Schedule Delay Sample Clauses

Schedule Delay. To the extent that the time initially established for the completion of CONSULTANT'S services is exceeded or extended through no fault of the CONSULTANT, compensation for any services rendered during the additional period of time may be computed as follows: at standard hourly rates. See Attachment B or as a fixed fee.
AutoNDA by SimpleDocs
Schedule Delay. Xxxxxxx does not undertake that the Goods will be transported from or loaded at the place of receiving or loading or will arrive at the place of discharge, delivery or transshipment aboard any particular vessel or other conveyance or at any particular date or time or to meet any particular market or in time for any particular use. Scheduled or advertised departure and arrival times are only expected times and may be advanced or delayed if carrier or any connecting carrier shall find it necessary, prudent or convenient. Carrier shall not be liable for any loss or damages whatsoever, including but not limited to incidental or consequential damages (even if Carrier is advised of the possibility of same), due in whole or in part to any delay in the scheduled departures or arrivals of the Vessel or other conveyances transporting the Goods.
Schedule Delay. To the extent that the time initially established for the completion of ARCHITECT'S services is exceeded or extended through no fault of the ARCHITECT, compensation for any services rendered during the additional period of time may be computed as follows: at standard hourly rates (See Attachment B) or as a fixed fee.
Schedule Delay. To the extent that the time initially established for the completion of CM's services is exceeded or extended through no fault of the CM, compensation for any services rendered during the additional period of time may be computed as follows: at standard hourly rates. See Exhibit (attached with Sample Agreement) or as a fixed fee.
Schedule Delay. A. Unless otherwise directed by the City, Consultant shall commence performance of the Services upon execution of this Agreement.
Schedule Delay. To the extent that the time initially established for the completion of CS’S services is exceeded or extended through no fault of the CS, compensation for any services rendered during the additional period of time may be computed as follows: at standard hourly rates. See Exhibit A or as a fixed fee.
Schedule Delay. The labor, materials, goods and services required of Vendor herein shall be provided as required by Xxxxxx-Xxxx, Inc. In the event Vendor delays the progress of Xxxxxx- Xxxx, Inc.’s work at the project due to late delivery of materials or goods or late provision of labor or services, Vendor shall be liable for all damages arising from or caused by such delay, including all liquidated damages imposed on Xxxxxx-Xxxx, Inc. by owner or General Contractor on account of such delay.
AutoNDA by SimpleDocs
Schedule Delay. Carrier does not undertake that the Goods will be transported from or loaded at the place of receiving or loading or will arrive at the place of discharge, delivery or transshipment aboard any particular vessel or other conveyance or at any particular date or time or to meet any particular market or in time for any particular use. Scheduled or advertised departure and arrival times are only expected times and may be advanced or delayed if carrier or any connecting carrier shall find it necessary, prudent or convenient. Carrier shall not be liable for any loss or damages whatsoever, including but not limited to incidental or consequential damages (even if Carrier is advised of the possibility of same), due in whole or in part to any delay in the scheduled departures or arrivals of the Vessel or other conveyances transporting the Goods.
Schedule Delay. MANUFACTURER shall ship all Products ordered by Company under this Section 1 in accordance with the shipping schedule and instructions set forth in Company’s applicable order under paragraph 1.1. Should MANUFACTURER anticipate that the shipment of any Products ordered by Company be delayed by any reason, MANUFACTURER shall notify Company thereof immediately, and thereafter MANUFACTURER and Company shall discuss in good faith on the shipment date of the Products. However, MANUFACTURER shall not be liable for any delay in shipment due to any causes that are beyond the reasonable control of MANUFACTURER and that cannot be overcome by MANUFACTURER’s exercise of reasonable diligence, provided that MANUFACTURER gives Company prompt notice of any circumstances that may give rise to any delay, the anticipated duration of delay and the action being taken by MANUFACTURER to mitigate the delay and that MANUFACTURER uses its reasonable best efforts to mitigate the delay.

Related to Schedule Delay

  • Excusable Delays Except with respect to defaults of subproviders, the Engineer shall not be in default by reason of any failure in performance of this contract in accordance with its terms (including any failure to progress in the performance of the work) if such failure arises out of causes beyond the control and without the default or negligence of the Engineer. Such causes may include, but are not restricted to, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather.

  • Excusable Delay The Contractor is entitled to an equitable adjustment of time, issued via Change Order, for delays caused by the following:

  • Force Majeure Delays In any case where either party hereto is required to do any act (other than the payment of money), delays caused by or resulting from Acts of God or Nature, war, civil commotion, fire, flood or other casualty, labor difficulties, shortages of labor or materials or equipment, government regulations, delay by government or regulatory agencies with respect to approval or permit process, unusually severe weather, or other causes beyond such party’s reasonable control the time during which act shall be completed, shall be deemed to be extended by the period of such delay, whether such time be designated by a fixed date, a fixed time or “a reasonable time.”

