Notice of Force Majeure Events Sample Clauses

Notice of Force Majeure Events. If either Party is unable to perform its obligations under this Agreement due to a Force Majeure Event, the Party unable to perform shall notify the other Party of the Force Majeure Event promptly after the occurrence thereof. The Party’s notice may be given orally but shall promptly be confirmed in writing or electronically.
AutoNDA by SimpleDocs
Notice of Force Majeure Events. If any event occurs or has occurred that may delay compliance with or otherwise cause a violation of any obligation under this Compliance Agreement, as to which TVA intends to assert a claim of Force Majeure, TVA shall notify EPA, the States, and the Citizen Plaintiffs in writing as soon as practicable, but in no event later than twenty-one (21) business days following the date TVA first knew, or by the exercise of due diligence should have known, that the event caused or may cause such delay or violation. In this notice, TVA shall reference this Paragraph of this Compliance Agreement and describe the anticipated length of time that the delay or violation may persist, the cause or causes of the delay or violation, all measures taken or to be taken by TVA to prevent or minimize the delay and any adverse environmental effect of the violation, the schedule by which TVA proposes to implement those measures, and TVA=s rationale for attributing a delay or violation to a Force Majeure Event. TVA shall adopt all reasonable measures to avoid or minimize such delays or violations. TVA shall be deemed to know of any circumstance which TVA, its contractors, or any entity controlled by TVA knew or should have known.
Notice of Force Majeure Events. As soon as possible following the date of commencement of any Force Majeure Event and in no event later than [***] after the date the Party whose performance is affected by the Force Majeure Event knows of the occurrence of such an event, the affected Party shall advise the other Party in writing of the commencement, the nature and expected duration of such Force Majeure Event. If means of providing notice to the other Party are interrupted, such notice shall be provided within [***] after the resumption of means of providing notice to the other Party. As soon as possible and in no event later than [***] following the termination of a Force Majeure Event, the Party having invoked such Force Majeure Event as a cause of suspension and/or delay of performance shall notify the other Party that it is able to resume performance.
Notice of Force Majeure Events. The claiming Party shall promptly give the other Party a written notice describing the particulars of the Force Majeure Event of the occurrence of any such Force Majeure Event, including an estimate of the expected duration and the probable impact of the Force Majeure Event on the performance of such Party’s obligations hereunder. The Party claiming the Force Majeure Event shall have a continuing obligation to deliver to the other Party regular updated reports supporting its claim until such time as the Force Majeure Event is no longer in effect.
Notice of Force Majeure Events. (a) The Affected Party shall give notice to the other Party in writing of the occurrence of any of the Force Majeure Event (“the Notice”) as soon as the same arises or as soon as reasonably practicable and in any event within 7 (seven) days after the Affected Party knew, or ought reasonably to have known, of its occurrence and the adverse effect it has or is likely to have on the performance of its obligations under this Agreement.
Notice of Force Majeure Events. After a Force Majeure Event provided in Article 7.1 occurs, the affected Party shall promptly notify the other Party of the Force Majeure Event and to what extent it may be affected, and:
Notice of Force Majeure Events. As a condition to claiming a Force Majeure Event, the claiming Party shall promptly give the other Party a written notice describing the particulars of the Force Majeure Event of the occurrence of any such Force Majeure Event, including an estimate of the expected duration and the probable impact of the Force Majeure Event on the performance of such Party’s obligations hereunder. The Parties agree to use reasonable efforts to notify each other of potential Force Majeure Events and update each other on developments regarding potential Force Majeure Events. The Party claiming the Force Majeure Event shall have a continuing obligation to deliver to the other Party regular updated reports supporting its claim regarding a Force Majeure Event promptly after such information is available to such Party and until such time as the Force Majeure Event is no longer in effect.
AutoNDA by SimpleDocs
Notice of Force Majeure Events. (a) The Affected Party shall give notice to the other Party in writing of the occurrence of any of the Force Majeure Event (“the Notice”) as soon as the same arises or as soon as reasonably practicable and in any event within 7 (seven) days after the Affected Party knew, or ought reasonably to have known, of its occurrence and the adverse effect it has or is likely to have on the performance of its obligations under this Agreement. The Affected Party shall not be entitled to any relief under the Agreement for or in respect of a Force Majeure Event unless it shall have notified the other Party of the occurrence of the Force Majeure Event.
Notice of Force Majeure Events. (a) As soon as practicable and in any case within 7 days of the date of occurrence of a Force Majeure Event or the date of knowledge thereof, the Affected Party shall notify Independent Consultant and the other Party of the same setting out, inter alia, the following in reasonable detail: the nature and extent of the Force Majeure Event; the estimated Force Majeure Period; the nature of and the extent to which, performance of any of its obligations under this Agreement is affected by the Force Majeure Event; the measures which the Affected Party has taken or proposes to take to alleviate/mitigate the impact of the Force Majeure Event and to resume performance of such of its obligations affected thereby; and any other relevant information concerning the Force Majeure Event, and /or the rights and obligations of the Parties under this Agreement.
Notice of Force Majeure Events. If a Party is rendered unable, wholly or in part, by a Force Majeure Event to perform, that Party shall give written notice detailing such Force Majeure Event to the other Party as soon as possible, but no later than seventy-two (72) hours after the commencement of such Force Majeure Event.