Common use of Rescheduling of Tests Clause in Contracts

Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 49 contracts

Samples: Draft Contract Agreement, Draft Contract Agreement, Draft Contract Agreement

AutoNDA by SimpleDocs

Rescheduling of Tests. If the Authority’s Independent Engineer certifies to the Authority and the Contractor Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 47 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 17 contracts

Samples: Model Agreement, Draft Contract Agreement, And Construction)

Rescheduling of Tests. If the Authority’s Authority Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 11 contracts

Samples: And Construction Agreement, And Construction Agreement, And Construction Agreement

Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 10 contracts

Samples: Draft Contract Agreement, nhidcl.com, nhidcl.com

Rescheduling of Tests. If the Authority’s Independent Engineer certifies to the Authority MOR and the Contractor Concessionaire that it is unable to issue the Completion Certificate, as the case may be, Certificate because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 7 contracts

Samples: Model Agreement, Model Agreement, Model Agreement

Rescheduling of Tests. If the Authority’s Authority‟s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 6 contracts

Samples: Procurement and Construction, Procurement and Construction Agreement, Agreement

Rescheduling of Tests. If the Authority’s Independent Engineer certifies to the Authority and the Contractor Concessionaire that it is unable to issue the Completion Certificate, as the case may be, Certificate because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 5 contracts

Samples: Concession Agreement, Model Concession Agreement, Concession Agreement

Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-re- schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 4 contracts

Samples: Draft Contract Agreement, Draft Contract Agreement, Construction Agreement

Rescheduling of Tests. If the AuthorityEmployer’s Engineer certifies to the Authority Employer and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 3 contracts

Samples: Epc Contract Agreement, And Construction Agreement, Contract Agreement for Design and Construction

Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor theContractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.. Drafit Contract Agreement

Appears in 3 contracts

Samples: Draft Contract Agreement, Draft Contract Agreement, Draft Contract Agreement

Rescheduling of Tests. If the Authority’s Employer's Engineer certifies to the Authority Employer and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 3 contracts

Samples: Epc Agreement, Epc Agreement, Procurement and Construction

Rescheduling of Tests. If the Authority’s Engineer Engineer-in-Charge certifies to the Authority and the Contractor Concessionaire that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor Concessionaire shall be entitled to re-re- schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Concession Agreement

Rescheduling of Tests. If the Authority’s Authority‟s Engineer certifies to the Authority and the Contractor Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Concession Agreement

Rescheduling of Tests. If the Authority’s Authority‟s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: nhidcl.com

Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.. Improvement and widening to two lane with paved shoulder of road from Km 21.100 to Km

Appears in 1 contract

Samples: Draft Contract Agreement

Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor Concessionaire shall be entitled to re-re- schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Model Concession Agreement

Rescheduling of Tests. If the Authority’s AUTHORITY’S/GMDAs Engineer certifies to the Authority Authority/GMDA and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Engineering Procurement And

AutoNDA by SimpleDocs

Rescheduling of Tests. If the Authority’s 's Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Draft Contract Agreement

Rescheduling of Tests. If the Authority’s Independent Engineer certifies to the Authority SH&DB and the Contractor DEVELOPER that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor DEVELOPER shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Agreement

Rescheduling of Tests. If the Authority’s Employer‟s Engineer certifies to the Authority Employer and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Procurement and Construction Agreement

Rescheduling of Tests. If the Authority’s Engineer Engineer-in-charge certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Contract Agreement

Rescheduling of Tests. If the Authority’s Engineer designated Officer certifies to the Concessioning Authority and the Contractor Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Concession Agreement

Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.. Draft Contract AgreementPage 80 of 145 Aug. 2020 Article 13 Change of Scope 13.1

Appears in 1 contract

Samples: Draft Contract Agreement

Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.. Change of Scope

Appears in 1 contract

Samples: Draft Contract Agreement

Rescheduling of Tests. If the AuthorityEmployer’s Engineer certifies to the Authority Employer and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Contract Agreement

Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Concession Agreement

Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.. Drafit Contract Agreement

Appears in 1 contract

Samples: Draft Contract Agreement

Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Draft Contract Agreement