Common use of Obligations Upon Termination Clause in Contracts

Obligations Upon Termination. Upon termination for Default in accordance with Section 16.1A, Contractor shall (i) immediately discontinue Work on the date specified in the notice; (ii) place no further orders for Subcontracts, Equipment, or any other items or services; (iii) inventory, maintain and turn over to Owner all Construction Equipment owned by Contractor and (subject to the relevant Construction Equipment lease or rental agreements) all Construction Equipment rented by Contractor and, in each case, present on the Site prior to Contractor’s receipt of the termination notice or provided by Owner for performance of the terminated Work; (iv) promptly make every reasonable effort to procure assignment or cancellation upon terms satisfactory to Owner of all Subcontracts, including rental agreements; (v) cooperate with Owner in the transfer of Work Product (subject to Section 10.1D), including Drawings and Specifications, Permits and any other items or information and disposition of Work in progress so as to mitigate damages; (vi) comply with other reasonable requests from Owner regarding the terminated Work; (vii) thereafter preserve and protect Work already in progress and to protect Equipment at the Site or in transit thereto, and to comply with any Applicable Law and any Applicable Codes and Standards; and (viii) perform all other obligations under Section 16.1B.

Appears in 16 contracts

Samples: Escrow Agreement, Escrow Agreement (Sabine Pass Liquefaction, LLC), Procurement and Construction Agreement (Cheniere Corpus Christi Holdings, LLC)

AutoNDA by SimpleDocs

Obligations Upon Termination. Upon termination for Default in accordance with Section 16.1ADefault, Contractor shall (i) immediately discontinue Work on the date and to the extent specified in the notice; , (ii) place no further orders for Subcontracts, Equipment, or any other items or services; services except as may be necessary for completion of such portion of the Work as is not discontinued, (iii) inventory, maintain and turn over to Owner leave on-Site all Construction Equipment owned by Contractor third-party equipment, machinery, materials, tools, supplies and (subject to the relevant Construction Equipment lease or rental agreements) all Construction Equipment scaffolding rented by Contractor and, in each case, present on the Site prior to Contractor’s receipt of the termination notice or provided by Owner for performance of the terminated Work; , (iv) promptly make every reasonable effort to procure assignment or cancellation upon terms satisfactory to Owner of all Subcontracts, including Subcontracts and rental agreementsagreements to the extent they relate to the performance of the Work that is discontinued; (v) cooperate with Owner in the transfer of Work Product (subject to Section 10.1D)Product, including Drawings and Specifications, Permits Permits, licenses and any other items or information and disposition of Work in progress so as to mitigate damages; (vi) if requested by Owner in writing, assign the PLA to Owner or such other Person as directed by Owner; (vii) comply with other reasonable requests from Owner regarding the terminated Work; (viiviii) thereafter execute only that portion of the Work not terminated (if any) and that portion of the Work as may be necessary to preserve and protect Work already in progress and to protect Equipment at the Site or in transit thereto, and to comply with any Applicable Law and any Applicable Codes and Standards; and (viiiix) perform all other obligations under Section 16.1B.17.1C.

Appears in 2 contracts

Samples: Engineering, Procurement and Construction Agreement (Mirant Corp), Engineering, Procurement and Construction Agreement (Mirant Corp)

