One Claim Sample Clauses

One Claim. All Claims against any one or more Insured arising from the same act or omission or from one series of related acts or omissions will be regarded as one Claim for the purposes of the Excess.
AutoNDA by SimpleDocs
One Claim. The insurance may provide for multiple Claims to be treated as one Claim for the purposes of an Excess contemplated by clause 3.1 on such terms as the Firm and the Insurer agree.
One Claim. When considering what may be regarded as one Claim for the purposes of the limits contemplated by clauses 2.1 and 2.3:
One Claim. The insurance may provide that, when considering what may be regarded as one Claim for the purposes of the limits contemplated by clauses 2.1 and 2.3:
One Claim. The insurance may provide that all Claims against any one or more Insured arising from the same act or omission or from one series of related acts or omissions will be regarded as one Claim for the purposes of the limits contemplated by clauses 2.1 and 2.3.
One Claim. Unless both of the parties agree otherwise, the arbitrator may not consolidate more than one person’s claims, and may not otherwise preside over any form of a representative or class proceeding.

Related to One Claim

  • False Claim The City reserves the right to recoup benefit payments to any employee who is guilty of submitting a false claim, or abuse of the privileges covered in this section, or working for another employer while on injury leave, and may take disciplinary action.

  • Submitting False Claims The full text of San Francisco Administrative Code Chapter 21, Section 21.35, including the enforcement and penalty provisions, is incorporated into this Agreement. Pursuant to San Francisco Administrative Code §21.35, any contractor or subcontractor who submits a false claim shall be liable to the City for the statutory penalties set forth in that section. A contractor or subcontractor will be deemed to have submitted a false claim to the City if the contractor or subcontractor: (a) knowingly presents or causes to be presented to an officer or employee of the City a false claim or request for payment or approval;

  • Claim A demand or assertion by the Owner or the Contractor seeking an adjustment of the Contract Sum or Contract Time, or both, or other relief with respect to the terms of the Contract. The term "Claim" also includes other disputes and matters in question between the Owner and the Contractor arising out of or relating to the Contract. The responsibility to substantiate a Claim shall rest with the party making the Claim. A demand for money or services by a third party, including a Trade Contractor, Supplier, or subcontractor to the Contractor, is ipso facto not a Claim against the Owner.

  • Delay Claim Must Be In Writing Any claim to extend the Contract Time and Material Completion and Occupancy Date must be in writing, must set forth in detail the basis for the claim and the number of days of delay claimed, must be correlated with the approved Overall Project Schedule, must be executed by the Contractor and delivered to the Design Professional and the Owner, and must be reviewed and an appropriate time assessed by the Design Professional.

  • Rights of Action All rights of action in respect of this Agreement, excepting the rights of action given to the Rights Agent under Section 18 hereof, are vested in the respective registered holders of the Right Certificates (and, prior to the Distribution Date, the registered holders of the Common Shares); and any registered holder of any Right Certificate (or, prior to the Distribution Date, of the Common Shares), without the consent of the Rights Agent or of the holder of any other Right Certificate (or, prior to the Distribution Date, of the Common Shares), may, in his own behalf and for his own benefit, enforce, and may institute and maintain any suit, action or proceeding against the Company to enforce, or otherwise act in respect of, his right to exercise the Rights evidenced by such Right Certificate in the manner provided in such Right Certificate and in this Agreement. Without limiting the foregoing or any remedies available to the holders of Rights, it is specifically acknowledged that the holders of Rights would not have an adequate remedy at law for any breach of this Agreement and will be entitled to specific performance of the obligations under, and injunctive relief against actual or threatened violations of the obligations of any Person subject to, this Agreement.

  • Initial Claim Post-Service Claims must be submitted to AvMed within 90 days from the date of service or within one year unless the Member was legally incapacitated; otherwise the Claim will be considered to have been waived.

  • LIENS, CLAIMS AND ENCUMBRANCES The Contractor warrants and represents that all materials, equipment or services delivered herein are free and clear of all liens, claims, or encumbrances of any kind.

  • FALSE CLAIMS Contractor warrants that it shall not, with respect to this Contract, make or present any claim upon or against the Government of the Virgin Islands, or any officer, department, board, commission, or other agency thereof, knowing such claim to be false, fictitious or fraudulent. Contractor acknowledges that making such a false, fictitious, or fraudulent claim is an offense under Virgin Islands law.

  • ANTI-TRUST CLAIM Contractor and its subcontractor(s) agree to assign to the District all rights, title, and interest in and to all causes of action they may have under Section 4 of the Xxxxxxx Act (15 U.S.C. Sec. 15) or under the Xxxxxxxxxx Act (Chapter 2 (commencing with Section 16700) of Part 2 of Division 7 of the Business and Professions Code), arising from purchases of goods, services, or materials pursuant to the Contract or a subcontract. This assignment shall be made and become effective at the time the District tenders final payment to the Contractor, without further acknowledgment by the Parties.

  • Unknown Claims Executive acknowledges that Executive has been advised to consult with legal counsel and that Executive is familiar with the principle that a general release does not extend to claims that the releaser does not know or suspect to exist in his or her favor at the time of executing the release, which, if known by him or her, must have materially affected his or her settlement with the releasee. Executive, being aware of this principle, agrees to expressly waive any rights Executive may have to that effect, as well as under any other statute or common law principles of similar effect.]3