Payment of Final Invoice Sample Clauses

Payment of Final Invoice. (a) Within 7 days of receipt by Owner of the Recalculation Settlement Statement for market transactions for the effective date of termination of this Agreement, Owner shall submit an invoice (“Final Invoice”) to CAISO and a copy to the Responsible Utility for all charges and other amounts then due under this Agreement. Amounts then due shall include: (i) charges for all Billable MWh and Ancillary Services provided under this Agreement and not previously invoiced; (ii) the Long-term Planned Outage Adjustment under Section 8.6. and (iii) refunds described in section 9.1(f) for Condition 2 Units. Calculation of the Long- term Planned Outage Adjustment shall be made by deeming the effective date of termination to be the end of the Contract Year, and by assuming that all Long-term Planned Outages scheduled to occur after the termination date occur as scheduled. The Final Invoice shall not include remaining Monthly payments of a Termination Fee under Section 2.5, which shall continue to be paid monthly until the obligation is extinguished.
AutoNDA by SimpleDocs
Payment of Final Invoice. (a) Within 7 days of receipt by Owner of the Recalculation Settlement Statement for market transactions for the effective date of termination of this Agreement, Owner shall submit an invoice (“Final Invoice”) to CAISO and a copy to the Responsible Utility for all charges and other amounts then due under this Agreement. Amounts then due shall include: (i) charges for all Billable MWh and Ancillary Services provided under this Agreement and not previously invoiced; (ii) the Long-term Planned Outage Adjustment under Section 8.6. and (iii) refunds described in section 9.1(f) for Condition 2 Units. Calculation of the Long-term Planned Outage Adjustment shall be made by deeming the effective date of termination to be the end of the Contract Year, and by assuming that all Long- term Planned Outages scheduled to occur after the termination date under this Agreement or any successor agreement entered into upon a redesignation pursuant to Section 2.2(f) occur as scheduled. The Final Invoice shall not include remaining Monthly payments of a Termination Fee under Section 2.5, which shall continue to be paid monthly until the obligation is extinguished.
Payment of Final Invoice. (a) Within thirty (30) days of the effective date of expiration or termination of this Agreement, Owner shall submit an invoice to ISO and a copy to the Affected Participating Transmission Owner for all amounts then due to or payable by Owner under this Agreement (the “Final Invoice”).
Payment of Final Invoice. (a) Within 79 days of the effective date of termination of this Agreement, Owner shall submit an invoice ("Final Invoice") to ISO and a copy to the Responsible Utility for all charges and other amounts then due under this Agreement. Amounts then due shall include: (i) charges for all Billable MWh and Ancillary Services provided under this Agreement and not previously invoiced and (ii) the Long-term Planned Outage Adjustment under Section 8.6. Calculation of the Long-term Planned Outage Adjustment shall be made by deeming the effective date of termination to be the end of the Contract Year, and by assuming that all Long-term Planned Outages scheduled to occur after the termination date occur as scheduled. The Final Invoice shall not include remaining Monthly payments of a Termination Fee under Section 2.5, which shall continue to be paid monthly until the obligation is extinguished.
Payment of Final Invoice. Owner shall pay the Contract Sum to Contractor within 30 days after Owner's receipt of the final invoice and all of the items listed in Section 11.1, all to the reasonable satisfaction of Owner. Neither final payment nor issuance of the Owner's Certificate of Acceptance shall affect or impair Owner's rights with respect to any defect in or nonconforming Work or any other breach or right or remedy under the Contract Documents.
Payment of Final Invoice. All prior invoices and payments shall be subject to correction in the Proposed Final Invoice. SANDAG will review Contractor’s Proposed Final Invoice and respond with a written request for additional information or documentation, changes or corrections within thirty (30) days of its receipt or, in the case of a Final Invoice accompanied by one or more claims, within sixty (60) days. Based on SANDAG’s response, Contractor shall submit a Final Invoice incorporating any changes or corrections made by SANDAG, together with any additional requested information or documentation. If SANDAG agrees with all requests for compensation in the Final Invoice, SANDAG will pay the entire sum found due within thirty (30) days of its receipt and will provide Contractor with a copy of an Approved Final Invoice. If SANDAG does not agree with any amounts claimed as compensation, SANDAG shall respond in writing, within such thirty (30) day period, identifying those items in the Final Invoice that SANDAG is refusing to pay, along with a written explanation of the basis of the rejection. If SANDAG fails or refuses to act on a Final Invoice within the required time period, the claim shall be deemed to have been rejected by SANDAG on the last day of the period within which SANDAG was required to respond. Upon final determination of all Contractorsclaims for payment in the Final Invoice, SANDAG shall pay the entire sum found due. SANDAG may, at that time, elect to make payment of sums not in dispute, without prejudice to the rights of either SANDAG or Contractor in connection with such disputed sums.‌

