Review Stages Sample Clauses

Review Stages. The Architect/Engineer shall submit documents to the Owner for review at completion of the Schematic Design Phase, Design Development Phase and at the following stages of completion of the Construction Documents Phase as follows: 50%, 100% The following Exhibits are fully incorporated into this Agreement by reference: EXHIBITS Ex A Personnel Titles and Hourly Rates Ex B BIM Execution Plan EXHIBIT A PERSONNEL TITLES AND HOURLY RATES The prime architectural or engineering firm for this project will assemble the following information from consulting team members associated with the project. The categories of personnel indicated should be edited to include only those expected to be actually working on this project. When preparing this schedule, you are expected to adhere to the position classifications and titles presented to the greatest extent possible. Additional consultant listings and/or position classifications may be added as needed or required by the project. FU irm/Position Classification UHourly Billing Rate Architecture [PBK] Principal $310.00 Associate Principal $275.00 Project Manager $250.00 Project Architect I $225.00 Project Architect II $225.00 Project Designer $225.00 Construction Administrator $130.00 Intern Architect $140.00 BIM/CADD Technician $140.00 Administrative Staff $100.00 MEP Engineering [Xxxxxxxx Xxxx Xxxxx, Inc.] Principal $277.00 Project Manager $201.00 Engineer $184.00 BIM/CADD Technician $136.00 Administrative Staff $ 95.00 Structural Engineering [IES] Principal $240.00 Project Manager $210.00 Senior Engineer $195.00 Engineer $180.00 BIM/CADD Technician $125.00 Administrative Staff $ 75.00 Civil Engineering [Xxxxxxx] Principal $240.00 Senior Project Manager $180.00 Project Manager $150.00 Senior Engineer $180.00 Engineer $150.00 Graduate Engineer $125.00 Engineering Designer $105.00 Construction Administrator $ 85.00 BIM/CADD Technician $ 80.00 Administrative Staff $ 75.00 Landscape Architecture [Edgeland] Principal $225.00 Landscape Architect $215.00 Administrative Staff $100.00 Cost Consultant [PBK] Principal $310.00 Senior Estimator $275.00 Estimator $225.00 Administrative Staff $100.00 Data/Telecommunications Consultant [DataCom] Principal $198.00 Senior Consultant $160.00 Consultant $138.00 Contract Administrator $ 98.00 BIM/CADD Technician $ 67.00 Administrative Staff $ 58.00 Security Consultant [DataCom] Principal $198.00 BIM/CADD Technician $ 67.00 Administrative Staff $ 58.00 EXHIBIT B BIM Execution Plan DEVELOPED BY ...
Review Stages. The Architect/Engineer shall submit documents to the Owner for review at completion of the 25%, 50%, and 100% Schematic Design Phase, 50% and 100% Design Development Phase and at the following stages of completion of the Construction Documents Phase as follows: 50%, 100% A/E -XXXX BIM Contract No. 6060 06/22 Project No. 15-3268 The following Exhibits are fully incorporated into this Agreement by reference: EXHIBITS Ex A Personnel Titles and Hourly Rates Ex B BIM Execution Plan EXHIBIT A PERSONNEL TITLES AND HOURLY RATES The prime architectural or engineering firm for this project will assemble the following information from consulting team members associated with the project. The categories of personnel indicated should be edited to include only those expected to be actually working on this project. When preparing this schedule, you are expected to adhere to the position classifications and titles presented to the greatest extent possible. Additional consultant listings and/or position classifications may be added as needed or required by the project. UFirm/Position Classification UHourly Billing Rate Architecture- Xxxxxx Xxxxxxxxx Xxxxxxx Architects Principal in Charge $315.00 Principal $290.00 Associate Principal $220.00 Senior Project Manager $215.00 Project Architect I $165.00 Project Architect II $190.00 Project Designer $175.00 Construction Administrator $180.00 Intern Architect $85.00 BIM/CADD Technician $185.00 Administrative Staff $80.00 Design Architecture- Bora Architecture & Interiors Principal $280.00 Associate Principal $200.00 Project Manager $166.00 Project Architect I $108.00 Project Architect II $119.00 Project Designer $143.00 Construction Administrator $143.00 Intern Architect $99.00 BIM/CADD Technician $174.00 Administrative Staff $106.00 MEP Engineering- Collaborative Engineering Group Principal $225.00 Associate Principal $225.00 Senior Project Manager $200.00 Project Manager $175.00 Senior Engineer $175.00 Engineer $150.00 Graduate Engineer $135.00 Engineering Designer $125.00 Construction Administrator $150.00 BIM/CADD Technician $95.00 Administrative Staff $75.00 Structural Engineering- JQ Principal $285.00 Associate Principal $245.00 Senior Project Manager $205.00 Project Manager $175.00 Senior Engineer $160.00 Engineer $145.00 Graduate Engineer $75.00 Engineering Designer $160.00 BIM/CADD Technician $140.00 Administrative Staff $90.00 Civil Engineering- JQ Principal $285.00 Associate Principal $245.00 Senior Project Manager $205...
Review Stages. The PSProvider shall submit documents to the Owner for review at completion of the Schematic Design Phase (if applicable), Design Development Phase and at the following stages of completion of the Construction Documents Phase as follows: 60%, 100%
Review Stages. The Architect/Engineer shall submit documents to the Owner for review at completion of the Schematic Design Phase, Design Development Phase and at the following stages of completion of the Construction Documents Phase as follows: (25% DD for GMP) & 25%, 50%, 75%, 100%
Review Stages. The Professional Services Provider shall submit CADD files and documents to the Owner for review at completion of the Schematic Design Phase, Design Development Phase and at the following stages of completion of the Construction Documents Phase: 50%, 95%, 100% 14.7 Not Used
Review Stages. The Project Architect shall submit all Project documents to the Owner as searchable .PDF and their native produced file format for review at each Design Phase as follows: Schematic Design: 50% and 100% Design Development: 50% and 100% Construction Documents: 50%, 75% and 100%
AutoNDA by SimpleDocs
Review Stages. There shall be four (4) design reviews at a 30% design stage (inhouse meeting with COUNTY), 60% pre-agency design stage, a 90% design stage, and a Final submittal. The COUNTY shall be allotted five (5) working days for review of the 60% submittal, 90% submittal, and Final submittal. All CADD-produced drawings shall be 24” X 36” at a true scale. Submittals of plans and support documentation shall be made at the following stages of plans completion with the indicated number of copies.

Related to Review Stages

  • Review Process A/E's Work Product will be reviewed by County under its applicable technical requirements and procedures, as follows:

  • ADB’s Review of Procurement Decisions 9. All contracts procured under international competitive bidding procedures and contracts for consulting services shall be subject to prior review by ADB, unless otherwise agreed between the Borrower and ADB and set forth in the Procurement Plan. SCHEDULE 5

  • Design Review At appropriate stages of design, documented reviews of the design results shall be planned and conducted. Participants at each Design Review shall include representatives of all functions concerned with the design stage being reviewed, as well as other specialist personnel, as required. Records of such reviews shall be maintained. Any computer software used to perform alternative calculations or verify clearances through the use of scale models or computer-aided design and drafting (CADD) techniques shall be validated before the use of the application, with validation documented in accordance with Section 2.2.15. In addition, at each submittal to IFA for review, Developer shall provide hand calculations that validate any calculations performed by computer software.

  • Project Review A. Programmatic Allowances