Requests for Change Orders Sample Clauses

Requests for Change Orders. Within ten (10) days of submitting its Notice of Claim, the Construction Manager shall submit to the Owner its Request for Change Order, which shall include a written statement of all details of the claim, including a description of the Work affected, the time extension requested (if any), and the amount sought for the claim. Waiver - The Construction Manager agrees that the Owner shall not be liable for any claim that the Construction Manager fails to submit as a Notice of Claim and Request for Change Order as provided in this paragraph. Any claim not so submitted shall be deemed waived.
AutoNDA by SimpleDocs
Requests for Change Orders. (i) Any SCA request for a Change Order shall be submitted to Developer in writing. SCA requests for Change Orders shall be subject to Developer’s approval, not to be unreasonably withheld, provided, that it shall not be deemed unreasonable for Developer to withhold its approval for any Change Order which:
Requests for Change Orders. Subject to the criteria in Sections 9.1(b) and (c) the following occurrences or circumstances shall entitle Contractor or Owner to a change to the Work and/or related obligations hereunder in accordance with the provisions of this Article 9 (each a “Change”):
Requests for Change Orders. R A F T 12.6.1 Subject to the other terms of the Agreement, if the Contractor believes that any act, error, or omission of GLWA constitutes a change in the Work entitling it to additional compensation, it shall within twenty (20) days after the date on which the Contractor discovers, or should with the exercise of appropriate diligence have discovered, the pertinent act, error or omission of GLWA (provided that the necessity of extra cost and/or time is already determinable, even if such extra cost and/or time has not yet been incurred), submit a Request for Change Order to the Contracting Officer stating the amount of the additional compensation or additional time to which it is entitled and justifying the request. The Contracting Officer shall evaluate the Request for Change Order within a reasonable period of time and advise the Contractor whether GLWA will xxxxx, xxxxx in part, or deny the Request for Change Order. Any additional compensation granted shall be recorded in the form of a Change Order. Failure of the Contractor to timely submit a Request for Change Order strictly (not substantially) in accordance with the requirements of this Section 12.6.1 shall constitute a waiver of and shall forever bar any recovery arising out of the pertinent act, error or omission of GLWA, even if GLWA was not prejudiced thereby.
Requests for Change Orders. The provisions of this Section 11.6 shall apply only if the Prompt Pay Act is applicable to a Project, and shall be null and void and of no force or effect for Projects to which the Prompt Pay Act does not apply.
Requests for Change Orders 

Related to Requests for Change Orders

  • Change Orders Any alteration or deviation from the Services mentioned or any other contractual specifications that result in a revision of this Agreement shall be executed and attached to this Agreement as a change order (“Change Order”).

  • SUBMITTALS Submittals required by the Contract Documents shall be prepared specifically for the Work by the Contractor to illustrate some portion of the Work. Submittals are not Contract Documents.