Owner Delay Sample Clauses

Owner Delay. If, other than solely as a result of an HQUS Delay, Force Majeure, or Concurrent Delay, any conditions set forth in Section 4.3 shall not have been satisfied or duly waived by the Target Date (such delay, an “Owner Delay”):
AutoNDA by SimpleDocs
Owner Delay. (a) If, as a result of an Owner Default, any conditions set forth in Section 4.2 shall not have been satisfied or duly waived within one hundred eighty (180) days following the later to occur of (i) the Target Date and (ii) the date upon which TransÉnergie has certified to Owner in good faith that the Québec Line is ready for Commissioning (such delay, an "Owner Delay," and such one hundred eightieth (180th) day, "Owner’s Initial Deadline"), then, for purposes of cost recovery under Section 8.1.2, AFUDC shall not be accrued on the Construction Costs and Carrying Charges shall not be accrued on the Pre-COD Expenses, in each case, from and after Owner’s Initial Deadline.
Owner Delay. Any delays in Contractor’s Work that are caused in whole or in part by Owner, its agents, consultants or separate contractors, and are not the fault of Contractor or any Subcontractor or any party for which either is responsible or liable at law or under the Contract Documents, shall be an “Owner Delay.”
Owner Delay. Delay damages are limited to additional field office and jobsite overhead costs incurred by Contractor directly attributable to the Delay of the Contract Time. Home office overhead is excluded from Delay damages and not compensable under the Contract. Before Contractor may obtain any increase in the Contract Amount to compensate for any Delay damages, Contractor shall have demonstrated to Owner’s satisfaction that:
Owner Delay. Defined in Section 3.4.1.
Owner Delay. 3.4.1.1 An “
Owner Delay. The unexcused failure by Owner prior to the Handover Date to provide the raw materials, chemicals, utilities and staffing of trained operating personnel necessary to support performance of the Performance Testing by Major Vendor in a timely manner in accordance with the Baseline Schedule (and the advance notices provided by Major Vendor to Owner not less than one hundred twenty (120), sixty (60) and thirty (30) days prior to scheduled date for commencement of such testing and as per instructions of Major Vendor to support the first start- up and commissioning tests and activities) will potentially result in the delay in the achievement of Handover of the Project, and Major Vendor shall have the right to request a change order extending the Guaranteed Handover Date by the same number of days of such delay.
AutoNDA by SimpleDocs
Owner Delay. As used in this Agreement, the term “Owner Delay” means any actual delay in the critical path of Contractor’s Work that is caused by Owner, Owner’s Lenders or any of Owner’s Consultants or Owner’s Contractors as a result of their acts or omissions, but only to the extent not the fault of Contractor or any Subcontractor or Vendor or any party for which any of them is responsible or liable at law or under the Contract). Owner and Contractor agree to use best efforts to provide all information and documentation reasonably required by Owner’s Lenders in order for Owner’s Lenders to render approvals under this Agreement. In addition to and without derogation of Contractor’s rights with respect to extensions of the Contract Time set forth in Section 11.6, Owner may, in its sole and absolute discretion, at any time and from time to time, whether before or after Final Completion, prospectively or retrospectively, and for any reason, whether for Owner’s sole benefit or otherwise (including, without limitation, in connection with a delay caused solely by Owner), grant to Contractor an extension of the time specified in this Agreement for the performance by Contractor of any of its covenants or obligations under this Agreement or any of the other Contract Documents (including, without limitation, the Guaranteed Date of Substantial Completion and the Interim Milestone Dates).
Owner Delay. Any delay in the performance of the Work caused by (i) failure by Owner to perform, or cause to be performed its obligations in accordance with this Agreement for any reason (other than the fault of Contractor, its Subcontractors or other parties for whom Contractor is responsible) or (ii) any action or inaction by the Utility for any reason (other than the fault of Contractor, its Subcontractors or other parties for whom Contractor is responsible).
Owner Delay. As used in this Agreement, the term “Owner Delay” means any actual delay in the critical path of Contractor’s Work that is caused by Owner, Owner’s Lenders or any of Owner’s Consultants or Owner’s Contractors as a result of their acts or omissions, but only to the extent not the fault of Contractor or any Subcontractor or Vendor or any party for which any of them is responsible or liable at law or under the Contract). Owner and Contractor agree to use best efforts to provide all information and documentation reasonably required by Owner’s Lenders in order for Owner’s Lenders to render approvals under this Agreement. In addition to and without derogation of Contractor’s rights with respect to extensions of the Contract Time set forth in Section 11.6, Owner may, in its sole and absolute discretion, at any time and from time to time, whether before or after Original Project Final Completion or Expansion Project Final Completion, prospectively or retrospectively, and for any reason, whether for Owner’s sole benefit or otherwise (including, without limitation, in connection with a delay caused solely by Owner), grant to Contractor an extension of the time specified in this Agreement for the performance by Contractor of any of its covenants or obligations under this Agreement or any of the other Contract Documents (including, without limitation, the Original Project Guaranteed Date of Substantial Completion or Expansion Project Guaranteed Date of Substantial Completion (as applicable) and the Original Project Interim Milestone Dates or Expansion Project Interim Milestone Dates (as applicable)).