Practical Completion. 28.1 The Contractor must give to the Owner 5 Business Days prior written notice of the date upon which the Contractor anticipates that the Works will reach the Practical Completion stage.
Appears in 4 contracts
Samples: Extension and Repair Contract, Extension and Repair Contract, Extension and Repair Contract
Practical Completion. 28.1 22.1 The Contractor must give to the Owner 5 Business Days business days prior written notice of the date upon which the Contractor anticipates that the Works Contract Work will reach the Practical Completion stageCompletion.
Appears in 4 contracts
Samples: Extension and Repair Contract, www.qbcc.qld.gov.au, nuspacehomes.com.au
Practical Completion. 28.1 The Contractor must give to the Owner 5 Business Days business days prior written notice of the date upon which the Contractor anticipates that the Works will reach the Practical Completion stageCompletion.
Appears in 4 contracts
Samples: Extension and Repair Contract, Extension and Repair Contract, nuspacehomes.com.au
Practical Completion. 28.1 22.1 The Contractor must give to the Owner 5 Business Days 3 business days prior written notice of the date upon which the Contractor anticipates that the Works Contract Work will reach the Practical Completion stageCompletion.
Appears in 1 contract
Samples: theoutsideperspective.com.au
Practical Completion. 28.1 27.1 The Contractor must give to the Owner 5 Business Days business days prior written notice of the date upon which the Contractor anticipates that the Works will reach the Practical Completion stageCompletion.
Appears in 1 contract
Samples: Repairs Contract
Practical Completion. 28.1 The Contractor must give to the Owner 5 Business Days 3 business days prior written notice of the date upon which the Contractor anticipates that the Works will reach the Practical Completion stageCompletion.
Appears in 1 contract
Samples: theoutsideperspective.com.au