Risk Register. 10.5 The ICB must maintain a risk register in respect of its exercise of the Delegated Functions and periodically review its content. The risk register must follow such format as may be notified by NHS England to the ICB from time to time.
Risk Register. Consultant shall prepare and maintain a Risk Register that identifies project risks, probabilities, mitigation measures, and ownership using the Program’s Risk Matrix and Assessment template. The Risk Register shall list interfaces with other projects, possible schedule impacts, and contingency plans. The Risk Register shall be updated on a monthly basis and submitted with Monthly Progress Reports.
Risk Register a. The initial Risk Register shall be provided within thirty (30) Business Days of the NTP in an electronic editable file format.
Risk Register the Contractor shall document risks that might affect the project and the characteristics of the risk defined by the ITS JPO. The TOCOR will provide a Microsoft Excel-based Risk Register template for the Contractor to populate and update as necessary. Each risk shall have a unique number, probability of occurrence and impact of occurrence rating. The risk log shall be updated monthly and submitted with monthly progress reports.
Risk Register. A listing of risks and opportunities, risk assessments, and an evaluation of mitigation and responsibility for those risks.
Risk Register the Contractor shall document risks that might affect the project and the characteristics of the risk defined by the ITS JPO. The COR will provide a Microsoft Excel- based Risk Register template for the Contractor to populate and update as necessary. Each risk shall have a unique number, probability of occurrence and impact of occurrence rating. The risk log shall be updated monthly and submitted with monthly progress reports.
Risk Register. (a) Risks that have been identified and priced pursuant to a risk analysis and included in the risk register, will be included in Target Cost. When a proposed method of dealing with the risk has been identified, the projected Chargeable Costs for the solution will replace the risk register for that risk in the Target Cost. If the projected Chargeable Cost for an item is less than what has been carried in the risk register, those remaining funds will be moved from the risk registry into the Cost Model and will be part of any surplus of funds available for shared savings. Once Construction begins, if a new risk is identified, it will be included in the risk register, however the Target Cost will not be adjusted.
Risk Register a) The Contractor shall be responsible for maintaining a risk register, agreed at the kick-off meeting. This register shall identify potential risks, their likelihood and severity, and propose meaningful mitigation measures (see ECSS-M-00-03B for more details).
Risk Register. Service Provider is encouraged to maintain a listing of the risks (“Risk Register”) that are met by the controls as set forth in the Robustness Rules in Exhibit E and implemented by the Service Provider. Service Provider should ensure the Risk Register is kept up to date.
Risk Register. (Please update the Risk Register and attach a link to its location on your secure server. Please copy the original and rename it with the appropriate time period. For example. Risk_Register_Jan19_Mar19). SCHEDULE 10 CEPI POLICIES [*****] SCHEDULE 11 TEAM CHARTER [*****] SCHEDULE 12 DISCLOSURE LETTER [*****] SCHEDULE 13 PARTNER FUNDER REQUIREMENTS [*****]