Request for Change Proposal Sample Clauses

Request for Change Proposal. (i) If the Department desires to initiate a Department Change, then the Department will issue a Request for Change Proposal. The Request for Change Proposal will set forth the nature, extent and details of the proposed Department Change.
AutoNDA by SimpleDocs
Request for Change Proposal. 4.5.4.1.1 If TxDOT desires to issue a TxDOT-Directed Change or to evaluate whether to initiate such a change, then TxDOT may, in its discretion, issue a Request for Change Proposal. The Request for Change Proposal shall set forth the nature, extent and details of the proposed TxDOT- Directed Change.
Request for Change Proposal. 16.1.2.1 If IFA desires to initiate or evaluate whether to initiate a Change Order, then IFA may, at its discretion, issue a Request for Change Proposal. The Request for Change Proposal shall set forth the nature, extent and details of the proposed IFA Change.
Request for Change Proposal. 14.1.2.1 If GDOT desires to initiate a GDOT Change or to evaluate whether to initiate such a change, then GDOT may, at its discretion, issue a Request for Change Proposal. The Request for Change Proposal shall set forth the nature, extent and details of the proposed GDOT Change.
Request for Change Proposal. A Request for Change Proposal (RFCP) is a written request that informs Contractor about a potential change in the Trade Work and requests a proposal for the potential change. Contractor shall promptly reply with such request. Contractor shall not implement the change or incur any costs until a Change Order is fully executed.
Request for Change Proposal. (i) If the Department desires to initiate a Department Change under the CA, the Department is to issue a Request for Change Proposal. Under the CA, the Request for Change Proposal is to set forth the nature, extent and details of the proposed Department Change. If the proposed Department Change relates to the DB Work, the Concessionaire shall forward the Request for Change Proposal to the DB Contractor, and the DB Contractor shall fulfill the Concessionaire’s obligations under the CA with respect to the Department Change as provided in this Section 14.02.
Request for Change Proposal. (a) If MDOT desires to initiate or evaluate whether to initiate a Change Order, then MDOT may issue a Request for Change Proposal. The Request for Change Proposal shall set forth the nature, extent and details of the proposed Change.
AutoNDA by SimpleDocs
Request for Change Proposal. 14.2.1.1 If the Alamo RMA desires to issue an Alamo RMA-Directed Change or to evaluate whether to initiate such a change, the Alamo RMA may, at its discretion, issue a Request for Change Proposal. The Alamo RMA may, at any time, ask Design/Builder to provide two alternative Change Order forms in accordance with Section 14.3.3.
Request for Change Proposal. 14.1.2.1 If KYTC desires to issue an KYTC-Directed Change or to evaluate whether to initiate such a change, then KYTC may, at its sole discretion, issue a Request for Change Proposal. The Request for Change Proposal shall set forth the nature, extent, and details of the proposed KYTC-Directed Change. KYTC may, in its sole discretion, determine whether to implement the potential change after consideration of DBT’s response.
Request for Change Proposal. (i) If the Department desires to initiate a Department Change, then the Department will issue a Request for Change Proposal. The Request for Change Proposal will set forth the nature, extent and details of the proposed Department Change. (ii) Within five Days following the Developer’s receipt of the Request for Change Proposal, the Developer will provide the Department with a preliminary estimate of the Developer’s Allocable Costs for preparing the Change Proposal (a “Change Proposal ... (iii) Within 14 Days following the Department’s written approval of the Change Proposal Estimate, the Developer will provide the Department with a preliminary written response, and within a reasonable time thereafter (not to exceed 30 Days or such oth... (iv) Within 30 Days following the delivery of the Change Proposal, the Developer and the Department will exercise good faith efforts to negotiate a mutually acceptable Change Order. (v) If the Department approved in writing the Change Proposal Estimate and the Developer delivered the Change Proposal then, within 30 Days following the delivery of the Change Proposal, the Department will pay to the Developer the lesser of (1) the D...