Common use of Rescheduling of Tests Clause in Contracts

Rescheduling of Tests. If the Independent Engineer certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. ENTRY INTO COMMERCIAL SERVICE

Appears in 23 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

AutoNDA by SimpleDocs

Rescheduling of Tests. If the Independent Engineer certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-re- schedule the Tests and hold the same as soon as reasonably practicable. ENTRY INTO COMMERCIAL SERVICE.

Appears in 16 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

Rescheduling of Tests. If the Independent Engineer or the Independent Panel, as the case may be, certifies to the Authority and the Concessionaire that it is unable to certify the completion of the facilities required for rendering the Services or issue the Completion Certificate or Provisional Certificatefor Project, as the case may be, because of events or circumstances on account of which the Completion Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Completion Tests and hold the same as soon as reasonably practicable. ENTRY INTO COMMERCIAL SERVICE.

Appears in 6 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

Rescheduling of Tests. If the Independent Engineer certifies to the Authority MPRDC and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. ENTRY INTO COMMERCIAL SERVICE.

Appears in 3 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

Rescheduling of Tests. If the Independent Engineer certifies to the Authority Government and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. ENTRY INTO COMMERCIAL SERVICE.

Appears in 3 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

Rescheduling of Tests. β€Œ If the Independent Engineer certifies to the Concessioning Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. ENTRY INTO COMMERCIAL SERVICE.

Appears in 3 contracts

Samples: Draft Concession Agreement, Concession Agreement, Concession Agreement

Rescheduling of Tests. If the Independent Engineer Expert certifies to the Contracting Authority and the Concessionaire Service Provider that it is unable to issue the Completion Certificate or Provisional Certificate, Certificate (as the case may be, ) because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire Service Provider shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. ENTRY INTO COMMERCIAL SERVICECLAUSE 15

Appears in 2 contracts

Samples: Project Agreement, Project Agreement

Rescheduling of Tests. If the Independent Engineer certifies to the Authority Participating ULBs and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. ENTRY INTO COMMERCIAL SERVICE.

Appears in 2 contracts

Samples: Model Concession Agreement, Model Concession Agreement

Rescheduling of Tests. If the Independent Engineer or the Independent Panel certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. ENTRY INTO COMMERCIAL SERVICE.

Appears in 2 contracts

Samples: Substitution Agreement, Stamp Paper

Rescheduling of Tests. xxx.xxxxxx.xxx Downloaded If the Independent Engineer certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. ENTRY INTO COMMERCIAL SERVICE

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

Rescheduling of Tests. If the Independent Engineer certifies to the TNRDC and Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. ENTRY INTO COMMERCIAL SERVICE.

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

Rescheduling of Tests. If the Independent Engineer certifies to the Authority MPRDC and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests Test and hold the same as soon as reasonably practicable. ENTRY INTO COMMERCIAL SERVICE.

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

Rescheduling of Tests. If the Independent Engineer certifies to the Authority TNRDC and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-re- schedule the Tests and hold the same as soon as reasonably practicable. ENTRY INTO COMMERCIAL SERVICE.

Appears in 1 contract

Samples: Concession Agreement

AutoNDA by SimpleDocs

Rescheduling of Tests. 14.6.1 If the Independent Engineer certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. ENTRY INTO COMMERCIAL SERVICE.

Appears in 1 contract

Samples: Concession Agreement

Rescheduling of Tests. If the Independent Engineer certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. ENTRY INTO COMMERCIAL SERVICE.

Appears in 1 contract

Samples: Draft Concession Agreement

Rescheduling of Tests. xxx.xxxxxx.xxx If the Independent Engineer certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. ENTRY INTO COMMERCIAL SERVICE.

Appears in 1 contract

Samples: Concession Agreement

Rescheduling of Tests. If the Independent Engineer certifies to the Concessioning Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. ENTRY INTO COMMERCIAL SERVICE.

Appears in 1 contract

Samples: Draft Concession Agreement

Rescheduling of Tests. If the Independent Engineer certifies to the Authority / SSNNL / FED and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. ENTRY INTO COMMERCIAL SERVICE.

Appears in 1 contract

Samples: Concession Agreement

Rescheduling of Tests. If the Independent Engineer certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule reschedule the Tests and hold the same as soon as reasonably practicable. ENTRY INTO COMMERCIAL SERVICE.

Appears in 1 contract

Samples: Concession Agreement

Rescheduling of Tests. oject If the Independent Engineer certifies to the Authority MOPIT and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. ENTRY INTO COMMERCIAL SERVICE.

Appears in 1 contract

Samples: Concession Agreement