column line 28. · The Landlord will follow the rack installation with sprinkler installation. · The Landlord will maintain a clean construction site, especially in the warehouse. Warehouse rack installer will be responsible for cleanup of all packing debris and rack material debris and trash associated with the rack material. The Landlord will be responsible for cleanup of all other trash from the rack installation. · The Landlord will repair any and all defects in the concrete floor surface. Should the warehouse rack installer damage the concrete floor, the repair for that damage will be accomplished by the Landlord and the cost of the repair will be borne by the warehouse rack installer. Building Cost Distribution: · The Landlord has provided a complete Building Cost Breakdown in the format provided in Tenant’s Request for Proposal for this Project (the “RFP”).