Obligations Upon Termination. Upon termination for Default in accordance with Section 16.1ADefault, Contractor shall (i) immediately discontinue Work on the date and to the extent specified in the notice; , (ii) place no further orders for Subcontracts, Equipment, or any other items or services; services except as may be necessary for completion of such portion of the Work as is not discontinued, (iii) inventory, maintain and turn over to Owner all Construction Equipment that is not owned by Contractor and (subject to the relevant Construction Equipment terms of any lease agreements with non-Affiliated third parties) or rental agreements) all Construction Equipment rented by Contractor and, in each case, present on the Site prior to Contractor’s receipt of the termination notice any other equipment or other items provided by Owner for performance of the terminated Work; , (iv) promptly make every reasonable effort to procure assignment or cancellation upon terms satisfactory to Owner of all Subcontracts, including Subcontracts and rental agreementsagreements to the extent they relate to the performance of the Work that is discontinued; (v) cooperate with Owner in the transfer of Work Product (subject to Section 10.1D)Product, including Drawings and Specifications, Permits Permits, licenses and any other items or information and disposition of Work in progress so as to mitigate damages; (vi) comply with other reasonable requests from Owner regarding the terminated Work; (vii) thereafter execute that portion of the Work as may be necessary to preserve and protect Work already in progress and to protect Equipment at the Site or in transit thereto, and to comply with any Applicable Law and any Applicable Codes and Standards; and (viii) perform all other obligations under Section 16.1B.16.1D.

Appears in 2 contracts

Samples: Epc Agreement (NextDecade Corp.), Epc Agreement (NextDecade Corp.)

Obligations Upon Termination. Upon termination for Default in accordance with Section 16.1A, Contractor shall (i) immediately discontinue Work on the date specified in the notice; (ii) place no further orders for Subcontracts, Equipment, or any other items or services; (iii) inventory, maintain and turn over to Owner all Construction Equipment owned by Contractor and (subject to the relevant Construction Equipment lease or rental agreements) all Construction Equipment rented by Contractor and, in each case, present on the Site prior to Contractor’s receipt of the termination notice or provided by Owner for performance of the terminated Work; (iv) promptly make every reasonable effort to procure assignment or cancellation upon terms satisfactory to Owner of all Subcontracts, including rental agreements; (v) cooperate with Owner in the transfer of Work Product (subject to Section 10.1D)Product, including Drawings and Specifications, Permits and any other items or information and disposition of Work in progress so as to mitigate damages; (vi) comply with other reasonable requests from Owner regarding the terminated Work; (vii) thereafter preserve and protect Work already in progress and to protect Equipment at the Site or in transit thereto, and to comply with any Applicable Law and any Applicable Codes and Standards; and (viii) perform all other obligations under Section 16.1B.

Appears in 1 contract

Samples: Engineering, Procurement and Construction Agreement (Cheniere Energy Inc)

AutoNDA by SimpleDocs

Obligations Upon Termination. Upon termination for Default in accordance with Section 16.1ADefault, Contractor shall (i) immediately discontinue Work on the date and to the extent specified in the notice; , (ii) place no further orders for Subcontracts, Equipment, or any other items or services; services except as may be necessary for completion of such portion of the Work as is not discontinued, (iii) inventory, maintain and turn over to Owner all Construction Equipment that is not owned or rented by Contractor and (subject to the relevant Construction Equipment terms of any lease or rental agreementsagreements with non-Affiliated third parties) all Construction Equipment rented furnished by Contractor and, in each case, present on the Site prior to Contractor’s receipt of the termination notice or any other equipment or other items provided by Owner for performance of the terminated Work; , (iv) promptly make every reasonable effort to procure assignment or cancellation upon terms satisfactory to Owner of all Subcontracts, including Subcontracts and rental agreementsagreements to the extent they relate to the performance of the Work that is discontinued; (v) cooperate with Owner in the transfer of Work Product (subject to Section 10.1D)Product, including Drawings and Specifications, Permits Permits, licenses and any other items or information and disposition of Work in progress so as to mitigate damages; (vi) comply with other reasonable requests from Owner regarding the terminated Work; (vii) thereafter execute that portion of the Work as may be necessary to preserve and protect Work already in progress and to protect Equipment at on the Site Land or in transit thereto, and to comply with any Applicable Law and any Applicable Codes and Standards; and (viii) perform all other obligations under Section 16.1B.16.1D.

Appears in 1 contract

Samples: Engineering, Procurement and Construction Agreement (Cheniere Energy, Inc.)