Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 49 contracts
Samples: Draft Contract Agreement, Draft Contract Agreement, Draft Contract Agreement
Rescheduling of Tests. If the Authority’s Independent Engineer certifies to the Authority and the Contractor Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 47 contracts
Samples: Concession Agreement, Concession Agreement, Concession Agreement
Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 17 contracts
Samples: Model Agreement, Draft Contract Agreement, And Construction)
Rescheduling of Tests. If the Authority’s Authority Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 11 contracts
Samples: And Construction Agreement, And Construction Agreement, And Construction Agreement
Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 10 contracts
Samples: Draft Contract Agreement, nhidcl.com, nhidcl.com
Rescheduling of Tests. If the Authority’s Independent Engineer certifies to the Authority MOR and the Contractor Concessionaire that it is unable to issue the Completion Certificate, as the case may be, Certificate because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 7 contracts
Samples: Model Agreement, Model Agreement, Model Agreement
Rescheduling of Tests. If the Authority’s Authority‟s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 6 contracts
Samples: Procurement and Construction, Procurement and Construction Agreement, Agreement
Rescheduling of Tests. If the Authority’s Independent Engineer certifies to the Authority and the Contractor Concessionaire that it is unable to issue the Completion Certificate, as the case may be, Certificate because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 5 contracts
Samples: Concession Agreement, Model Concession Agreement, Concession Agreement
Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-re- schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 4 contracts
Samples: Draft Contract Agreement, Draft Contract Agreement, Construction Agreement
Rescheduling of Tests. If the AuthorityEmployer’s Engineer certifies to the Authority Employer and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 3 contracts
Samples: Epc Contract Agreement, And Construction Agreement, Contract Agreement for Design and Construction
Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor theContractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.. Drafit Contract Agreement
Appears in 3 contracts
Samples: Draft Contract Agreement, Draft Contract Agreement, Draft Contract Agreement
Rescheduling of Tests. If the Authority’s Employer's Engineer certifies to the Authority Employer and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 3 contracts
Samples: Epc Agreement, Epc Agreement, Procurement and Construction
Rescheduling of Tests. If the Authority’s Engineer Engineer-in-Charge certifies to the Authority and the Contractor Concessionaire that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor Concessionaire shall be entitled to re-re- schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 1 contract
Samples: Concession Agreement
Rescheduling of Tests. If the Authority’s Authority‟s Engineer certifies to the Authority and the Contractor Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 1 contract
Samples: Concession Agreement
Rescheduling of Tests. If the Authority’s Authority‟s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 1 contract
Samples: nhidcl.com
Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.. Improvement and widening to two lane with paved shoulder of road from Km 21.100 to Km
Appears in 1 contract
Samples: Draft Contract Agreement
Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor Concessionaire shall be entitled to re-re- schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 1 contract
Samples: Model Concession Agreement
Rescheduling of Tests. If the Authority’s AUTHORITY’S/GMDAs Engineer certifies to the Authority Authority/GMDA and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 1 contract
Samples: Engineering Procurement And
Rescheduling of Tests. If the Authority’s 's Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 1 contract
Samples: Draft Contract Agreement
Rescheduling of Tests. If the Authority’s Independent Engineer certifies to the Authority SH&DB and the Contractor DEVELOPER that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor DEVELOPER shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 1 contract
Samples: Agreement
Rescheduling of Tests. If the Authority’s Employer‟s Engineer certifies to the Authority Employer and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 1 contract
Rescheduling of Tests. If the Authority’s Engineer Engineer-in-charge certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 1 contract
Samples: Contract Agreement
Rescheduling of Tests. If the Authority’s Engineer designated Officer certifies to the Concessioning Authority and the Contractor Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 1 contract
Samples: Concession Agreement
Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.. Draft Contract AgreementPage 80 of 145 Aug. 2020 Article 13 Change of Scope 13.1
Appears in 1 contract
Samples: Draft Contract Agreement
Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.. Change of Scope
Appears in 1 contract
Samples: Draft Contract Agreement
Rescheduling of Tests. If the AuthorityEmployer’s Engineer certifies to the Authority Employer and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 1 contract
Samples: Contract Agreement
Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 1 contract
Samples: Concession Agreement
Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.. Drafit Contract Agreement
Appears in 1 contract
Samples: Draft Contract Agreement
Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 1 contract
Samples: Draft Contract Agreement