  • Tenant Delays A "Tenant Delay” shall be defined as any delay in the design, permitting or performance of the Base Building Work to the extent that such delay is actually caused by any act or, where there is a duty to act under this Lease, any failure to act by Tenant or Tenant's contractors, architects, engineers, or anyone else engaged by or on behalf of Tenant in connection with the construction of the Tenant Improvement Work as set forth in this Article III (including, without limitation, any delays resulting from the Approved Tenant Finishes under Section 3.l(C) above) and disclosed to Tenant as hereinafter provided. Notwithstanding the foregoing, in no event shall any delays in the completion of the Base Building Work caused by Tenant’s use of non-union labor constitute a Tenant Delay hereunder. Notwithstanding the foregoing, no event shall be deemed a Tenant Delay unless and until Landlord has given Tenant written notice (the "Tenant Delay Notice") advising Tenant: (x) that a Tenant Delay is occurring and setting forth Landlord's good faith estimate as to the likely length of such Tenant Delay; (y) of the basis on which Landlord has determined that a Tenant Delay is occurring; and (z) the actions which Landlord believes that Tenant must take to eliminate such Tenant Delay. No event shall be deemed to be a Tenant Delay unless and until Tenant has failed to rectify the situation causing the Tenant Delay within forty-eight (48) hours after Tenant's receipt of the Tenant Delay Notice (which for the purposes of determining receipt may be delivered by hand to Tenant's Construction Representative, with copies to follow to Tenant at the notice address set forth in Section 1.2 of this Lease within five (5) days thereafter); provided, however, that if Tenant shall fail to eliminate the delay within the aforesaid 48-hour period, then the 48-hour cure period shall be included in the period of time charged to Tenant pursuant to such Tenant Delay Notice (it being understood and agreed that if Tenant shall in fact eliminate the Tenant Delay within the 48-hour cure period, no Tenant Delay shall be deemed to have occurred for the purposes of this Article III). In addition, any delay to the extent caused by (i) Landlord Delay or (ii) subject to the limitations of subsection (D) below, Tenant's Force Majeure (as defined in said subsection (D)) shall not constitute Tenant Delay. Tenant covenants that no Tenant Delay shall delay commencement of the Term or the obligation to pay Annual Fixed Rent or Additional Rent. The Delivery Dates and/or the date of substantial completion of the Base Building Work, as applicable, shall be deemed to have occurred as of the date when such Delivery Dates and/or date of substantial completion of the Base Building Work, as applicable, would have occurred but for any Tenant Delays, as determined by Landlord in the exercise of its good faith business judgment (it being understood and agreed that the foregoing shall not be construed so as to relieve Landlord of its obligation to actually complete the Base Building Work, notwithstanding the fact that substantial completion may have been deemed to have occurred prior to actual completion as the result of Tenant Delays).

  • Construction Schedule The progress schedule of construction of the Project as provided by Developer and approved by District.

  • Commencement Date Delay Except as otherwise provided in the Lease, Delivery of the Premises shall occur when Landlord’s Work has been Substantially Completed, except to the extent that completion of Landlord’s Work shall have been actually delayed by any one or more of the following causes (“Tenant Delay”):

  • Project Schedule Construction must begin within 30 days of the date set forth in Appendix A, Page 2, for the start of construction, or this Agreement may become null and void, at the sole discretion of the Director. However, the Recipient may apply to the Director in writing for an extension of the date to initiate construction. The Recipient shall specify the reasons for the delay in the start of construction and provide the Director with a new start of construction date. The Director will review such requests for extensions and may extend the start date, providing that the Project can be completed within a reasonable time frame.

  • Additional Work If changes in the work seem merited by Consultant or the City, and informal consultations with the other party indicate that a change is warranted, it shall be processed in the following manner: a letter outlining the changes shall be forwarded to the City by Consultant with a statement of estimated changes in fee or time schedule. An amendment to this Agreement shall be prepared by the City and executed by both Parties before performance of such services, or the City will not be required to pay for the changes in the scope of work. Such amendment shall not render ineffective or invalidate unaffected portions of this Agreement.

  • Tenant Delay If the Substantial Completion of the Tenant Improvement Work is delayed (a “Tenant Delay”) as a result of (a) any failure of Tenant to approve the Construction Pricing Proposal pursuant to Section 2.6 above on or before Tenant’s Approval Deadline; (b) Tenant’s failure to timely approve any matter requiring Tenant’s approval; (c) any breach by Tenant of this Work Letter or the Lease; (d) any request by Tenant for a revision to the Approved Construction Drawings (except to the extent such delay results from any failure of Landlord to perform its obligations under Section 2.7 above); (e) Tenant’s requirement for materials, components, finishes or improvements that are not available in a commercially reasonable time given the anticipated date of Substantial Completion of the Tenant Improvement Work as set forth in this Agreement; (f) any change to the base, shell or core of the Premises or Building required by the Approved Construction Drawings; or (g) any other act or omission of Tenant or any of its agents, employees or representatives, then, notwithstanding any contrary provision of this Agreement, and regardless of when the Tenant Improvement Work is actually Substantially Completed, the Tenant Improvement Work shall be deemed to be Substantially Completed on the date on which the Tenant Improvement Work would have been Substantially Completed if no such Tenant Delay had occurred.

  • Work Schedule A 4/10 work schedule is four (4) ten hour days in a seven (7) day period, for a total of forty (40) hours per week.