SCHEDULE OF THE WORK Sample Clauses

SCHEDULE OF THE WORK. 6.2.1 Before submitting the first application for payment, the Construction Manager shall submit to the Owner and, if directed, the Design Professional a Schedule of the Work showing the dates on which the Construction Manager plans to commence and complete various parts of the Work, including dates on which information and approvals, self-performed work, selection of allowance items, and other known Owner services, tasks and work are required from the Owner. The Construction Manager shall comply with the approved Schedule of the Work, unless directed by the Owner to do otherwise or the Construction Manager is otherwise entitled to an adjustment in the Contract Time. The Construction Manager shall update the Schedule of the Work on a monthly basis or at appropriate intervals as required by the conditions of the Work and the Project.
AutoNDA by SimpleDocs
SCHEDULE OF THE WORK. 7.2.1 Before submitting the first application for payment, the Construction Manager shall submit to the Owner and, if directed, the Design Professional a Schedule of the Work showing the dates on which the Construction Manager plans to commence and complete various parts of the Work, including dates on which information and approvals are required from the Owner. The Construction Manager shall comply with the approved Schedule of the Work, unless directed by the Owner to do otherwise or the Construction Manager is otherwise entitled to an adjustment in the Contract Time. The Construction Manager shall update the Schedule of the Work on a monthly basis or at appropriate intervals as required by the conditions of the Work and the Project.
SCHEDULE OF THE WORK. The Design Builder shall prepare and submit a Schedule of Work for the Owner’s acceptance and written approval as to milestone dates. This Schedule shall indicate the dates for the start and completion of the various stages of the Work, including the dates when information and approvals are required from the Owner. The Schedule shall be revised as required by the conditions of the Work.
SCHEDULE OF THE WORK. 3.4.1 The Design-Builder shall:
SCHEDULE OF THE WORK. The Subcontractor is responsible for the sequencing, scheduling and coordinating of the Work, for monitoring the progress of the Work, and for taking appropriate action to keep the Work on schedule. Within two weeks after signing the Subcontract, unless otherwise extended by the Contractor at the time of the signing of the Subcontract, the Subcontractor shall prepare and submit to the Contractor a preliminary schedule for accomplishing the Work based upon the completion time stated in the Subcontract. A fully complete progress schedule for accomplishing the work must be submitted in like manner no later than 60 days after signing the Subcontract. No progress payments will be payable to the Subcontractor until after it has submitted a preliminary schedule which is acceptable to the Contractor. Neither the second progress payment nor any subsequent payment shall be payable to the Subcontractor until it has submitted a fully complete progress schedule.
SCHEDULE OF THE WORK. 6.2.1 Before submitting its first application for payment, Construction Manager shall submit to Owner and, if directed, Design Professional a Schedule of the Work showing the dates on which Construction Manager plans to begin and complete various parts of the Work, including dates on which information and approvals are required from Owner. Except as otherwise directed by Owner, Construction Manager shall comply with the approved Schedule of the Work . Unless otherwise agreed, the Schedule of the Work shall be formatted in a detailed precedence-style critical path method that (a) provides a graphic representation of all activities and events, including float values that will affect the critical path of the Work and (b) identifies dates that are critical to ensure timely and orderly completion of the Work. Construction Manager shall update the Schedule of the Work on a monthly basis or as mutually agreed by the Parties.
SCHEDULE OF THE WORK. General: The Contractor is responsible for the scheduling and sequencing of the Work, for coordinating the Work, for monitoring the progress of the Work, and for taking appropriate action to keep the Work on schedule to finish on or before the Contract Completion Date. The Contractor may attempt to achieve Substantial Completion before the Contract Completion Date and receive payment in accordance with Section 36 for the Work completed each period. However, the Contract Completion Date shall be used in all schedules and schedule updates as the deadline for which Substantial Completion is to be achieved. The time (in Days) between the Contractor’s planned early completion and the Contract Completion Date is part of the Float. Extensions of time allowed pursuant to Sections 38, 39, and 43, the determination of any compensation for compensable delay, and all other matters between the Owner and the Contractor will be determined using the Contract Completion Date, not an earlier Substantial Completion date planned by the Contractor. Within two (2) weeks after the Contractor signs the Contract, unless otherwise extended by the Owner at the time of the signing, the Contractor shall prepare and submit to the Owner, with a copy to the A/E, a schedule for achieving Substantial Completion by the Contract Completion Date. The preliminary schedule shall be in sufficient detail to show the sequencing of the various trades for each floor level, wing or work area. The Owner will notify the Contractor of any comments on the preliminary schedule within fifteen (15) Days of receipt by the Owner. A fully complete Project schedule meeting the requirements set forth below in subparagraph (1) or (2), as applicable, must be submitted no later than sixty (60) Days after the Contract is signed by the Owner.
AutoNDA by SimpleDocs
SCHEDULE OF THE WORK 

