Monthly Schedule Updates Sample Clauses

Monthly Schedule Updates. Each month, XXXX shall submit to Owner for its review an update of the Accepted Construction Schedule. The monthly Schedule Update shall reflect agreed assessments of actual completion reached during weekly meetings. If Owner and XXXX cannot agree, then XXXX shall use Owner’s assessment of actual progress to prepare the Schedule Update. XXXX’x monthly Schedule Update shall include: (a) a diagram showing the target versus actual dates for each activity; (b) an updated critical path method report; and (c) a narrative report that includes, but is not limited to, a description of problems, current and anticipated delays and their causes, impacts of delays, and corrective actions that XXXX has taken or proposes to take to overcome problems and recover from delays. XXXX shall identify any events that will delay the completion of an interim milestone or the completion of the overall Project in the monthly Schedule Update. On Owner’s acceptance of the monthly Schedule Update, it shall become the current Accepted Construction Schedule. Any request for an extension of the Contract Time must be based on the Accepted Construction Schedule. The submission of an acceptable monthly Schedule Update will be part of the basis of the progress payment and shall be a condition precedent to Owner’s obligation to make such progress payment to XXXX.
AutoNDA by SimpleDocs
Monthly Schedule Updates. Each month, CM shall submit to County for its review an update of the Accepted Construction Schedule. The monthly Schedule Update shall reflect agreed assessments of actual completion reached during weekly meetings. If County and CM cannot agree, then CM shall use County’s assessment of actual progress to prepare the Schedule Update. CM’s monthly Schedule Update shall include: (a) a diagram showing the target versus actual dates for each activity; (b) an updated CPM report; and (c) a narrative report that includes, but is not limited to, a description of problems, current and anticipated delays and their causes, impacts of delays, and corrective actions that CM has taken or proposes to take to overcome problems and recover from delays. CM shall identify any events that will delay the completion of an interim milestone or the completion of the overall Project in the monthly Schedule Update. On County’s acceptance of the monthly Schedule Update, it shall become the current Accepted Construction Schedule. Any request for an extension of the Contract Time must be based on the Accepted Construction Schedule. The submission of an acceptable monthly Schedule Update will be part of the basis of the progress payment and shall be a condition precedent to County’s obligation to make such progress payment to CM.
Monthly Schedule Updates. The Progressive Contractor shall prepare and deliver each Monthly Schedule Update with every Monthly Progress Payment Request. For avoidance of doubt, Monthly Schedule Updates do not serve to revise or amend, nor shall be deemed to revise or amend, a Baseline Pricing Package Schedule.
Monthly Schedule Updates. Each month, Contractor shall submit to County for its review an update of the Accepted Project Schedule. The monthly Schedule Update shall reflect agreed assessments of actual completion reached during weekly meetings. If County and Contractor cannot agree, then Contractor shall use County Contractor monthly Schedule Update shall include: (a) a diagram showing the target versus actual dates for each activity; (b) an updated critical path method report; and (c) a narrative report that includes, but is not limited to, a description of problems, current and anticipated delays and their causes, impacts of delays, and corrective actions that Contractor has taken or proposes to take to overcome problems and recover from delays. Contractor shall identify any events that will delay the completion of an interim milestone or the completion of the overall Project in the monthly Schedule Update. On County Schedule Update, it shall become the current Accepted Project Schedule. Any request for an extension of the Contract Time must be based on the Accepted Project Schedule. The submission of an acceptable monthly Schedule Update will be part of the basis of the progress payment and shall be a condition precedent to County such progress payment to Contractor.
Monthly Schedule Updates. On the 15th day of each month, the Contractor shall submit a Monthly Schedule Update using the same software used to prepare the Baseline Schedule. The Engineer will not submit the Engineer’s Monthly Estimate specified in 7-3.2 for processing until the Monthly Schedule Update has been submitted. The schedule may be emailed to the Engineer or submitted on a CD with 2 printed color copies on 11-inch x 17-inch sheets. Should the update not reflect the actual progress of the Work, the update will be returned to the Contractor for inclusion of the changes on the next update. Updates shall conform to 6-1.1.2 and the following:

Related to Monthly Schedule Updates

  • Schedule Updates the Contractor agrees to maintain the Work duration schedule updates on an ongoing basis and, when the County requests it, include the updates in its payment request. The Contractor may be required to submit a narrative report with each monthly update which shall include a description of current and anticipated problem areas, delaying factors and their impact, and an explanation of corrective action taken or proposed. Failure to do so may be considered a material breach of the Contract. Any additional or unanticipated costs or expense required to maintain the schedules shall be solely the Contractor’s obligation and Contractor agrees not to charge the County.

