Common use of Preliminary Cost Estimates Clause in Contracts

Preliminary Cost Estimates. 2.1.5.1 When the Owner has sufficiently identified the Project requirements and the Architect has prepared other basic design criteria, the Construction Manager shall prepare, for the review of the Architect and approval of the Owner, a preliminary cost estimate utilizing area, volume or similar conceptual estimating techniques.

Appears in 4 contracts

Samples: www.sec.gov, Immunicon Corp, Mapinfo Corp

AutoNDA by SimpleDocs

Preliminary Cost Estimates. 2.1.5.1 1. When the Owner has sufficiently identified the Project requirements and the Architect Architect/Engineer has prepared other basic design criteria, the Construction Manager shall prepare, for the review of the Architect Architect/Engineer and approval of the Owner, a preliminary cost estimate utilizing area, volume or similar conceptual estimating techniques.

Appears in 4 contracts

Samples: Agreement, Agreement, Agreement

Preliminary Cost Estimates. 2.1.5.1 2.1.5.1. When the Owner has sufficiently identified the Project project requirements and the Architect has prepared other basic design criteria, the Construction Manager shall prepare, for the review of the Architect and approval of the Owner, a preliminary cost estimate utilizing area, volume or similar conceptual estimating techniques.

Appears in 3 contracts

Samples: Form of Construction Management Agreement, Form of Construction Management Agreement, Construction Management Agreement

Preliminary Cost Estimates. § 2.1.5.1 When the Owner has sufficiently identified the Project requirements and the Architect has prepared other basic design criteria, the Construction Manager shall prepare, for the review of the Architect and approval of the Owner, a preliminary cost estimate utilizing area, volume or similar conceptual estimating techniques.

Appears in 1 contract

Samples: Agreement

Preliminary Cost Estimates. 2.1.5.1 When the Owner has sufficiently identified the Project requirements and the Architect has prepared other basic design criteria, the Construction Manager manager shall prepare, for the review of the Architect and approval of the Owner, a preliminary cost estimate utilizing area, volume or similar conceptual estimating techniques.

Appears in 1 contract

Samples: Agreement (Lifecore Biomedical Inc)

Preliminary Cost Estimates. § 2.1.5.1 When the Owner has sufficiently identified the Project requirements and the Architect has prepared other basic design criteria, the Construction Manager shall prepare, for the review of the Architect and approval of the Owner, a preliminary cost estimate and schedule utilizing area, volume or similar conceptual estimating techniques.

Appears in 1 contract

Samples: www.govbids.com

Preliminary Cost Estimates. 2.1.5.1 When the Owner has sufficiently identified the Project requirements and the Architect has prepared other basic design criteria, the Construction Manager shall prepare, for the review of the Architect and written approval of the Owner, a preliminary cost estimate utilizing area, volume or similar conceptual estimating techniques.

Appears in 1 contract

Samples: Agreement for Construction

AutoNDA by SimpleDocs

Preliminary Cost Estimates. § 2.1.5.1 When the Owner has sufficiently identified Based on the Project requirements and the Architect has prepared other basic design criteriaOwner’s program (“Owner’s Program”), the Construction Manager shall prepare, for the review of the Architect and approval of the Owner, a preliminary cost estimate utilizing area, building type, volume or and similar conceptual estimating techniquestechniques as appropriate.

Appears in 1 contract

Samples: United Therapeutics Corp

Preliminary Cost Estimates. 2.1.5.1 a. When the Owner has sufficiently identified the Project requirements and the Architect Owner’s Representative has prepared other basic design criteria, the Construction Manager shall prepare, for the review of the Architect Owner’s Representative and approval of the Owner, a preliminary cost estimate utilizing area, volume or similar conceptual estimating techniques.

Appears in 1 contract

Samples: oklahoma.gov

Preliminary Cost Estimates. 2.1.5.1 1. When the Owner has sufficiently identified the Project requirements and the Architect Architect/Engineer has prepared other basic design criteria, the Construction Manager shall prepare, for the review of the Architect Architect/Engineer and approval of the Owner, a preliminary cost estimate utilizing area, volume or similar conceptual estimating techniques.. SAMPLE

Appears in 1 contract

Samples: Agreement

Preliminary Cost Estimates. 2.1.5.1 When the Owner has sufficiently identified the Project requirements and the Architect has prepared other basic design criteriarequirements, the Construction Manager Operations Contractor shall prepare, for the review of the Architect and approval of the Owner, a preliminary cost estimate utilizing area, volume or similar conceptual estimating techniques.

Appears in 1 contract

Samples: Agreement (Western Goldfields Inc)