Rescheduling of Tests. If the Independent Monitor[s] certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 4 contracts
Samples: Concession Agreement, Concession Agreement, Concession Agreement
Rescheduling of Tests. If the Independent Monitor[s] Expert certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-re- schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 3 contracts
Samples: Draft Concession Agreement, Draft Concession Agreement, Draft Concession Agreement
Rescheduling of Tests. If the Independent Monitor[s] Expert certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-re- schedule the Tests and hold the same as soon as reasonably practicable. Provided, however, that the Concessionaire shall be excused for the delay in Tests arising hereunder if such delay is not solely attributable to the Concessionaire.
Appears in 1 contract
Samples: niti.gov.in
Rescheduling of Tests. If the Independent Monitor[s] certifies to the Implementing Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-re- schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 1 contract
Samples: Model Concession Agreement
Rescheduling of Tests. If the Independent Monitor[s] Monitor certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 1 contract
Samples: Concession Agreement
Rescheduling of Tests. If the Independent Monitor[s] Monitor certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 1 contract
Samples: Concession Agreement
Rescheduling of Tests. If the Independent Monitor[s] Expert certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. Provided, however, that the Concessionaire shall be excused for the delay in Tests arising hereunder if such delay is not solely attributable to the Concessionaire.
Appears in 1 contract
Samples: fci.gov.in