Related to SCHEDULE OF THE WORK

  • SCHEDULE OF SERVICES Consultant shall perform the Services within the Term of this Agreement, in accordance with the Schedule of Services set forth in Exhibit “B” attached hereto and incorporated herein by reference, and in accordance with any other completion schedule or milestones which may be separately agreed upon in writing by the Parties. Consultant represents that it has the professional and technical personnel required to perform the Services in conformance with such conditions. In order to facilitate Consultant’s conformance with the Schedule, City shall respond to Consultant’s submittals in a timely manner. Upon request of City, Consultant shall provide a more detailed schedule of anticipated performance to meet the Schedule of Services.

  • Work Schedule A 4/10 work schedule is four (4) ten hour days in a seven (7) day period, for a total of forty (40) hours per week.

  • CONVERSION SCHEDULE The Original Issue Discount Senior Convertible Debentures due on March 1, 2018 in the aggregate principal amount of $385,000 are issued by Legend Oil and Gas, Ltd., a Colorado corporation. This Conversion Schedule reflects conversions made under Section 4 of the above referenced Debenture. Dated: Date of Conversion (or for first entry, Original Issue Date) Amount of Conversion Aggregate Principal Amount Remaining Subsequent to Conversion (or original Principal Amount) Company Attest

  • Construction Schedule The progress schedule of construction of the Project as provided by Developer and approved by District.

  • Contract Schedule The information set forth in the Contract Schedule is true and correct.

  • Work Location While employed by the Company hereunder, the Executive shall perform his duties (when not traveling or engaged elsewhere in the performance of his duties) at the offices of the Company in Bermuda. The Executive shall travel to such places on the business of the Company in such manner and on such occasions as the Company may from time to time reasonably require.

  • Project Schedule Construction must begin within 30 days of the date set forth in Appendix A, Page 2, for the start of construction, or this Agreement may become null and void, at the sole discretion of the Director. However, the Recipient may apply to the Director in writing for an extension of the date to initiate construction. The Recipient shall specify the reasons for the delay in the start of construction and provide the Director with a new start of construction date. The Director will review such requests for extensions and may extend the start date, providing that the Project can be completed within a reasonable time frame.

  • Schedule The Work shall be performed as expeditiously as possible in conformity with the schedule requirements contained herein and in the Statement of Work. The draft and final versions of all deliverables shall be submitted by the dates specified in the Exhibit A Schedule and Project Period noted in Item No. 7 of this Agreement. It is understood and agreed that the delivery of the draft and final versions of such deliverables by the Contractor shall occur in a timely manner and in accordance with the requirements of the Exhibit A Schedule.

  • Punch List If, at any time after the Project has been Physically Completed, there shall exist any item or items requiring completion or correction, then the Developer agrees to use all reasonable diligence to complete or correct such item or items so that each conforms to the Final Plans. The parties shall make a Punch-List of the items requiring completion or correction (the "Punch List"). Each item on the Punch-List shall be assigned a reasonable value based upon the reasonable cost of completion or correction of the same or such other value as may be required by the Owner's lender ("Punch-List Amount"). The Developer shall give its written undertaking to complete each such item within forty-five (45) days (or such other period of time as is mutually agreed upon by the parties).

  • Collateral Schedules and Locations Insofar as the Collateral consists of inventory, Grantor shall deliver to Lender, as often as Lender shall require, such lists, descriptions, and designations of such Collateral as Lender may require to identify the nature, extent, and location of such Collateral. Such information shall be submitted for Grantor and each of its subsidiaries or related companies.

Time is Money Join Law Insider Premium to draft better contracts faster.