Planned Outages Sample Clauses

Planned Outages. Seller shall schedule Planned Outages for the Project in accordance with Good Industry Practices and with the prior written consent of Buyer, which consent may not be unreasonably withheld or conditioned. The Parties acknowledge that in all circumstances, Good Industry Practices shall dictate when Planned Outages should occur. Seller shall notify Buyer of its proposed Planned Outage schedule for the Project for the following calendar year by submitting a written Planned Outage schedule no later than October 1st of each year during the Delivery Term. The Planned Outage schedule is subject to Buyer’s approval, which approval may not be unreasonably withheld or conditioned. Buyer shall promptly respond with its approval or with reasonable modifications to the Planned Outage schedule and Seller shall use its best efforts in accordance with Good Industry Practices to accommodate Xxxxx’s requested modifications. Notwithstanding the submission of the Planned Outage schedule described above, Seller shall also submit a completed Outage Notification Form to Buyer no later than fourteen (14) days prior to each Planned Outage and all appropriate outage information or requests to the CAISO in accordance with the CAISO Tariff. Seller shall contact Buyer with any requested changes to the Planned Outage schedule if Seller believes the Project must be shut down to conduct maintenance that cannot be delayed until the next scheduled Planned Outage consistent with Good Industry Practices. Seller shall not change its Planned Outage schedule without Buyer’s approval, not to be unreasonably withheld or conditioned. Seller shall use its best efforts in accordance with Good Industry Practices not to schedule Planned Outages during the months of July, August, September and October. At Buyer’s request, Seller shall use commercially reasonable efforts to reschedule Planned Outage so that it may deliver Product during CAISO declared or threatened emergency periods. Seller shall not substitute Energy from any other source for the output of the Project during a Planned Outage.
AutoNDA by SimpleDocs
Planned Outages. Seller will include its proposed Planned Outage Schedule in ils Annual Forecast of generation and implement the Notification procedures set forth in Appendix A no later than August 1st of each year. Whenever possible, Seller will notifY Buyer of changes to the yearly Planned Outage schedule 60 days prior to the start of the month when this change is expected to occur. Seller will provide updates regarding a Planned Outage at least fourteen (14) days before each Planned Outage. Seller shall not conduct Planned Outages during the months of January, June through September, and December. Seller shall request a change to the Planned Outage Schedule if Seller believes the Project must be shut down to conduct maintenance that cannot be delayed until the next Scheduled Planned Outage consistent with Good Utility Practices. Seller shall not substitute Energy from any other source during a Planned Outage. At any time up to the commencement of work for the Planned Outage, Buyer may direct Seller to change its Outage Schedule as ordered by XXXXX. If Buyer requests any other change to a Planned Outage Schedule, Seller may propose an alternative Schedule change or use commercially reasonable efforts to accommodate Buyer's request.
Planned Outages. No Planned Outage may be scheduled to occur during any portion of the time period commencing on May 15 and concluding on September 15.
Planned Outages. 7.1.1 First year of RMR operation. The ISO and Owner have developed a planned outage schedule covering the first year of each RMR Generator’s operation under this Agreement. The agreed upon schedule is included as Confidential Schedule 2 to this Agreement. The ISO will accommodate limited, reasonable changes to the agreed planned outage schedule requested by Owner, so long as such changes will not interfere with the ability of the RMR Generator to meet the Reliability Need. Planned outage schedules for subsequent years will be developed in accordance with this Article 7.
Planned Outages. Seller shall schedule and utilize all planned outages in accordance with the procedures and subject to the limitations set forth in Exhibit D.
Planned Outages. Except as otherwise provided herein, Seller shall not schedule a Planned Outage during daylight hours (sun up to sunset) during any portion of the months of November, December, January, February, June, July, and August, except to the extent a Planned Outage is reasonably required to enable a vendor to satisfy a guarantee requirement. Seller shall provide PacifiCorp with an annual forecast of Planned Outages for each Contract Year at least one month, but no more than three months, before the first day of that Contract Year, and shall promptly update such schedule, or otherwise change it, only to the extent that Seller is reasonably required to change it in order to comply with Prudent Electrical Practices. Seller shall not schedule any maintenance of Interconnection Facilities during such months, without the prior written approval of PacifiCorp, which approval shall not be unreasonably withheld or delayed.
Planned Outages. Except as otherwise provided herein, Seller shall not schedule a Planned Outage during any portion of the months of November, December, January, February, June, July, and August, except to the extent a Planned Outage is reasonably required to enable a vendor to satisfy a guarantee requirement. Seller shall provide PacifiCorp with an annual forecast of Planned Outages for each Contract Year at least one month, but no more than three months, before the first day of that Contract Year, and shall promptly update such schedule, or otherwise change it, only to the extent that Seller is reasonably required to change it in order to comply with Prudent Electrical Practices. Seller shall not schedule any maintenance of Interconnection Facilities during such months, without the prior written approval of PacifiCorp, which approval shall not be unreasonably withheld or delayed.
AutoNDA by SimpleDocs
Planned Outages. No later than fifteen (15) Business Days prior to the end of each year during the Term, Seller shall provide to Buyer a Planned Outage schedule for the upcoming year. Seller shall provide Buyer with reasonable advance notice of any material change in the Planned Outage schedule. Seller shall determine the number and extent of Planned Outages in a Commercially Reasonable Xxxxxx recognizing that it is the intent of the Parties to maximize production of the Facility and to such extent Seller shall be excused from providing the Product during such Planned Outage(s). Unless both Parties expressly agree otherwise, any Planned Outage shall only occur during the months of March, April, May, September, October, or November.
Planned Outages. (a) A Generator Planned Outage shall be included in Generator Planned Outage schedules established prior to the scheduled start date for the outage, in accordance with standards and procedures specified in the PJM Manuals.
Planned Outages. The Participant shall notify the DSO of any Planned Outages by submitting an Outage Notice via the Platform no later than the Bid/Offer Submission Start Date.