Section closure Sample Clauses

Section closure. 17.7.1 The Concessionaire shall not close any section of the Bus Terminal for undertaking maintenance or repair works except with the prior written approval of the Independent Engineer. Such approval shall be sought by the Concessionaire through a written request to be made to the Independent Engineer, and a copy thereof furnished to the Authority, at least 7 (seven) days before the proposed closure of such section and shall be accompanied by particulars thereof. Within 3 (three) days of receiving such request, the Independent Engineer shall grant permission with such modifications as it may deem necessary and a copy of such permission shall be sent to the Authority.
AutoNDA by SimpleDocs
Section closure. 18.7.1 The Concessionaire shall not close any section of the Rail System for undertaking maintenance or repair works except with the prior written approval of MOR. Such approval shall be sought by the Concessionaire through a written request to be made to MOR, at least 7 (seven) days before the proposed closure of such section and shall be accompanied by particulars thereof. Within 3 (three) days of receiving such request, MOR shall grant permission with such modifications as it may deem necessary. Provided that for closure of any one trackway for a period not exceeding 2 (two) hours in a day, the prior notice for seeking approval of MOR shall be not less than 2 (two) hours prior to such proposed closure.
Section closure. 17.8.1. Upon notice given by the Authority to this effect prior to commencement of an Accounting Year, the Concessionaire shall, save and except as provided in Clause 17.7, not schedule a closure of any part of the Storage Facility at any time during a continuous period of 180 (one hundred and eighty) days as may be specified by the Authority for and in respect of such Accounting Year.
Section closure. 16.7.1 Save and except as provided in Clause 16.6, the Mine Operator shall not shut down or de-commission any section of the Mines for undertaking maintenance or repair works, not forming part of the Maintenance Programme, except with the prior written approval of the Engineer in charge. Such approval shall be sought by the Mine Operator through a written request to be made to the Engineer in charge, and a copy thereof furnished to the Authority, at least 7 (seven) days before the proposed closure of such section and shall be accompanied by particulars thereof. Within 3 (three) days of receiving such request, the Engineer in charge shall grant permission with such modifications as it may deem necessary and a copy of such permission shall be sent to the Authority.
Section closure. 17.7.1 The Concessionaire shall not close any section of the XXX Ropeway or part thereof for undertaking maintenance or repair works except with the prior written approval of the Independent Engineer. Such approval shall be sought by the Concessionaire through a written request to be made to the Independent Engineer, and a copy thereof furnished to the Authority, at least 7 (seven) days before the proposed closure of such section and shall be accompanied by particulars thereof. Within 3 (three) days of receiving such request, the Independent Engineer shall grant permission with such modifications as it may deem necessary and a copy of such permission shall be sent to the Authority.
Section closure. 12.6.1 The Developer shall not close any section of the Rail System for undertaking maintenance or repair works except with the prior written approval of MOR. Such approval shall be sought by the Developer through a written request to be made to MOR, at least 7 (seven) days before the proposed closure of such section and shall be accompanied by particulars thereof. Within 3 (three) days of receiving such request, MOR shall grant permission with such modifications as it may deem necessary. Provided that for closure of any one track way for a period not exceeding 2 (two) hours in a day, the Developer shall give prior notice of not less than 2 (two) hours for seeking approval of MOR for such proposed closure.
AutoNDA by SimpleDocs
Section closure. 17.13.1 Upon notice given by the Authority to this effect prior to commencement of an Accounting Year, the Concessionaire shall, save and except as provided in Clause 17.12, not schedule a closure of any part of the Project Facility at any time during a continuous period of 90 (ninety) days as may be specified by the Authority for and in respect of such Accounting Year.
Section closure. 16.7.1 Save and except as provided in Clause 16.6, the MDO shall not shut down or de- commission any section of the Mines for undertaking maintenance or repair works, not forming part of the Maintenance Programme, except with the prior written approval of HCL. Such approval shall be sought by the MDO through a written request to be made to HCL, at least 7 (seven) days before the proposed closure of such section and shall be accompanied by particulars thereof. HCL shall grant permission, with such modifications as it may deem necessary, within 7 (seven) days of receipt of such a written request.
Section closure. 6.1 The Concessionaire shall not close any section of the Project Installations for undertaking maintenance or repair works except with the prior written approval of the Quality Assurance Inspector. Such approval shall be sought by the Concessionaire through a written request to be made to the Quality Assurance Inspector, and a copy thereof furnished to the Concessioning Authority, at least seven (7) days before the proposed closure of such section and shall be accompanied by particulars thereof. Within three (3) days of receiving such request, the Quality Assurance Inspector shall grant permission with such modifications as it may deem necessary and a copy of such permission shall be sent to the Authority.