Pre-Construction Services Fee Sample Clauses

Pre-Construction Services Fee. The Pre-Construction Services Fee, which for all portions of the Project and all GMPs, is a fixed fee that shall, in no event, exceed Six Hundred Forty-Five Thousand Six Hundred Sixty-Three and No/100 Dollars ($645,663.00) for the Project, an allocable portion of which shall be shown in each GMP Amendment covering each portion of the Project. The Pre-Construction Services Fee is part of the Total Project GMP.
AutoNDA by SimpleDocs
Pre-Construction Services Fee. PHASE FEE Pre-Design Phase $ Conceptual Schematic Design $ Advanced Schematic Design $ Design Development $ 60% Construction Documents $ 100% Construction Documents $ Total: $
Pre-Construction Services Fee. Amount. The County shall pay, and the Construction Manager shall accept as complete payment for performance of Pre-Construction Services, a negotiated fixed fee not to exceed $28,000.00. The scope, timing, number of deliverables and payment processes are set forth in Chapter 2, Article 2 of Appendix “A,” and shall be in accordance with a Project-specific Appendix “E” submitted with the Construction Manager’s scope of services.
Pre-Construction Services Fee. Amount. The Pre-Construction Services Fee shall be: [Select one of the following]
Pre-Construction Services Fee. Payment. [Select one of the following] X The lump sum fixed Pre-Construction Services Fee shall be paid in accordance with Appendix “C”. □ The lump sum fixed Pre-Construction Services Fee shall be set and paid pursuant to the time schedule in Appendix “E” when executed by the parties. □ The time and material not to exceed Pre-Construction Services Fee shall be paid in accordance with the labor and material rates set forth in Appendix “E”. □ Other:
Pre-Construction Services Fee. For the performance of the Pre-Construction Services, the fee therefore as set forth in paragraphs 9.1.1 shall be paid monthly based upon detailed invoices totaling the aggregate of all work previously performed as submitted by the Construction Manager, with the total payment not to exceed the fee for such services as set forth in paragraph 9.1.1.
Pre-Construction Services Fee. Amount. The Pre-Construction Services Fee shall be: The Owner shall pay, and the Construction Manager shall accept as complete payment for performance of Pre-Construction Services, the fixed fee of ($ ) Dollars. If the scope of the Pre-Construction Services is materially increased through no fault of the Construction Manager, the Pre-Construction Services Fee shall be equitably adjusted.
AutoNDA by SimpleDocs

Related to Pre-Construction Services Fee

  • PRE-CONSTRUCTION PHASE SERVICES The Pre-Construction Phase shall be deemed to commence upon the date specified in a written Notice to Proceed with Pre-Construction Phase Services issued by Owner and shall continue through completion of the Construction Documents and procurement of all major Subcontractor agreements. Contractor is not entitled to reimbursement for any costs incurred for Pre-Construction Phase Services performed before issuance of the written Notice to Proceed. Pre-Construction Phase Services may overlap Construction Phase Services. Contractor shall perform the following Pre-Construction Phase Services:

  • PRE-CONSTRUCTION PHASE FEE The Pre-Construction Phase Fee is the total compensation payable to Contractor for the performance of Pre-Construction Phase Services, except for Additional Pre-Construction Phase Services approved in advance and in writing by Owner. The Pre-Construction Phase Fee shall be a lump sum amount based on the AACC established in this Agreement.

  • Pre-Construction Phase Employer’s Liability, Workers’ Compensation, Comprehensive General Liability and Comprehensive Automobile Liability in the amounts as set forth in the UGSC.

  • Contract Construction 6.27.1 The parties acknowledge that each party and its counsel have reviewed this CONTRACT and that the normal rule of construction to the effect that any ambiguities are to be resolved against the drafting party shall not be employed in the interpretation of this CONTRACT or any amendment or exhibits hereto.

  • Construction Services 4,500 thousand SDR for Japan Post in Group A 15,000 thousand SDR for all other entities in Group A 4,500 thousand SDR for entities in Group B Architectural, engineering and other technical services covered by this Agreement: 450 thousand SDR Other services: 130 thousand SDR List of Entities which procure the services, specified in Annex 4:

  • COMPENSATION FOR CONSTRUCTION PHASE SERVICES 5.1 For the Construction Manager’s performance of the Work as described in Section 2.3, the Owner shall pay the Construction Manager the Contract Sum in current funds. The Contract Sum is the Cost of the Work as defined in Section 6.1.1 plus the Construction Manager’s Fee.

  • Pre-Construction Conference Participate in a pre-construction conference prior to commencement of Work at the Site.

  • Project Construction The Contractor agrees to provide continuous on-site supervision on each Job Order, while progress on the project is being accomplished. The Contractor’s Project Manager will ensure:

  • ADDITIONAL CONSTRUCTION The Promoter undertakes that it has no right to make additions or to put up additional structure(s) anywhere in the Project after the building plan has been approved by the competent authority (ies) except for as provided in the Act.

  • Coordination of Design and Construction Contract Documents 5.5.1 Review model(s), Drawings, Specifications and other Construction Documents as they are developed by A/E during the Schematic Design, Design Development, and Construction Documents design phases of the Project.