Related to Payment of Final Invoice

  • Final Invoice Within six months after completion of the construction of the Connecting Transmission Owner’s Attachment Facilities and the System Upgrade Facilities and System Deliverability Upgrades, Connecting Transmission Owner shall provide an invoice of the final cost of the construction of the Connecting Transmission Owner’s Attachment Facilities and the System Upgrade Facilities and System Deliverability Upgrades, determined in accordance with Attachment S to the NYISO OATT, and shall set forth such costs in sufficient detail to enable Developer to compare the actual costs with the estimates and to ascertain deviations, if any, from the cost estimates. Connecting Transmission Owner shall refund to Developer any amount by which the actual payment by Developer for estimated costs exceeds the actual costs of construction within thirty (30) Calendar Days of the issuance of such final construction invoice.

  • Payment of Invoice A payment by the State shall not prejudice the State's right to object to or question any payment, invoice, or other matter. A payment by the State shall not be construed as acceptance of goods delivered, any part of the services provided, or as approval of any amount invoiced.

  • Payment – Invoicing Instructions The Contractor will provide an invoice on the Contractor’s letterhead for goods delivered and/or services rendered. In the case of goods, the Contractor will leave an invoice with each delivery. Each invoice will have a number and will include the following information:

  • Payment Invoicing The Contractor will be paid upon submission of invoices to the Customer after delivery and acceptance of commodities or contractual services is confirmed by the Customer. Invoices must contain sufficient detail for an audit and contain the Contract Number and the Contractor’s Federal Employer Identification Number.

  • Monthly Invoice Based on Monthly Delivery Protocol according to Article 9.1 within thirteen (13) calendar days after the expiry of the relevant Month of Delivery SELLER shall issue and render to BUYER by e-mail a monthly invoice (“Monthly Invoice”) relevant to Month of Delivery, indicating the quantity of the delivered Natural Gas (expressed in kWh and Ncm), applicable Contract Price (expressed in EURO/MWh) and the total amount to be paid by BUYER, including but not limited to the payment for the respective quantity of Natural Gas not taken in the frame of MDCQ (if any). Monthly Delivery Protocol shall be deemed to be inseparable part of Monthly Invoice.

  • Invoice The Interconnected Transmission Owner shall provide Transmission Provider a quarterly statement of the Interconnected Transmission Owner’s scheduled expenditures during the next three months for, as applicable (a) the design, engineering and construction of, and/or for other charges related to, construction of the Interconnection Facilities for which the Interconnected Transmission Owner is responsible under the Interconnection Service Agreement and the Interconnection Construction Service Agreement, or (b) in the event that the Interconnection Customer exercises the Option to Build pursuant to Tariff, Attachment P, Appendix 2, section 3.2.3.1, for the Interconnected Transmission Owner’s oversight costs (i.e. costs incurred by the Transmission Owner when engaging in oversight activities to satisfy itself that the Interconnection Customer is complying with the Transmission Owner’s standards and specifications for the construction of facilities) associated with Interconnection Customer’s building Transmission Owner Attachment Facilities and Direct Connection Network Upgrades, including but not limited to Costs for tie-in work and Cancellation Costs. Interconnected Transmission Owner oversight costs shall be consistent with Tariff, Attachment P, Appendix 2, section 3.2.3.2(a)(12). Transmission Provider shall bill Interconnection Customer on behalf of the Interconnected Transmission Owner, for the Interconnected Transmission Owner’s expected Costs during the subsequent three months. Interconnection Customer shall pay each bill within twenty (20) days after receipt thereof. Upon receipt of each of Interconnection Customer’s payments of such bills, Transmission Provider shall reimburse the Interconnected Transmission Owner. Interconnection Customer may request that the Transmission Provider provide a quarterly cost reconciliation. Such a quarterly cost reconciliation will have a one-quarter lag, e.g., reconciliation of Costs for the first calendar quarter of work will be provided at the start of the third calendar quarter of work, provided, however, that Section 11.2.3 of this Appendix 2 shall govern the timing of the final cost reconciliation upon completion of the work.