  • Monthly Updates The Contractor must provide the Design Professional and the Owner with monthly updates of the Overall Project Schedule indicating completed activities and any changes in sequencing or activity durations. (See also Articles 2.1.2 and 2.1.5).

  • Service Updates Our Services may automatica ly download and insta l updates to your computer system from time to time and you hereby permit and consent to same. Updates are genera ly developed to improve our Services, including by providing enhanced functionality, bug fixes, and new software.

  • Daily Schedule 1. Double Bus Runs - Teachers shall be required to be on duty a total of seventy-five (75) minutes in grades K-6 and sixty (60) minutes in grades 7-12 before and after the published regular pupil's school day.

  • Monthly Statement The Contractor shall submit a statement to the Engineer at the end of each month, in a tabulated form approved by the Engineer, showing the amounts to which the Contractor considers himself to be entitled. The statement shall include the following items, as applicable; - the value of the Permanent Work executed up to the end of previous month - such an amount (not exceeding 75 percent of the value) as the Engineer may consider proper on account of materials for permanent work delivered by the Contractor in the site - such amount as the Engineer may consider fair and reasonable for any Temporary Works for which separate amounts are provided in the Bill of Quantities - adjustments under Clause 70 - any amount to be withheld under retention provisions of Sub-clause 60.3 - any other sum to which the Contractor may be entitled under the Contract If the Engineer disagrees with or cannot verify any part of the statement, the Contractor shall submit such further information as the Engineer may reasonably require and shall make such changes and corrections in the statement as may be directed by the Engineer. In cases where there is difference in opinion as to the value of any item, the Engineer’s view shall prevail.

  • Shift Schedule The words "shift schedule" when used in this Agreement shall mean a timetable of the shifts and off days assigned to a position or group of positions which commences at the beginning of a pay period and includes one complete rotation of said shifts.

  • Recovery Schedule If the initial schedule or any current updates fail to reflect the Work’s actual plan or method of operation, or a contractual milestone date is more than fifteen (15) days behind, Owner may require that a recovery schedule for completion of the remaining Work be submitted. The Recovery Schedule must be submitted within seven (7) calendar days of Owner’s request. The Recovery Schedule shall describe in detail Construction Contractor’s plan to complete the remaining Work by the required Contract milestone date. The Recovery Schedule submitted shall meet the same requirements as the original Construction Schedule. The narrative submitted with the Recovery Schedule should describe in detail all changes that have been made to meet the Contract milestone dates.

  • Monthly Statements Each month we will send you a statement showing purchases, cash advances, payments, and credits made to your Account during the billing cycle, as well as your “New Balance”, any Finance Charge and any late charges. Your statement also will identify the minimum monthly payment you must make for that billing period and the date it is due. You agree to retain for statement verification copies of transaction slips resulting from each purchase, each advance, and other transactions on your Account. Unless you notify us of a billing error in accordance with the section entitled “Your Billing Rights”, you accept your monthly statement as an accurate statement of your Account with us.

  • Monthly Status Reports 19.1.1 During the Operation Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Authority and the Independent Engineer a monthly report stating in reasonable detail the condition of the Project including its compliance or otherwise with the Maintenance Requirements, Maintenance Manual, Maintenance Program and Safety Requirements, and shall promptly give such other relevant information as may be required by the Independent Engineer or the Authority. In particular, such report shall separately identify and state in reasonable detail the defects and deficiencies that require rectification.

  • Delivery Schedule The scheduled months of delivery of the Aircraft are listed in the attached Table 1. Exhibit B describes certain responsibilities for both Customer and Boeing in order to accomplish the delivery of the Aircraft.

Time is Money Join Law Insider Premium to draft better contracts faster.