Preparing Progress Payment Requests. In preparing construction estimates, the Contractor may request a progress payment based on the actual percentage of work completed during the preceding month. The estimate shall contain a breakdown of the total Contract amount; to include a separate breakdown of all approved change orders, into principal items of construction, showing the estimated quantity, unit price, and total for each item. In preparing progress payment requests, the material delivered on the site and preparatory work done may be taken into consideration, if properly documented, or as may be required by the Division Manager so that quantities can be verified. In addition to material delivered on the site, material such as large pieces of equipment and items purchased specifically for the project, but stored off the site, may be considered for payment, provided prior written approval is given by the Division Manager.
AutoNDA by SimpleDocs
Preparing Progress Payment Requests. In preparing construction estimates, the Contractor may request a progress payment based on the actual percentage of work completed during the preceding month. The estimate shall contain a breakdown of the total Contract amount, to include a separate breakdown of all approved change orders, into principal items of construction, showing the estimated quantity, unit price, and total for each item. In preparing progress payment requests, the material delivered on the site and preparatory work done will not be taken into consideration. In addition to material delivered on the site, material such as large pieces of equipment and items purchased specifically for the project, will not be taken into consideration.

Related to Preparing Progress Payment Requests

  • PROGRESS PAYMENT 5.4.1 After receipt by the Contract Administrator of a Proper Invoice submitted by the Contractor in accordance with 5.3 – PROPER INVOICES:

  • Progress Payments 5.1.1 Based upon Applications for Payment submitted to the Architect by the Contractor and Certificates for Payment issued by the Architect, the Owner shall make progress payments on account of the Contract Sum to the Contractor as provided below and elsewhere in the Contract Documents.

  • Payment Requests Review applications for payment with Contractor for compliance with the established procedure for their submission and forward with recommendations to Engineer, noting particularly the relationship of the payment requested to the schedule of values, Work completed, and materials and equipment delivered at the Site but not incorporated in the Work.

  • Periodic Progress Payments The Owner shall make progress payments, less retainage, as set forth in Section 4 of the General Conditions.

  • Progress Payments; Retainage A. Owner shall make progress payments on account of the Contract Price on the basis of Contractor’s Applications for Payment on or about the first day of each month during performance of the Work as provided in Paragraph 6.02.A.1 below, provided that such Applications for Payment have been submitted in a timely manner and otherwise meet the requirements of the Contract. All such payments will be measured by the Schedule of Values established as provided in the General Conditions (and in the case of Unit Price Work based on the number of units completed) or, in the event there is no Schedule of Values, as provided elsewhere in the Contract.

  • Payment request The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.

  • Stop Payment Requests If you desire to stop any transfer that has already been processed, you must contact customer care for the Service pursuant to Section 22 of the General Terms. Although we will make a reasonable effort to accommodate your request, we will have no liability for failing to do so. We may also require you to present your request in writing within fourteen (14) days. The charge for each request will be the current charge for such service as set out in the applicable fee schedule.

  • Quarterly Progress Reports The goal of this task is to periodically verify that satisfactory and continued progress is made towards achieving the objectives of this Agreement on time and within budget. The objectives of this task are to summarize activities performed during the reporting period, to identify activities planned for the next reporting period, to identify issues that may affect performance and expenditures, and to form the basis for determining whether invoices are consistent with work performed. The Recipient shall: • Prepare a Quarterly Progress Report which summarizes all Agreement activities conducted by the Recipient for the reporting period, including an assessment of the ability to complete the Agreement within the current budget and any anticipated cost overruns. Progress reports are due to the CAM the 10th day of each January, April, July, and October. The Quarterly Progress Report template can be found on the ECAMS Resources webpage available at xxxxx://xxx.xxxxxx.xx.xxx/media/4691. Product: • Quarterly Progress Reports

  • Monthly Progress Reports During the Construction Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Authority and the Independent Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Engineer.

  • Stop Payment Request You may ask the Credit Union to stop payment on any check drawn upon or ACH debit scheduled from your checking account. You may request a stop payment by telephone, by mail, or in person. For checks, the stop payment will be effective if the Credit Union receives the order in time for the Credit Union to act upon the order. For ACH debits, the stop payment order must be received at least three (3) banking days before the scheduled date of the transfer. You must state the number of the account, date, and the exact amount of the check or item and the number of the check or originator of the ACH debit. If you give the Credit Union incorrect or incomplete information, the Credit Union will not be responsible for failing to stop payment on the item. If the stop payment order is not received in time for the Credit Union to act upon the order, the Credit Union will not be liable to you or to any other party for payment of the item. If we recredit your account after paying a check over a valid and timely stop payment order, you agree to sign a statement describing the dispute with the payee, to transfer all of your rights against the payee or other holders of the check to the Credit Union, and to assist the Credit Union in legal action taken against the person.