Return of Contract Performance Guarantee Sample Clauses

Return of Contract Performance Guarantee. 6.5.1 If the TSP fails to achieve COD of any of the Elements on their respective Scheduled COD specified in this Agreement, subject to conditions mentioned in Article 4.4, the Long Term Transmission Customers shall have the right to encash the Contract Performance Guarantee and appropriate in their favour as liquidated damages an amount specified in Article 6.4.1, without prejudice to the other rights of the Long Term Transmission Customers under this Agreement.
AutoNDA by SimpleDocs
Return of Contract Performance Guarantee. 6.5.1 The Contract Performance Guarantee as submitted by TSP in accordance with Article 3.1.1 shall be released by the Nodal Agency within three (3) months from the COD of the Project. In the event of delay in achieving Scheduled COD of any of the Elements by the TSP (otherwise than due to reasons as mentioned in Article
Return of Contract Performance Guarantee. 6.5.1 The Contract Performance Guarantee as submitted by TSP in accordance with Article
Return of Contract Performance Guarantee. 1.04.1 Subject to Article 1.03, MPPMCL, shall return/release the Performance Guarantee three (3) months after the commercial Operation date.
Return of Contract Performance Guarantee. 6.5.1 The Contract Performance Guarantee as submitted by TSP in accordance with Article 0 shall be released by the Nodal Agency within three (3) months from the COD of the Project. In the event of delay in achieving Scheduled COD of any of the Elements by the TSP (otherwise than due to reasons as mentioned in Article 0 or Article 0) and consequent part invocation of the Contract Performance Guarantee by the Nodal Agency, Nodal Agency shall release the Contract Performance Guarantee, if any remaining unadjusted, after the satisfactory completion by the TSP of all the requirements regarding achieving the Scheduled COD of the remaining Elements of the Project. It is clarified that the Nodal Agency shall also return/release the Contract Performance Guarantee in the event of (i) applicability of Article 0 to the extent the Contract Performance Guarantee is valid for an amount in excess of Rs.5.91 Crore (Rupees Five Crore Ninety One Lakh Only), or (ii) termination of this Agreement by the Nodal Agency as mentioned under Article 0 of this Agreement.
Return of Contract Performance Guarantee. 3.8.1 The Procurer shall return / release the Contract Performance Guarantee in the event of (i) applicability of Article 3.4.2 to the extent the Contract Performance Guarantee is valid for an amount in excess of Rupees ………………… ( ) [Insert amount not less than that derived on the basis of 40.00 lakhs per MW of the Contracted Capacity], or (ii) termination of this Agreement by any Party under Article 3.4.3, 3.4.4 or Article 3.4.5 of this Agreement.
Return of Contract Performance Guarantee. 3.4.1 The Procurer(s) shall return / release the Contract Performance Guarantee in the event of termination of this Agreement by Seller for Procurer(s) default within 30 days.
AutoNDA by SimpleDocs
Return of Contract Performance Guarantee. 3.8.1 The Procurer(s) shall return / release the Contract Performance Guarantee in the event of

Related to Return of Contract Performance Guarantee

  • Performance Guarantee 9.4.1 The Concessionaire shall, for the performance of its obligations hereunder during the Concession Period, provide to the Authority no later than [90] days prior to expiry of the Performance Security, an irrevocable and unconditional guarantee from a Bank for a sum equivalent to Rs. ***** crore (Rupees ***** crore)7 in the form set forth in Schedule-FF (the “Performance Guarantee”). Until such time the Performance Guarantee is provided by the Concessionaire pursuant hereto and the same comes into effect, notwithstanding anything contained in clause 9.3 the Performance Security shall remain in force and effect, and upon such provision of the Performance Guarantee pursuant hereto, the Authority shall release the Performance Security to the Concessionaire.

  • Continuing Contract Performance Pending final resolution of a Claim including litigation, unless otherwise agreed in writing the Contractor shall proceed diligently with performance of the Contract and the Owner shall continue to make payments in accordance with the Contract Documents.

  • F2 Monitoring of Contract Performance F2.1 The Contractor shall immediately inform the Authority if any aspect of the Contract is not being or is unable to be performed, the reasons for non-performance, any corrective action and the date by which that action will be completed.

  • Monitoring of Contract Performance The Contractor shall comply with the monitoring arrangements set out in the Monitoring Schedule including, but not limited to, providing such data and information as the Contractor may be required to produce under the Contract.

  • CALL-OFF CONTRACT PERFORMANCE 12.1 The Supplier shall perform all its obligations under all Call-Off Contracts entered into with the Authority or any Other Contracting Body:

  • Performance Guarantees Contractor agrees to provide the County the performance guarantees specified in Attachment A and to pay any penalties incurred in accordance with the terms of Attachment A.

  • Continuing Performance Each party is required to continue to perform its obligations under this contract pending final resolution of any dispute arising out of or relating to this contract, unless to do so would be impossible or impracticable under the circumstances.

  • Return of Performance Bank Guarantee Payment on Order Instrument

  • Payment Guarantee 20.1 On Contracts where one hundred (100%) percent performance bonds and payment bonds are executed, this Article 20 does not apply.

  • Contract Performance C19.1 The Contractor shall ensure that: